Story points are pointless, measure queues
- quantified 2y agoStory points were only ever an approximate unit of time. To fit them into a clear unit of time such as a sprint is a clear indicator of this. To call them complexity or anything else is misleading- transcribing a dictionary by hand into a CSV file is super simple (1 pt) and takes a long time (how many points is 3 FTE-months in your calibration?). Eatimating effort-time vs completion time are quite different, serving different stakeholders. A story that takes 1 point of effort by anyone's pointing system could still take a week due to any number of factors (crucial collaborator gets sick, laptop crunched by a car, ransomware attack, whatever). The only really estimable aspect is how long the developer will spend on the work, not when it will be done. Air speed, not ground speed. That said, it's not clear how queue analysis helps when you haven't spent any time saying how long you might expect each task in the queue to be, or what the dependencies are between tasks within and across teams. Given engaged team members, I've gotten very good results on predicting the pace of progress for sprints, and it all never mattered because everything needed to be shipped. About 4-6 weeks before each X was to be completed we could say with confidence that X would be ready in 4-6 weeks. Not terribly useful.
- bboygravity 2y agoI just don't get what the new terminology is for. Like how is this helping anybody? Manhours = story points Task = story Subtask = sprint Upcoming tasks = backlog Task turn around time = ?? Project goal(s) = epic(s) I'm probably not even doing this right, but what are we doing here anyway?! It gets real fun when the project involves software/firmware + mechanical engineering (think machines, robotics, etc), gotta love their faces when you teach them the special magic advanced project words for special software people.
- drewcoo 2y agoThe idea was to not use direct measures of time to estimate because someone above you will start assuming those estimates are promises and then life gets unpleasant. Story points, much as I personally dislike them, were invented for developer defense.
- bboygravity 2y agoThere has always been a perfectly fine word for that which means exactly the same thing: man hours. I remember learning in school (way before the hocus pocus fancy new words came out) that the development of an Intel CPU cost around 1000 man-years. I don't understand how expressing this as "it took 1000 kilo-story points" or whatever would bring any advantage whatsoever.
- usea 2y agoI've never seen such systems emerge from the team as a tool for self-empowerment. They are always foisted upon the team by managers who are trying to, ultimately, turn estimates into promises.
- dennis_jeeves2 2y ago>I just don't get what the new terminology is for. Like how is this helping anybody? The corporate world likes to come up with new terminology for old stuff and brands it as some new profound discovery. The result being that the new young generation of employees believe that they are living in a new enlightened age (bestowed by their corporate overlords) compared to their older counterparts who were living in the intellectual un-enlightened, dark ages.
- IanCal 2y agoThe broader point with all this is every field comes up with jargon because it's a form of compression rather than repeating the same phrases again and again. The differences between what you've written there and how they've been used in the teams I've been in are the point here. Instead of saying "manhours but with a conversion factor that we figure out over time and an understanding of the variation" you say "story points". Story points aren't hours. People are really bad at estimating with time, but they're much better if you just get them to compare things and say which one seems like it'll take longer. Stories aren't tasks, either. A task is a single unit of work that you can do and complete. Stories are groups of things that solve a particular problem. For example, adding a password reset is a story. But that might be distinct tasks that different people can take on, or should be coded and released independently. Maybe that requires setting up an email service or server, UI changes in the frontend, backend changes, is there design that needs doing for it, etc. > Subtask = sprint Sprint is a bit of a weird one sure but it's a short length of time. Different for different teams, typically 1-4 weeks. > Upcoming tasks = backlog Backlog isn't a very custom term here is it? Also it's not the upcoming tasks, it's things that probably should be done but not right now. New idea? New feature? Cool, backlog, doesn't interrupt the current set of work for the next couple of weeks. Every field can do this with every other field. Doctors with their fancy words like anterior, why don't they just say "the bit at the front"? I know there can be cringey project managers, yes. On the other hand, I've also seen highly skilled engineers scoff at these kinds of things then spend way too long building stuff that doesn't actually address what the user needs, misses out key parts because they never thought about who was actually tracking those ancillary pieces of work and making sure they're done, and fail to deliver. Oh and finally if someone wants to come along and say "well we did it differently", if that worked for you then great! The classic point of agile was that you should try things and keep what works. None of these concepts are particularly complex imo.
- ozim 2y agoBut you have !sprints! and if you have laptop crunched you either have other dev taking over - so something else doesn't get done - or story that dev with crunched laptop is not going to deliver. That's just life and I also understand how disconnected management can be - but a lot of time you cannot say "exactly" when something will be done, because that is just not possible.
- dilyevsky 2y agoAll of these shenanigans are just dancing around the intractable problem which is - nobody ever figured out a way to produce reliable estimates.
- skydhash 2y agoThat’s because you’re dealing with a pile of abstractions on top of the cpu, data storage and channels that connect them all. You’re perched on top of the babel tower trying to figure where to put the next stone without everything crumbling around you. And you don’t even know the shape of the stone. You only have a vague description of it. Just too many unknowns.
- parasense 2y agoAlso, the whole thing about "velocity" is just weird. It's as if some marketing goon heard the word "Velocity" and decided to over load the term in a manner that does not mean Velocity in the mathematical sense. Like in Calculus... the velocity curve is the first derivative of the linear graph, and the accelleration curve is the 2nd derivative. And for that matter, who cares about velocity, we have always wanted accelleration which sorta yields velocity. The problem with velocity, it's a dumb idea, because if I drop a rock from a tall building, it builds velocity as it free-falls down, and so it goes -- you have differetn kinds of velocity, but you only really have one kind of accelleration. Another issue, as the blog points out, story points are a simple scallar number, and you cannot easily say how that sum is factored into risk, complexity, effort, etc... So why even have it? Clearly a story needs to be a kind of vector with these properties (risk, complexity, effort...) set to possitive or negative values, and then do the typical vector math to plot the dirrection and magniture of the story in the n-dimensional space... Then, one can actually calculate stupid ideas like velocity or accelleration to speak in the language of project/program managers. Ultimatly the managers need a way to quantize the units of work done by development staff to better plan, and that's understandable, yet really hard. I think putting the cart before the horse is usualyl a dumb idea, and things should go back to measuring performan after the work is done, instead of estimating performance before work begins. Nobody wants to commit to a performance contract for each and every task ad nausium, and thats what happens durring sprints.
- adversaryIdiot 2y ago[flagged]
- andrewstuart2 2y agoStory points aren't time (as OP states). They're relative complexity, and uncertainty (hence the fibbonacci sequence building uncertainty in to larger numbers). And stories should be able to sized as big numbers. I've never been on a team comfortable with more than a 7, at least not since my first agile experience where we all took an agile/scrum training together for a few days. We'd frequently give things like 21 or 30 or 50 points, as appropriate. That's the only place I've ever seen a burndown chart that looked like it should. Everywhere else, it's flat until the last day and then drops to zero as all those "it's a 7 I promise" get carried over to the next sprint for the 3rd time.
