After owning a product, I've developed a lot of sympathy for the people outside of engineering who have to put up with us. Engineers love to push back on estima
by notjustanymike 8mo ago
After owning a product, I've developed a lot of sympathy for the people outside of engineering who have to put up with us. Engineers love to push back on estimates, believing that "when it's done" is somehow acceptable for the rest of the business to function. In a functioning org, there are lot of professionals depending on correct estimation to do their job.
For us, an accurate delivery date on a 6 month project was mandatory. CX needed it so they could start onboarding high priority customers. Marketing needed it so they could plan advertising collateral and make promises at conventions. Product needed it to understand what the Q3 roadmap should contain. Sales needed it to close deals. I was fortunate to work in a business where I respected the heads of these departments, which believe it or not, should be the norm.
The challenge wasn't estimation - it's quite doable to break a large project down into a series of sprints (basically a sprint / waterfall hybrid). Delays usually came from unexpected sources, like reacting to a must have interruption or critical bugs. Those you cannot estimate for, but you can collaborate on a solution. Trim features, push date, bring in extra help, or crunch. Whatever the decision, making sure to work with the other departments as colaborators was always beneficial.
- kubb 8mo agoYou're saying it would be convenient for you to know the future. It would also be convenient for me. That said, if you haven't done very similar work in the past, it's very unlikely you'll know exactly how much time it will take. In practice developers have to "handle" the people requesting hard deadlines. Introduce padding into the estimate to account for the unexpected. Be very specific about milestones to avoid expectation of the impossible. Communicate missed milestones proactively, and there will be missed milestones. You're given a date to feel safe. And sometimes you'll cause unnecessary crunch in order for a deadline you fought for to be met. Other times, you'll need to negotiate what to drop. But an accurate breakdown of a project amounts to executing that project. Everything else is approximation and prone to error.
- doix 8mo agoI used to work in the semiconductor industry writing internal tools for the company. Hardware very rarely missed a deadline and software was run the same way. Things rarely went to plan, but as soon as any blip occured, there'd be plans to trim scope, crunch more, or push the date with many months of notice. Then I joined my first web SaaS startup and I think we didn't hit a single deadline in the entire time I worked there. Everyone thought that was fine and normal. Interestingly enough, I'm not convinced that's why we failed, but it was a huge culture shock.
- thebruce87m 8mo ago> I used to work in the semiconductor industry writing internal tools for the company. Hardware very rarely missed a deadline and software was run the same way. Former Test Engineer here. It was always fun when everyone else’s deadline slipped but ours stayed the same. Had to still ship on the same date even if I didn’t have silicon until much later than originally planned.
- doix 8mo agoYep, you and layout folks drew the short straws.
- ozim 8mo agoWhat was the thing you were estimating? R&D? I think you were estimating time to build things that were out of R&D and you had specifications that were actual specifications you were building up to. In SaaS my experience is: someone makes up an idea not having any clue how existing software is working or is laid out, has no specifications beside vague not organized bunch of sentences. Software development team basically starts R&D to find out specifications and what is possible - but is expected to deliver final product.
- ferguess_k 8mo agoI had the same experience when doing an exercise implementing `mmap` for `xv6` -- that was the last lab. There was no specification except for a test file. Passing that test file is relatively easy and I could game it. I consulted the manpage of `mmap` but it is pretty far from a specification, so eventually I had to write a lot of tests in Linux to figure out what it can do and what it can't do (what happens when I over-mmap? what happens when I write back pass EOF? etc.), and write the same tests for `xv6` so that I could test my implementation. Not sure about hardware, but it is really hard to get a clear specification for software.
- xtreme 8mo agoThis aligns with my experience in the semi industry. SWEs tend to see trimming scope as moving the goalpost and do not consider as an option. Providing advance notice is mostly about client management, and clients are often surprisingly receptive to partial solutions.