- ozim 2y agoI agree - just countless times I have to beat that up into peoples head and even people who I would consider smart "points <> time". After the sprint you can kind of infer the time but it should not be guideline for next estimations unless these are tasks like "fix typos".
- throw310822 2y agoIf they're not time, why use numbers? Use fruits: easy peasy, it's a lemon. A really tough story, a coconut. You can't add them in any case, because they're not time.
- ozim 2y agoThat is one of the complications - one thinks developers should be smart as in abstract thinking so they should understand (just like all the other numbers humanity made up): "numbers we call story points are not having property to add them and they are not convertible to time". *Properties of Whole Numbers: Whole numbers are closed under addition and multiplication. Zero is the additive identity element of the whole numbers. 1 is the multiplicative identity element. It obeys the commutative and associative property of addition and multiplication. It satisfies the distributive property of multiplication over addition and vice versa. *
- jf22 2y agoI've personally had great success with story points. Success with story points comes when everybody realized they are useless for anything outside of a dev cycle and when you realize that the effort into making them somewhat accurate is the valuable part.
- deleted 2y ago[deleted]
- KothuRoti 2y agoMy personal experience with story points is that the number never really mattered, but the process of the team discussing how to rate the complexity of a task was very useful. In terms of having utility of estimating how long something will take, I personally have never been able to translate story points into a reliable indicator for that for many reasons (e.g team changing, domain changing, variability in operational load outside of development work). Overall I tend to avoid using story points, but on the few teams I worked on who really wanted to use it, I always framed it around building shared understanding rather than a metric that is actually useful for estimating work.
- bsder 2y agoIn addition, I like the whole "Full Queues Amplify Variability" chart. It's intuitively obvious, but I never realized it was that bad. I'm going to have to run that down and see if it's actually backed by real data. Too many business books are complete flimflam.
- buescher 2y agoReinertsen's books are very, very good. The most recent and most up-to-date is Principles of Product Development Flow, which that chart came from. The previous one, Managing the Design Factory, is pretty similar and I think it's a better read. Another great takeaway from it is to prioritize things by cost of delay, or even better, what he calls Weighted Shortest Job First, where you divide the cost of delay by the expected length of the task. The only problem is that the same people that want to get oddly formal and inappropriately rigorous with things like story points will want to turn cost-of-delay into an accounting exercise - or object that it's impossible because they don't have the accounting system for it - which misses the point entirely.
- d_watt 2y agoI'm not sure I agree with the framing of this article. It seems to be comparing two different things, 1. Points as a method for attributing difficulty to a work item, vs 2. The collaboration process of creating a task list as a method of breaking down work. Running a team, I found pointing useful, more useful than the individual line engineers did, as we had different goals. My goal, in optimizing the team, was to go through all our work, get everyone in a room and create a relatively optimal plan for the next couple of weeks. By going through the exercise of pointing, we often found that something one person thought was hard, another found easy. That act of estimating would reveal knowledge one person had that another didn't, that made the task easier. Without that process, the work might have been harder do do, because the easy way was never revealed. We also adhered to a 8 points is too many philosophy that meant any item that hard needed to be decomposed to simple tasks to repoint. The "queuing" section basically implies the planning process should decompose tasks all the way to nothing but 1 point stories (or at least similarly sized work items within some variance). It's basically the same process as pointing, except not calling out some things are chunkier than others because it all comes out in the wash. TL;DR this articles definition of queuing is basically pointing where task = 1 point items.
- ravenstine 2y agoWe should be thankful that it's commonplace to use points instead of units of time like days even if points are horseshit. Estimates aren't that useful most of the time, and the last thing I would need is a manager telling me they're concerned because my ticket took 3 days instead of the two that the whole team estimated.
- ooterness 2y agoAs someone looking at algorithms for managing buffer bloat, this resonates. In IP routers, the goal is to keep the congested link busy. i.e., Idle time from a momentary hiccup is wasted time. You need a small buffer to do this, but piling on more data adds latency without actually doing any good. Algorithms like CoDel realized that a lot of previous attempts to make this were noisy as heck. Minimum latency through the queue is the signal that makes sense. Everything else is misleading or gives inaccurate predictions. Why should it be any different for managing tasks for human workers? [1] https://en.wikipedia.org/wiki/CoDel https://en.wikipedia.org/wiki/CoDel
- mikeocool 2y agoGiven the size of my scroll bar, I rate reading this article a 13. My PM has decided I shouldn't bother reading it, as the likely value isn't worth the effort, because whenever we take on a 13, it ends up dragging on for like 4 sprints, and preventing a lot of other higher value/lower effort stuff from getting done. Maybe at some point in the future, we'll break the article and have a few people on the team each read it part of it for lower effort, and then synthesize their take aways.
- brightball 2y agoTotally get it. :-) I did include a helpful TLDR near the beginning with the highlights though.
- choppaface 2y agoI found the tldr really confusing and next-to-useless. It’s a really really long article and I just wanted to read about queuing since yeah story points can suck.
- brightball 2y agoI’ll see what I can do to improve it.
- jurassicfoxy 2y agoThis article was not written for the reader, but written because the writer loves to hear himself write.
- josiahpeters 2y agoI feel personally attacked by this comment. This hits so close to home. I think I have some personal reflection to do.
- deleted 2y ago[deleted]
- egeozcan 2y agoStory points are pointless on their own, but estimation meetings are invaluable. In those meetings, story points serve as shortcuts for expressing gut feelings. However, after the meetings, they become completely useless, and even harmful, because, as the article mentions, people start treating them like precise numbers and do arithmetic with them.
- andirk 2y agoMuch like one huge difference between string "42" and the number 42 is that the latter can have math done to it. If you want to avoid the arithmetic, label tasks with words like "simple", "small", "quick", or my favorite "Won't fix".
- egeozcan 2y ago> Much like one huge difference between string "42" and the number 42 is that the latter can have math done to it I actually agree with your comment but this part made me laugh out loud because JavaScript :) ("42" - 1 === 41 but "42" + 1 === "421")
- andirk 2y agoGood ol overloading of the + operator at work there
- steveBK123 2y agoStory points are UBI for Product Managers
- einpoklum 2y agoBut my managers say I have to allocate story points! I'm sure they know what's best and not just making me jump through hoops because of their artificial imposition of JIRA under the title of being supposedly "agile"! Right?
- xn 2y agoEstimate using time (hours, days, weeks, months, years). Reflect your uncertainty in your estimates using confidence intervals. If your confidence intervals are too wide, break down the work and estimate the smaller tasks and/or spend some time doing the work necessary to narrow your confidence intervals.
- psychoslave 2y agoI can estimate rather accurately how much time it will take me to cook a meal assuming that: - I already mastered the receipt as I prepared the very exact same one many times in the past - I already checked that I have all the ingredients required at hand - I will cook in my own kitchen - no entropy engine (aka family members) was thrown before in the kitchen to put utensils in an other place than the place were I tidily store them (admittedly without conducting formal formation of the rest of the disruption forces) - no one will interfere because the way I do it is not the super fancy other way in which it could also be done - no external catastrophe happen which obviously need to be taken care of immediately, just at this point in recipe where by the time I will come back most of what I did so far will be better started again from scratch because the underlying laws of physics I was assuming so far changed so significantly that the left ongoing work is now utterly incompatible with the divergences that universe bumped to Meanwhile, in the easier transparent stationary landscape of software development, whenever I came with a to-my-mind-credible estimate for a non trivial endeavor, it was systematically rejected and superseded by a soon-to-be-blown-away deadline.
- psychoslave 2y agoI find the requirement to give a note together is a good insensitive to stay focus on what the topic is, try to grab it, ask questions to start to put some lights on the biggest dark corner of the task. I couldn't care less about the resulting quantification. What matter is how well we communicate in the team, how helpful we are with each other, how well we can progress and keep motivation where struggle with huge hindrances paving the way. The points are not the point, but they are not pointless. The map is not the territory. Everyone can have a different map and a different metric system if any. If at the end of the day people inhabiting the territory do it in a satisfying way, all good. It doesn't matter much what the plan on the paper might look like: it will always be a mere epiphenomenal artifact of the actual human processes at play.
- Unknoob 2y agoStory points are in fact time, and I'm tired of pretending they're not. You can sugar coat it all you want and say they represent complexity, but at the end of the day(or sprint), the higher the complexity, the more time it takes to complete.
- herpdyderp 2y agoThe problem therein is that that time depends on who is given the story. Perhaps that should be part of the estimation itself? (Who is working on it.)
- nucleardog 2y agoFixing the machine at the factory can be quite complex, but you might have a technician in and out in a day or two to get it done. Assembling 5,000 identical widgets is not complex, but it might takes you weeks or months. Complexity and wall time occasionally move the same way on the graph (generally with wall time climbing much faster than our view of complexity), but they’re not necessarily or always so. I tend to explain “complexity” more in terms of “at what skill level of employee would we stop seeing substantial gains in quality/speed/maintainability/etc when we assign this work out”. Something that a senior could do substantially better/faster than an intermediate is “high” complexity. Something that the intermediate could do substantially better/faster than the junior is “medium” complexity. Adding some fields to a form is low complexity—an intermediate or senior won’t do a substantially different job than the junior—but doing 10 fields versus 100 fields will change the amount of time it takes quite a bit. Architecting a new service will see gains to senior and beyond and is high complexity but may not actually take all that long. Ultimately, this boils down to “how many decisions remain to be made”. Most tasks can be made lower complexity by making those decisions in detail. “Rearchitect this module” becomes medium complexity when someone turns that into “rearchitect this module following X pattern” and low when someone turns it into “move methods A, B, C into new class X and split method D into E and F along this line”. This view of complexity doesn’t directly drive wall time, but _does_ very directly impact the variability of that estimate. The more decisions remaining and the more unknowns up front, the wider the range of possible outcomes. Reducing the complexity will reduce the range of estimates.
- 2y ago
- tetha 2y agoThe article lost me at a certain point, somewhere around the "solving the conondrum". It lost me, because we have two estimations - an overall size guess of an epic and an actual implementation estimation of an epic. Like the overall size guess is just 2-3 seniors looking at an issue and wondering if this takes days, weeks, months or years to implement. The actual implementation discussion is however what the article is talking about. We get most or all of the team into a meeting and we talk through what needs to be done, and structure all of that into individual concrete tasks everyone can have an idea of implementing them. And then we estimate those tasks. And this estimation in turn is communication to management. Like, we've realized that about 21 is what one of us can do in a usual monthly iteration outside of massive outages and such (we're an operational team). So if an epic turns out to require some 3 21's and 3 13's... that can easily take 6-12 months unless we put exceptional focus on it. With high focus... as a team of 4-5, that will still take 3-6 months to do. On the other hand, something that falls into a bunch of 5's and 9's and such tends to be muddled and struggled through regardless of whatever crap happens in the team much more reliably. It needs smaller chunks of overall attention to get done. And note that this communication is not deadlines. This is more of a bottom-up estimation of how much more or less uninterrupted engineering time it takes to do something. A 21 in our place by now means that other teams have to explicitly make room for the assigned person to have enough headspace to do that. Throw two interruptions at them and that task won't happen. It's more bin-packing than adding, tbh.
- jordanmorgan10 2y agoOr just lose Agile altogether
- xyst 2y agoSo basically a “kanban board” with priorities attached to each unit of work. Gotcha
- bb88 2y agoThis is a problem from a management perspective, not a developer one. Story points are usable, but they're a "Wild Ass Guess" metric, not a true metric of actual work, and treating them other than a guess is fraught with problems. A 13 point story could fall somewhere between 8 and 21. Some stories we guessed 8, and ended up being more like 21 (because the dev had to fight unexpected politics, or the API was billed as being "easy to use" but anything but.) All these are fine and should be fine to developers, except to management.
- 23B1 2y agoProject Management should be called Project Leadership, and the tools of the former should inform – but not dictate – the decisions of the latter.
- lmm 2y agoThe post is correct about some problems but completely wrong about solutions. Breaking down tasks that are already sub-sprint-sized in a meeting is the wrong way to do it; you'll put the boundaries in the wrong place and end up duplicating work, and then going overtime when the integration stage takes longer than you thought it would. The right place to do that breakdown is agile, just-in-time: give one person or pair/mob responsibility for a piece of user-facing functionality (that they've already agreed is sub-sprint-sized) and let them do whatever breakdown makes sense for that. If they get confused or stuck they can always raise it in standup (that's why we have them!). Similarly: > What happens when the team has turnover? What happens a few months down the line when this work comes back up based on the points that were given previously? Why would you ever put points on it a few months ahead of time? You do estimation in the sprint planning when it's a candidate for that sprint. There's no need to write down the reasoning for the estimation because the estimation is only relevant for the duration of that meeting (as you prioritise stories for that sprint), and maybe in the retrospective two weeks later if the estimate was way off. I can see the argument for t-shirt sizes. The "queue" idea is the opposite, and has all the problems of point/time estimation. > When anyone not directly involved with the project asks why it's taking longer than they thought, the answer will be spelled out in the tasks list. These changes were added on these dates, for these reasons based on this feedback from these people. There is no "your estimate was wrong" situation. There is no "re-estimating" process. There's not even an ask to approve if you can change the point value. It just happens. Guess what? They're going to ask for dates. They're going to ask why the estimate changed, and not care about the answer because they just want to blame you for their estimates being off. And your "tasks" have just become the same time tracking that you were (rightly) scared of; you have the same problem of having to do a bunch of pointless busywork to justify that you were actually working. (Suppose a "task" is suddenly twice as complex as you thought it was; now you've got to file a second "task" with a fake description to justify why you only did 3 tasks this week when Bob did 4). The problems the article identifies are: spending too much time and effort on estimation, estimating too far in advance (and then having the team and/or circumstances change), and treating estimates as deadlines. These are all real problems. But they're not problems with story points (indeed story points are actively helpful on the last one, since everyone has to at least pretend to admit that story points are not time estimates), and they're just as easy or difficult to solve whether you use story points or something else.