- chrisfosterelli 8mo agoI agree. Software engineering is basically the only industry that pretends this is professionally acceptable. Imagine if government staff asked when a bridge would be done or how much it would cost and the lead engineer just said "it's impossible to estimate accurately, so we wont. It's a big project tho". Estimating in software is very hard, but that's not a good reason to give up on getting better at it
- piyuv 8mo agoNot a good analogy. Once you build a bridge, it’s done. Software nowadays is never “done”, and requirements constantly change. It’s more akin to building a rope bridge and trying to upgrade it to accommodate cars while it’s in active use.
- chrisfosterelli 8mo agoWhen customers ask when feature X will be ready, they sure have an idea of done in their mind.
- nradov 8mo agoSure, so extract the customer's definition of done as part of requirements analysis process and write it down. Get them to agree in writing, including the explicit exclusion of other things that aren't part of their idea of done.
- PxldLtd 8mo agoSounds like you don't have a good process for handling scope changes. I should know, the place I'm at now it's lacklustre and it makes the job a lot harder. Usually management backs off if they have a good understanding of the impact a change will make. I can only give a good estimate of impact if I have a solid grip on the current scope of work and deadlines. I've found management to be super reasonable when they actually understand the cost of a feature change. When there's clear communication and management decides a change is important to the product then great, we have a clear timeline of scope drift and we can review if our team's ever pulled up on delays.
- bluGill 8mo ago> Trim features, push date, bring in extra help, or crunch. There are problems with all of these. The company knows they can sell X of the product for $Y (often X is a bad guess, but sometimes it has statistical range - I'll ignore this for space reasons but it is important!). X times Y equals gross profit. If the total costs to make the feature are too high the whole shouldn't be done. If you trim features - the affects either the number you can sell, or the price you can sell for (sometimes both). If you push the date that also affects things - some will buy from a competitor (if possible - and the later date makes it more likely the competitors releases with that feature). Bring in extra help means the total costs goes up. And worse if you bring them in too late that will slow down the delivery. Crunch is easiest - but that burns out your people and so is often a bad answer long term. This is why COMPANIES NEED ACCURATE ESTIMATES. They are not optional to running a company. That they are impossible does not change the need. We pretend they are possible because you cannot run a company without - and mostly we get by. However they are a fundamental requirement.
- nightski 8mo agoCompanies need accurate estimates like I need accurate stock market forecasts.
- jungturk 8mo agoThey don't NEED them, but better project estimates can reduce the error bars on other dependent estimates (e.g. estimated sales, estimated ship dates, estimated staffing requirements, etc...), and that might be useful to a business (or not).
- praptak 8mo agoIf your business model needs the impossible then it's a bad business model. If your margins are too thin to absorb the schedule uncertainty then don't produce software. Alternatively treat it like a bet and accept it may not pay off, just like any other business where uncertainty is the norm (movies, books, music).
- Phlebsy 8mo agoI would settle for accurate estimates being a requirement if sticking to the estimate and allocations is as well. Every project I've been a part of that has run over on timeline or budget had somebody needling away at resources or scope in some way. If you need accuracy to be viable, then the organization cannot undermine the things that make it possible to stay on track.
- dorn64 8mo agoIt all starts with sales and marketing cramming every possible feature and half-rumour they heard about competitors' features into a 6 month project deadline. That's a long time, 6 months, no? How hard can it be? Respectfully, it'll be done when it's done.
- replygirl 8mo agowe are the ones qualified to say what needs to be cut to provide reasonable certainty for the deadline. it is not the job of non-technical stakeholders to mitigate risk in technical projects
- CuriouslyC 8mo agoThis is true, but the problem is that engineers are being asked to over-extrapolate given the evidence, and expected to own that extrapolation despite the paucity of evidence to make a good estimate. I *HATE* estimating roadmaps, because it feels unfair. I'm happy to estimate a sprint.
- plagiarist 8mo agoYou estimate your best and then during the project the people who keep changing the spec every two weeks ask why the deadline is slipping.