- jmward01 2y agoThe fundamental issue isn't addressed but it sure is hinted at. Scheduling is an NP problem. As queue size, or backlog, or (insert thing here that tracks work to be done) grows it takes n^p calculations to schedule it optimally. This is hit on when it mentions small teams hitting their estimates. They can do this because their task list is small enough to go through all the permutations and actually come up with an accurate estimate. The only way to keep an n^p problem under control is to divide and conquer it. The leafs of that process must not go beyond a fixed size and the task divisions can't be recombined prematurely. Everything else is just yet another management idea that that will fall apart when the task has too many pieces. Once agile or any other management methodology acknowledges the fundamental mathematics at the core of things I may actually take them more seriously.
- T-zex 2y agoWhat stops management from committing Feature A to be delivered after 250 tasks are completed? Yes the fact and the reasons that the Feature A expands to 500 will be documented, but who will care about it? This will still be a "delay" from the management point of view.
- wombatpm 2y agoTo quote Douglas Adams: I love deadlines. I love the whooshing sound they make as they blow past.
- JohnMakin 2y agoStory points are a useful exercise when trying to discuss complexity of a task but IME it completely falls apart when used as a metric to determine anything useful like velocity. I had a terrible experience with them once. I was a relatively new, enthusiastic engineer on a struggling team of guys who'd been at the company a long time and were pretty burnt out. Inevitably I started getting all the "hard" stories with a lot of points, til it got to some stupid point where I was outputting about 80-90% of our team's combined story points. Management caught wind of it, didn't like it, so what they decided to do was adjust my points "downward" to be more in line with the rest of my team's output. It really irritated me, because it'd result in absurd situations where my teammates would get a "3 point" ticket that was like, just updating some field in a config file to an already-known value and checking it in somewhere, and I'd get this whole-ass project wrapped in a single ticket and they'd give me the same amount of points for it. And of course this was tied in to performance reviews, adding to how annoying it was. Another super irritating thing that would happen is I'd be asked to estimate complexity on some super vaguely defined ticket describing some problem that would take a lot of detective work to even figure out how to solve, so how am I supposed to give an accurate estimate of complexity? If I knew that much, I'd already have probably fixed whatever the issue was.
- fallinditch 2y agoI think some of the problems and issues we're discussing here derive from confused project management methodologies that call themselves 'agile' yet require detailed estimation, measurement and reporting of task timing. Story point allocation can be useful to give a quick and easy 'good enough' estimation of time/effort required for a significant chunk of work (epic). I find that this approximate approach is almost always more accurate than trying to estimate every little task. If the project manager and engineers try to break down a project into small granular tasks with time estimates then it's almost inevitable that the effort will be underestimated because it's virtually impossible to anticipate every sub task, blocker, unforseen delay, etc (and then there's the extra time it takes to manage all these micro tasks in your PM system!). In such situations the old project manager trick of doubling all estimates tends to provide a more accurate timeframe. This is why story points can be more accurate: because you are estimating the effort it takes to do something relative to your previous experience of similar workloads. So, if you avoid estimating granular tasks and keep your estimates as the approximate amount of effort relative to something you've done before, then you will end up with a more realistic timeframe. Story points can help with this mindset. Also your team will not have to waste time faffing around in Jira too much, or whatever system you use.
- rerdavies 2y agoThe value of story points is that it acknowledges that not all stories are equally time-consuming. Importantly, story points also provide a process for identifying stories that should be further decomposed. In my experience, story points allow forecasting that's as good as any forecasting method I've ever used. And I've used pretty much every schedule forecasting method over my long career. The author touches on many of the reasons why story points don't work. And pretty much every reason he gives is something that you are not supposed to do. The key to getting them to work is trust, and a commitment to never use story points as metrics to measure the performance of developers. Any attempt to do so will result in gaming of the system. The tradeoff that stories provide is lack of precision in exchange for not having to spend 50% of your development cycle up front doing detailed analysis required to provide detailed estimates (which never worked anyway). Things you must also never do: - compare calibrated burndown factors between teams. - Ask why the calibration factor isn't N. THe calibration factor is. - Have stories with more than N story points (where N is 3 or 5). Decompose them. - Introduce the least bit of stress. - Use burndown rates to generate commitments, instead of forecasts. - Use forecast results to justify asking developers to work overtime. The last point, I think, is particularly interesting. The manager who was my first scrum master made the following commitment to us: you will never work overtime again. And voluntarily working overtime will be consider a bad thing, not a good thing, since it impairs predictability of the team's productivity. "I know you don't believe me", he said. But he was right. We never worked overtime again.
- rerdavies 2y agoCould somebody explain how queue theory fits into agile processes? Where are these unmanageable queues, that need to be emptied coming from? Queue theory only becomes a problem when (1) stories are being added to the active story queue at a furious rate; and (2) nothing gets shipped until the active story queue is emptied. I don't think think either of those things are supposed to be true in an agile process, especially the last. It sounds suspiciously like a symptom of gamification to me (if new stories are being added by the development team). Or a broken process where field defects (which are supposed to go to the top of the queue) are so numerous that they completely overwhelm active development, which is an entirely different issue, requiring an entirely different response from management. If story points are so wrong that it no longer fits in a sprint, it seems reasonable to split the story. In my experience, I don't think I've seen it happen more than a handful of times. How often is an initial story point estimate so wrong that it has to be revised upward to the point that it no longer fits in a sprint? If it's wrong, but still fits in a sprint, just do it. It makes me wonder whether there's gamification going on around using story points to evaluate developer performance. (Assuming that stories are converted to tasks at the start-of-sprint meeting).
- sithlord 2y agoIn my world, on my team - everything is a 3. and if its not a 3 lets figure out why. IE, lets have a fairly sized piece of work we scope for most tickets. If its bigger than that, lets discuss it, see if its worht breaking down (if its larger) and if not lets just agreee thats a larger piece than 3. that way we can just keep an eye on relative size of issues.
- ecshafer 2y agoMy team doesnt really have story points. But we work kind of similar to you: is this too big? If it is, lets see if we can break it down to smaller tasks. I think it works much better than arguing over story points.
- andrewflnr 2y agoThat's pretty close to what the article is describing, if I understand it right. They functionally define "tasks", the ones put in the queues they suggest measuring, as bits of work small enough that most of the uncertainty is gone. So until that's proven wrong (when reality smashes a task into a bunch more tasks), it's more-or-less equivalent to all your stories having the same number of story points.
- aetherspawn 2y agoI am reading this slowly and there’s some good stuff in here, but it’s really long and I don’t have 1-2hrs to sit down and read it properly. I liked the suggestion of having a dedicated architecture team to break things down into work items. Comment your favourite parts/highlights?
- brightball 2y agoI struggled with the length but couldn’t find a good way to shorten it more unfortunately. That’s the main reason I included a TLDR. Thanks for giving it your time though.
- andrewflnr 2y agoYou could trim down the parts dunking on story points a lot. It starts to feel redundant and most of it is dubiously relevant. If we care about the topic at all, we probably already have an idea of what story points are and what's wrong with them, and are mostly interested in your proposal to replace them. You only need to refresh our memory about the existing system, and maybe link to other critiques.
- brightball 2y agoFair critique. I was mostly trying make a thorough case first. I’ll definitely have a followup focused more on queues.
- jmull 2y agoI’ve never had a problem estimating projects using time units.
- iampracticising 2y agoDon’t the tasks in queues have the same issues with the tasks from story points do? What if the tasks are not defined well enough? So some tasks in the queue might take a day to complete, another could take months?
- eksx 2y agoA task that takes months is a project. I view tasks as something I could get done in one day with full focus. Then at the 2 day mark I reevaluate. The additional day can always act as a buffer.
- wsc981 2y agoJust estimate time. In the end, whenever I worked with story points in various companies, even though developers, Project Managers or Scrum Masters would often state that Story Points are a measure of complexity, in the end, the Velocity for a given sprint was measured in Story Points as well. So, in the end a Story Point is equal to an amount of time in a sprint. This is also stated in the article: > Story points do not represent Time, yet the Velocity metric they are usually combined with defacto converts them to time, sabotaging everyone from the start by doing the thing that you can't do with a precise number and a range...adding them together. Better yet, just don't bother with SCRUM and all it's pointless and time-consuming ceremonies and just get shit done. This is my preferred mode of working and I've been lucky to be able to work like this for the last couple of years.
- happytoexplain 2y agoI disagree with the first part. The only thing less useful than estimating points is estimating hours.
- stanislavb 2y agoIf story points convert to "hours"/"days"/"time" in the end of the day, why is estimating in time less useful? Asked in another way - why is it more useful to estimate in an unit that's more abstract/distant-from-reality?
- XorNot 2y agoI mean I agree, but it's because you should estimating in days. No task significant enough to warrant a ticket in a queue and design effort takes less then a day. Even if you you swear it's "done", the more likely outcome is you'll be dealing with it for hours later that week when some sort of an issue crops up. I've seen so many people "bid" 0.5 and 0.25 day units of time (in points or whatever) and then act offended when I challenge them on that, yet 3-4 days later they're still plugging away at the same task due to "complications".
- kelnos 2y ago
- al_borland 2y agoWhen my company first started using Scrum it was with Rally. It had story point, but also estimated time and actual time. We used them all, and I found the estimated and actual time to be the most useful. We then went to Jira, which kept the points and dropped the time. Since we were tracking the actual time things took as well, our estimates got better over time. The team would help to keep others honest. For example, writing documentation always took at least 3x longer than anyone expected, so we’d alway make people add more time to those stories. Once we had reasonably accurate time estimates, there was also a feature for available hours. If someone was on vacation, we’d subtract those hours while planning the sprint. It was then easy to see who was over committed, balance the work, and to make sure we were being realistic. We worked like this for about 2 years. It was probably the best 2 years I had in the job. We got a lot done, we were being strategic about our work rather than reactive, and while we would push to get things wrapped for the end of the sprint and the demo, it never involved all nighters or heroics. We pushed because people on the team wanted to do more and go faster, not because of pressure from the outside. I noticed people got more down when they tried to do less, so I’d often push back on people trying to overload the sprint. If they finished everything, we could always add more. Outside the team, our VP told us we were 3+ months ahead of everyone and if I wanted to go hang out in a cafe in Europe for a few months, go. This is all a distant memory now. So many lessons learned, but they all fall on deaf ears in the current organization.
- kelnos 2y agoUgh, yes, thank you. I wish management types would get it through their heads that you just cannot reliably estimate most software development projects. (I said "most" -- there are of course exceptions.) You can't evaluate employee performance by looking at a burn-down chart. You can't show pretty graphs at the end of every sprint and expect that to predict the future of the project. What you can do is set a reasonable deadline with your team, have them work toward it, and allow them to adjust your expectations on what exactly you will be getting by that deadline. Yes, establishing that deadline in the first place requires some sort of estimation, but story points, t-shirt sizes, etc. are useless for that. Everyone on the team sitting down, breaking things down into as-small-as-possible tasks, and coming up with time ranges for each task is the way to do that. Then you add up all the minimums and maximums and you have a time range for the whole project. But that range is still only a guess, and can't be taken as gospel. And it may be wild, like "somewhere between 6 weeks and 6 months", and you have to accept that. That's it. That's the best you can do. As the project carries on, the only thing you can reasonably report on is the list of features or functionality that's been implemented so far, and the new range of the estimate based on what's remaining to do. You can also look at the completed work, and map out where in the per-task estimate range the team ended up hitting, but that still can't predict the future. You especially can't evaluate performance based on this stuff. That requires being an involved (but not micro-manager-y) manager who knows the team and can identify when their people are shining bright, and when they are struggling (or just slacking off). It's called people management for a reason; you have to involve the humans in that process and can't evaluate them based on some made-up numbers and dodgy, hand-wavy math.
- Terr_ 2y agoI've always thought of story points as ideally* working like a kind of international currency exchange, where it is normal and expected that Team Teal Dollars will not have any permanent or consistent relationship to Team Maroon Doollars nor to Actual Time. (The saying "time is money" notwithstanding.) The points will inflate or deflate over the course of months, or even abruptly change with team composition or shifting to new technologies or even vague morale issues. All that is normal, it captures important facets of work, and trying to stop it from happening only creates other problems. What matters is that somebody is looking at near-past behavior and using it to make a near-future estimate. * If someone tries to mandate a fixed arbitrary correspondence between points and real world time, that would be a non-ideal scenario for various reasons.
- roenxi 2y agoStory points are primarily a social tool - senior management politics requires that something gets measured; story points make them happy and provide a quantitative way of communicating with the rest of the business. Until we come up with a way of measuring programmer productivity - which is not a queue - there is hard to improve on using story points.
- eksx 2y ago“Which is not a queue” why not a queue?