- SpicyLemonZest 8mo agoIt's definitely unfair in a sense. But companies that make over-extrapolated roadmap estimates from not enough evidence systematically outcompete those who don't, because their customers greatly prefer companies who give a date and then try their best to hit it over companies who say they don't know when the product will be ready for X and you'll just have to wait and see.
- CuriouslyC 8mo agoI get that, and I don't mind giving guidance on roadmaps, it's just the ownership when stuff outside my control goes wrong that bothers me. I shouldn't be responsible for product going in circles on little details with the customer causing req churn, yet I have been held accountable for missing estimates under that exact circumstance.
- fallinditch 8mo agoYes. I took over the project management of a job where the previous project manager had spent a year planning it out, but development had not yet started. The client was furious, understandably. I abandoned the plans from the previous PM and discussed the job with the developer who ballpark estimated that the work would take 2 months. After a quick analysis I adjusted this to 14 weeks. But the account manager thought this sounded too long and insisted that we plug everything in to a Gantt chart, define the shit out of everything, map the dependencies, etc, which showed that the development would only take 6 weeks. The project ended up taking 14 weeks.
- analog31 8mo ago>>>> In a functioning org, there are lot of professionals depending on correct estimation to do their job. A side effect is, no there aren't. Allow me to explain that catty remark. The experienced pro's have figured out how to arrange their affairs so that delivery of software doesn't matter, i.e., is someone else's problem. The software either arrives or it doesn't. For instance, my job is in technology development for "hardware" that depends on elaborate support software. I make sure that the hardware I'm working on has an API that I can code against to run the tests that I need. My department has gone all-in on vibe coding. Customers aren't waiting because the mantra of all users is: "Never change anything," and they can demand continued support of the old software. New hardware with old software counts as "revenue" so the managers are happy.
- nine_k 8mo agoYes, the key part of estimation is not that we need to say how large must be the (time) box to contain the project, but rather how much of a project can we pack into a box no larger than what the business could bear. Hence the separation into must-haves, highly desirable, and nice-to-haves. Hence the need for modularity and extensibility: you if don't get to build everything in one go, and can't always even predict what parts would be left outside the scope, you have more of a lego-like structure. BTW maybe if we finally shook off the polite lie of planning how much work a project could be, and instead started to think in terms of possible deliverables within different time frames, the conversation would become saner.
- davnicwil 8mo agoWith respect, I think this approach is actually harmful to everyone in the org because you're trying to twist reality to fit a premise that is just impossible to make true: that estimates of how long it takes to build software are reliable. The reluctance to accept the reality that it cannot be made true achieves nothing positive for anybody. Rather it results in energy being lost to heat that could otherwise be used for productive work. This isn't about respect between functions, this isn't about what ought to be professionally acceptable in the hypothetical. It's about accepting and working downstream of a situation based in objective truth. Believe me, I wish it were true that software estimates could be made reliable. Everyone does. It would make everything involved in making and selling software easier. But, unfortunately, it's not easy. That's why so few organisations succeed at it. I don't present easy answers to the tensions that arise from working downstream of this reality. Yes, it's easier to make deals contingent on firm delivery dates when selling. Yes, it's easier to plan marketing to concrete launch dates. Yes, it's easier to plan ahead when you have reliable timeframes for how long things take. But, again unfortunately that is simply not the reality we live in. It is not easy. Flexibility, forward planning and working to where the puck is going to be, and accepting redundancy, lost work, or whatever if it never arrives there is part of it. That I think is what people in different functions are best served rallying and collaborating around. One team, who build, market and sell software with the understanding that reliable estimates are not possible. There simply is no other way.
- RaftPeople 8mo ago> you're trying to twist reality to fit a premise that is just impossible to make true: that estimates of how long it takes to build software are reliable. It's not binary, it's a continuum. With experience, it's possible to identify whether the new project or set of tasks is very similar to work done previously (possibly many times) or if it has substantial new territory with many unknowns. The more similarity to past work, the higher the chance that reasonably accurate estimates can be created. More tasks in new territory increases unknowns and decreases estimate accuracy. Some people work in areas where new projects frequently are similar to previous projects, some people work in areas where that is not the case. I've worked in both. Paying close attention to the patterns over the years and decades helps to improve the mapping of situation to estimate.