- danielrhodes 2y agoPeople take these kinds of things way too literally. There is no golden solution here. What gets repeated over and over continues to be true: teams should choose a system that works for them. And ideally that system is measurable, so the team can evaluate progress, improve its own performance, and align itself better with other teams and the business. But in terms of scrum and points here's my take: I've seen points work on some teams and not work so well on other teams. It's imperfect, but if you just accept that, you can make it work quite well. The reason it's helpful to estimate complexity as opposed to time is that people with different experience levels would give different estimates based on their abilities. Complexity allows you to rally around a common understanding of a solution regardless of how fast one team member might be able to complete it versus another. Does complexity have some relationship to time? Absolutely. Everybody knows this. That doesn't mean that we should be using time instead. So how can a team estimate accurately? You will hear from some people that their estimates were wildly off or that it's impossible to estimate a project or they felt pressure to under-estimate. If your estimate is too broad, you need to do the mental work of breaking it down into smaller chunks that are easier to estimate. If you feel under pressure to ship on an unrealistic schedule, that's not a points/scrum problem. But the "it's done when it's done" is also not realistic either. The idea that the estimate has to be 100% spot on is also not true. Again, it's imperfect and that is ok. But you'll find that the better a team knows their codebase and knows the product, the better they'll get over time at estimating. But if the work is too vague, the team should push back until they have enough information to more accurately break things down. This process makes for better software, especially when the team does it together. Another missing aspect I see a lot is having a feedback mechanism. If you as a team are discussing why a task took longer than the estimate, or track metrics over time, you can all get together and figure out where problems on the team are. For example: maybe there are too many bugs that are hindering product work? Why? Maybe you're moving too fast vis-a-vis the expected quality bar. Some sort of feedback mechanism (e.g. retros) is crucial - the team as a whole should aim to deliver what it says it would and understand why it couldn't. The whole point of these things is that as a team you can deliver consistently not more speedily. Consistency comes before speed. The other important thing is having a way to continually improve. You want to use each sprint as a way to measure the team so it can get better. When I've seen teams that did this well, they were dramatically more productive than the teams that didn't do it well.
- gregwebs 2y agoStory points seem to be a reaction to a process that doesn’t include the proper amount of time needed to actually make a proper estimate. They seem designed to obscure how long something will take to accomplish. I think people like this because estimating is really hard and obscuring is seen as the solution. The alternative approach is to do more detailed estimates. In addition to any design work this can require time boxing a “spike” to better understand things. This approach works well for estimating but leaves the sprint uncommitted until the spikes are complete.
- iftheshoefitss 2y agoAre there any companies that have no estimation no pointing etc just figure out what needs to be implemented and implement it type situation?
- hu3 2y agoStartups that have their spec aligned to chaotic good.
- slater 2y agoYou forgot to add "on bro"
- iftheshoefitss 2y ago[flagged]
- lifeformed 2y agoBut what exactly is a "task"? It still seems like an arbitrary unit.
- osigurdson 2y agoI think if you have a clear and compelling vision, along with motivated people, story points, scrum, etc. can all work well. If you don't have that, then no process works. So, get the former and don't worry too much about the latter.
- jasonlotito 2y agoIn this example, example task sizes are assumed to be the same level of effort. That's not necessarily an easy thing to do, and sort of falls into the same problems that pointing out stories. If your tasks aren't the same level of effort, then one task could take a week, and then next takes an hour. The author seems so sure, I'm almost sure I missed something, but unless you can reconcile how you can have 1 hour tasks and 1 week tasks and consider them the same, well... I'm just confused.
- jksmith 2y agoCompletely missing the point, which often happens with xor thinking. The beauty of story points is that they rely on human ability to compare things quickly. It's almost instinctive. ex. You're being chased by a rhinoceros through the jungle. You come upon a tree with branches and a boulder with handholds. 2 seconds, which do you choose? Story points are just a warmup for more elaboration, not an xor decision. This article is making a single-level decision, which completely misses point of using story points. The work-effort really required will be discovered in more elaboration. Story points just give you a live or die measurement, that's it.
- mvkel 2y agoThe system doesn't matter per se. What matters is that you have one
- citrusx 2y agoThe problem with the proposed solution is that many teams can't accurately break down tasks small enough. And, even those smaller tasks have variability in how long they take to do. What I've seen is that most teams don't really know how far "stories" break down into their simplest tasks until they actually do the work. So, that puts us back at square one, for the most part. A story point may not tell you a lot, but tasks in this form often present the same problem.
- Hnrobert42 2y agoGood lord. Get to the point.
- Mathnerd314 2y agoWhat about function points? (https://en.wikipedia.org/wiki/Function_point https://en.wikipedia.org/wiki/Function_point) They are basically just lines of code, but LOC has a precise definition and is not just "whatever it takes" like a story point.
- aussieguy1234 2y agoIve been in lots of teams using story points. What I've found is that what one point is worth is never consistent between teams. A 3 for one team could be a 1 for another. Or a 1 could be 0.5/0.25. In one team, 3 points might be equivalent to 3 days work. In another it might be 1 day.
- captaincaveman 2y agoYeah, and thats fine, there is literally no need to have them consistent between teams.
- jiveturkey 2y agoI'm not sure I get it. If you're doing story points, you are doing big-A Agile yes? In that case, you absolutely always have an impossibly long queue. The things that don't get done keep going into technical debt, which as a rule doesn't decrease. Until at some point you declare technical bankruptcy. If you reduce this to just the queue for the current sprint, that is generally a smaller size, the queue length is determined by ... the story points. So to manage the queue without story points, your job is to break the stories into equal-sized tasks, so that the queue size has a meaning. However, you cannot break a story up that way (this requires estimation of task complexity -- the premise of the article and our own battle tested experience is we don't know how to do that) and even if you could you run into the infinite queue as I mentioned. > I am certified to teach it as a SAFe Practice Consultant (SPC) :sus:
- ChicagoDave 2y agoMy experience is that when used with cross-team members as level of effort, discussed with each story and receives a high confidence vote (fist of five), then measured against each team members capacity (measured over several sprints), story points serve a valuable way to manage work. They do not equate to hours and cannot be boxed by management expectations. Management can separately track actuals (hours), but that really should never concern the team.
- forgotpassword2 2y agoIn my opinion, I think that assigning days to story points and breaking down task/sub-task to fit within a max of 5 days solves most of the problems. Yes, every task can't be estimated correctly but it does help in tracking things.
- Too 2y agoThis article argues against story points but then concludes that the solution is breaking down work packages into atoms called tasks and measure the queue length. Those are two different dimensions. No matter how hard you try to break things down, a task queue will still have items in it with different sizes. There is nothing saying you can't refine work packages together in your team, while still using story points. That's actually how it's done almost everywhere. When items end up with a very high estimate there will be a push to refine it to something smaller. Something you should do but only as long as it still makes sense. In fact the worst place i ever worked at was where we were given strict orders to break down every story until they all became 1 story point (still using story points...). Doesn't take a genius to figure out what happened next. All packages started having pointless micro-tasks with thousands of cross dependencies between them: "open the editor", "write a function" "write a unit test", "commit the code", "review the code". How am i supposed to write a unit test before the function signature has even been made? How am i supposed to iterate when finding bugs? More complex tasks still overran their estimates by factor 10, in fact even worse than before, some things just can't split, yet they still needed 1 point estimate. Using the queue length and the impact on variability is still an interesting concept, i just don't think you should connect it with breaking down everything into single-sized items.
- hi_hi 2y agoThe bit where it broke down for me was where they initially make the (great) point that agile falls down where small story points for simple tasks (which is accurate) are added to large story points for complex tasks (which is much less accurate), leading to a net inaccurate estimate. So the take away is to break down complex tasks. Then they introduce queues, which are made up of small tasks. I admit I stopped reading at this point. Is the useful thing the queue, or the fact everything is now broken down into small tasks?
- brightball 2y ago> Is the useful thing the queue, or the fact everything is now broken down into small tasks? Yes. :-) There are numerous benefits to both that are explained in more detail. The short version is that the small tasks will give you a more accurate rate of progress. The exercise to break things down that way will benefit the entire team's communication and understanding of the problem. Writing them down will keep a record in place for new developers who join where a point measure wouldn't provide any real context. The queue gives you a clearer picture of job sizing that can be measured and naturally changes with scope changes. It gives you a leading indicator of additional complications so that you can pivot earlier in the process if needed. Awareness of variability amplification from the queuing process also makes people conscious of flow control of work, as well as the extreme negative consequences that happen when that work is over-scheduled. They work together to create multiple benefits.
- clement_b 2y agoVery interesting take and definitely an article I will come back to, but in the end, the size of tasks is relative, and the author counts them. How's that better than counting story points? Feels like a lot of folklore for a similar result. In the end, like with story points, what matters is the effort put into splitting a problem to better understand it and plan accordingly.
- avereveard 2y agoYeah sure everything eventually averages out with enough sampling, and maybe queue based forecast converge faster than velocity and point based forecast. Why? Don't know, whole article reeks of gut feeling, which is strange as data should be available since the whole point of scrum masters is clerking things out. The problem with a queue system is not in the averages tho, but in the exceptions: say sprint or project is late, which features give you the largest impact when moved around or canned? If the customer wants to reduce cost, how do you give visibility of feature effort? Or are we in the toxic agile version with fixed scope, cost and deadline? Because then just ditch the overhead and waterfall your way trough OH and btw this system is not gaming resistant, people may pick the smaller task first to meet queue processing frequency, and then you'd get massive frequency drop at the end.
- resonious 2y agoThe proposed queue system seems somewhat orthogonal to story points to me. You could easily do the queue thing with or without story points, or vice versa. With the pure queue solution, you still need to make sure the tasks are all "small". The problem of defining "small" is the same problem that makes story points so unreliable and confusing. So I suspect the kicker here is just having a group of motivated and competent people.
- luke-stanley 2y ago`Measure queues` like `Work In Progress limits` from Kanban. Cleverly the article dodges mentioning those terms!
- mnsc 2y agoFrom when I was doing kanban there were, very intentionally, little to no forecasting done. We broke up a feature a bit and started chugging along. Every question from mgmt like "when will it be done?" was met with a "we are working on that right now, so asap" and that flew. However that was a stable product that was mature and had quite a few customers paying an annual license that were mostly happy, but of course appreciative for new features. Right now I'm working on a bigger product that fails to capture customers in a highly competitive sector and everything is about time and estimates. Middle mgmt is pretty stressed out and the latest bid is to estimate tshirt sizes. But really, it should be translated to time/increments.
- bitwize 2y agoRemember, for any project -- software or otherwise -- in any business, the business is going to need to know the answers to two key questions: * When is it going to be done? * How much is it going to cost? You should therefore estimate in units of time because you will be held accountable for time. (And time is money.) This is straightforward if you break the work down into components of manageable size beforehand and prepare a bill of materials itemizing each component that the final product will require. Using the BOM approach means that completion progress for the system as a whole can be tracked in terms of which materials are complete and ready to go, not just a number or percentage of how complete someone thinks it is. Now what if your team gives one set of estimates and the estimates are off? Well, what managers have found is that usually there's a pretty consistent ratio between the time a programmer estimates a certain task will take vs. the time it takes them to actually perform a task. Therefore, the correct way to go about time accounting is, for each task, the developer should give a time estimate before starting the task and record the time it actually took them to complete it when they are finished. The ratio between the two, as it stabilizes over time, will give project management increasingly good information about how long it will actually take a given developer to do a given task, based on their estimate, and enable them to calculate schedules accordingly.
- dfgdgf 2y ago[flagged]
- poikroequ 2y agoStory points don't help me do my job. They do a great job of wasting my time and making me less productive. It's not just story points, but the whole agile/scrum methodology feels terribly wasteful. The gross amount of time we waste setting estimates, refining stories, sprint planning. To what end? So management can make some meaningless charts? So that the "decision makers" can use these contrived numbers to figure out who gets cut in the next round of layoffs?
- heywire 2y agoIs there anyone else out there still doing waterfall and estimating in hours and everything is just going fine, or am I just that lucky? I work on a small professional services team customizing a couple of our products for our customers. A few times a month we get a request for an estimate to add a new feature or workflow. We do a high level customer requirements doc, discuss it as a team, the seniors from each area (design, development, qa) each provide an estimate in a range of hours. This all gets wrapped up into a final price to the customer. If they approve it, we dive into detailed design and have them sign off on the result. Then we go into development for weeks to months, qa, and then release. Our processes really haven’t changed in over 20 years. We’re constantly ranked as one of the most productive teams, and get high scores on our post-project surveys from our customers.
- sumedh 2y agoWhat does QA do when you guys are building the software?
- azangru 2y ago> Scrum tried to fix this in 2011 when “Commitment” was changed to “Forecast” I've checked scrum guides released in 2010 and in 2011. The word "commitment" does not appear in the pre-2011 version. And, as far as I remember, the word "forecast" replaced the word "estimate" in the 2020 edition of the scrum guide compared to the 2017 edition.
- arcbyte 2y agoI don't understand people like this author. I guess I do. It's all marketing flamebait to get attention. He knows exactly what story points are, he goes through them exhaustive, but strangely deriding them the whole time. Then he concludes by purporting to invent the very practice you ALWAYS were supposed to have been doing to make story points work. You have to find a set of repeatable work to compare new stories to for reference. That's the whole game. That's his tasks "idea". That has always been part of every implementation and lesson on story points ive been exposed to. It's a completely nonsensical article. Story points have always been about queues and implementing Little's Law. Always. Yes, it sucks to be on teams that just argue about points and don't work to refer to standard architectures for building blocks. That doesn't mean story points are broken, it's pointing out something else in your organization is broken. A lot of real criticism in this comment, but props to the author for writing at least. It's more than I do as a part time internet complainer.
- brightball 2y agoI can see that perspective I suppose, but it's certainly not marketing flame bait. Whatever story ports were always supposed to be, they aren't. Numerous people's real world experiences go sideways, because of the way that they are designed. You're setup for failure and confusion. I never claimed to invent anything. I'm highlighting Donald Reinertsen's work that more people should be following. The purpose of the article is to remind people of why everything is broken so that they can identify it and fix it, including examples.
- ffsm8 2y agoAs far as my current employer is concerned, 3 story points equal 8 hours of work. The previous one considered only complexity, so a simple change that needs adjustments all over the project would still be considered 1 story point, even if you needed multiple days to get it done. The PO in the job before that kept asking "but how much time will you need for that" until he got an answer, ultimately making story points redundant. Really, ymmv
- tacitusarc 2y agoSo this may not be fair, but you lost me quite a bit with the positive take on SAFe, which is the worst, most unproductive experience of any process I’ve had. I also do not understand the queues and capacity issue. I have never been in an environment where we do not have so much work that we cannot meaningfully see past the end of the queue. I don’t necessarily view that as a bad thing.