- subprotocol 8mo agoI think the hardest part of estimation often gets glossed over: genuine technical unknowns. Not "we didn’t think hard enough," but cases where the work itself is exploratory.
- lubujackson 8mo agoI agree whole-heartedly with the source article as well as this comment. The point is that the work of estimation is most of the work. We can have better estimates if we break things down to bite-sized chunks, but "when will this be done" is largely impossible and comes down to many external factors. Laypeople understand this implicitly in other contexts. My favorite metaphor is building something like a new shopping mall. If you ask for an estimate you first need to architect the entire thing. This is equivalent to breaking down the task into sprints. In most companies the entire architecture phase is given very little value, which is insane to me. Once we have our blueprints, we have other stakeholders, which is where things really go off the rails. For the mall, maybe there is an issue with a falcon that lives on the land and now we need to move the building site, or the fixtures we ordered will take 3 extra months to be delivered. This is the political part of estimating software and depends a lot on the org itself. Then, finally building. This is the easy part if we cleared the precursor work. Things can still go wrong: oops we hit bedrock, oops a fire broke out, oos the design wasn't quite right, oops we actually want to change the plan. But yes, estimates are important to businesses. But businesses have a responsibility to compartmentalize the difference. Get me to a fully ticketed and approved epic and most engineers can give you a pretty good estimate. That is what businesses want, but they consider the necessary work when they Slack you "how long to build a mall?"
- mikepurvis 8mo agoI've also seen it argued that real world estimates for things like construction projects are so good because 99% of it is do-overs from similar projects in the past; everyone knows what it takes to pour a column or frame a floor or hang a beam. Whereas with software most of what was done previously is now an import statement so up to 80-100% of the project is the novel stuff. Skilled leaders/teams know to direct upfront effort toward exploring the least understood parts of the plan to help reduce down-stream risk but to really benefit from that instinct the project plan has to regularly incorporating its findings.
- nradov 8mo agoReal world estimates for construction projects are often way off. Especially for remodeling or renovation of older buildings, where the most serious problems can remain hidden until you get into the demolition phase.
- nradov 8mo agoThe most effective approach that I've found to prevent delays in large scale software projects is to carve out a dedicated team to deal with critical bugs, L3 support tickets, and urgent minor enhancements. Don't count them in capacity planning. They serve to insulate the feature teams from distractions. Rotate those assignments for each project so that everyone takes a turn.
- boltzmann-brain 8mo ago> who have to put up with us this kind of (self-)deprecation is exactly the kind of thing that makes it impossible to be happy as a technical person in a startup
- 9rx 8mo ago> "when it's done" is somehow acceptable for the rest of the business to function. Well, it is the truth. It won't be done before it is done. It is understandable that there is a business that needs to function, but the issue here is the question of asking for an estimate like you've already solved the problem, instead of actually sitting down with the engineer to discuss the business problems that need to be solved. That's what engineers are there for: To solve business problems. Estimates are irrelevant as the solution will be designed with the business constraints in mind. > it's quite doable to break a large project down into a series of sprints This too comes across like the problem is already solved. You don't need to break problems down into sprints. That is a ridiculous way to operate. This kind of thing only shows up where there is some weird effort to separate engineers from their jobs. In fact, "sprint" comes from Scrum, which was designed to be a transitionary exercise to get engineers more comfortable with Agile, which is all about removal of managers. It is intended to teach engineers to think and act more like managers so that when you get rid of the managers completely that they don't flounder. If you are doing it as more than a temporary thing, you've entirely missed the point.
- mgfist 8mo agoThat's why the right way to do it is to have a hard deadline given to engineers, then the engineers cut whatever scope is needed to actually wrap something up by the deadline
- steele 8mo ago"us"