- monkeynotes 2y agoI don't really understand why the author needed to use all those words to suggest t-shirt sizes instead of story points. All the stuff about breaking down tasks, watching a backlog queue to monitor cadence, and have regular meetings is already happening with, or without story points. People overthink this stuff all the time. Every team should figure out what works best for them, even down to project by project. Getting shit done isn't hard to monitor. You have a bucket of well defined tasks, have sprint meetings, look for blockers and assumptions, watch work flowing through. It's not really that difficult. Whether you use story points or some other estimation tool is really just an exercise of calibration, it's not gospel. The estimation process is the important thing, discuss as a team, agree on complexity, make sure the task is bite sized etc.
- ath3nd 2y agoTo me story points, planning poker, scrum, and a bunch of other "agile" artifacts are funny concepts. Making 4-5 highly paid professionals sit around in a circle with a bunch of cards trying to estimate how long/complex/??? the task is, writing it down, and doing that every two weeks, to dubious results, is exactly what one can expect out of today's businesses. My guess is management doesn't trust that engineers aren't just fiddling around, so they hire a bunch of management-like people to watch over the drones, and show them who's in control. And how else you can show you are in control if you don't introduce magical rituals and tracking useless metrics, and make grown people participate? That way, all these meeting rooms can be occupied and the owners can feel like something important's happening and that they are getting their money's worth.
- cynicalpeace 2y agoThe point of all of this is to communicate to management how long a task is going to take. I would suggest that a good manager doesn't need this communication. A good manager will have already done the task, or something similar, to already know how quick it can be done. If they haven't, they're probably inexperienced in the task. They were appointed because they were a "people person" but this fact has actually introduced more friction to the team (needing the story points yada yada) rather than just assigning a simple deadline from the get-go. Once a deadline is introduced, Parkinson's Law kicks in and you get more or less efficient work depending on how aggressive the deadline is. I'm advocating for experienced managers, not deadlines per se, since that is just 1 tool in the toolbox. I'm also advocating against the countless asinine ways to communicate to lousy managers. Throw the points in the trash and start hiring cracked programmers as your engineering team's standard bearer. See the company grow and have happier employees.
- 0xbadcafebee 2y ago> what if we substitute something else for story points? Then that new thing becomes the new measure, you change what you do to meet that measure, and things are screwed up again. The author's final paragraphs describe implementing a complex process that an intelligent team has to use in a nuanced way. And somehow simultaneously declares that the original problem was story points, one single aspect of a complex process, and not the fact that there's a complex process that nobody understands or follows correctly. You know how Toyota gets TPS to work so well? They do one thing, well, at a time, repeatedly. Product development sucks because it's trying to do a million things once, constantly changes its mind, doesn't train its workers, and conflates designing, engineering, assembling, and operating, as one giant "thing". Then it wonders why it can't keep track of time.
- yesbutnobutyes 2y agoIn my experience people mainly like to complain or exist within a state of conflict where they are against something. Story points are relative value as defined by the team, for the purpose of forecasting and reporting. They really can be anything the team decides, as long as it's a reliable measure. Ultimately they exist to answer"How long will this take?", which is the most dependable question from people writing the cheques. People asking that question don't care if it's Fibonacci or hours or t-shirt sizes or anything at all. "Is x bigger (or smaller) than x", followed by "is this more important than this" should be brain-dead easy and logical for everyone involved. In my 10+ years I've learned that it's ultimately just that people don't want to be told what to do and/or need tribalism (an "other") to feelat balance with their environment. There's no escape from prioritization and sizing. Throw scrum in the garbage and you'll still be doing it by another name.
- pixiemaster 2y agoWell history in IT repeats itself in cycles. look up #NoEstimates for good and thoughtful content about this topic, and various anecdotes for inspiration. then derive your own conclusions.
- csbbbb 2y ago> Now, if you're paying attention and reading this with a critical eye something in your brain just told you "Wait, this is just waterfall! We can't know everything up front!" The article presents the "story points" problem to be caused by an ignorant or presumptive misunderstanding of how the system works by outside parties. I think articles like this are an interesting and necessary part of the overall project-managent discourse. However, they tend to infer that the problem of ignorance can be resolved by the management framework directly, to which I disagree. Ignorance, regardless of project-management, has to be addressed by clear communication and boundaries.
- sirwhinesalot 2y agoI've never understood the point of the points (pun intended) you can try to convince yourself they're measuring "complexity" or whatever but what they're measuring is time, so why not cut out the middleman?. I'm not saying to estimate tasks accurately to the hour. Just rough ballparks: "I think I can do these 3 on friday". "Give me a week, it's gonna take a pile of tests to make sure we get it right". "Hmm I probably need the whole sprint for that, we don't have a clear view of the impact, it sounds like a small change but it uppends our current architecture". These are the real discussions, the numbers are a silly abstraction on top of this and are unnecessary. It should also be 100% expected that the estimates will be wrong. New bugs will show up, regressions will be introduced, requirements will change last minute. It should also be expected that some tasks that were supposed to get done won't be and other tasks that weren't in the planning could be snuck in. You are "Agile" are you not? If you're not than just go back to waterfall and stop dragging the Agile Manifesto through the mud, thanks. The entire point of the exercise is the discussion, it gives you some idea of what is likely to go well and be finished and what is a risk factor. If you're measuring "velocity" god help you.
- beryilma 2y agoRegardless of what anybody says to the contrary, story points are and have always been used as an obfuscated measure of time. When we can never estimate plan timelines correctly in the first place, why would anybody think that we should be able to measure story points with any accuracy? It is just another stupid PM gimmick to create useless management metrics.
- andreleite77 2y agoStory points never make sense to me. It's not only because of the schizophrenic process of estimating tasks' complexity (not time) to understand how many of them can be added to a two-week time window. In teams that focus on points: 1. you spend time giving points to tasks in a meeting with the whole team 2. to calculate how many points can be added to a sprint based on the points given in the past, without any adjust for the cases where the points allocated to a task were wrong 3. to determine the group of tasks that will be assigned to each developer 4. to finally, discuss why the number of points assigned to a sprint was not fully delivered (it's rare to find sprints where the tasks are delivered earlier; Parkinson's law explains that) It's unlikely that any stakeholder would prioritize a team's precise task estimation over the rapid delivery of features or projects. In this sense, a kanban process will have the same outcome with much less energy spent, and small tasks will give you the same statistical value without spending hours estimating "complexity." The Sisiphisean job of trying to assign the correct number of tasks to a sprint is only there to comfort team members who don't want to consider the actual value of the processes they use.
- tracker1 2y ago... but $OTHER_TEAM is going through 20% more points each sprint than your team. I hate story points, in fact I hate most automated issue trackers, generally speaking. I don't mind that there's a backlog and that features should have some details. But I'm now stuck in an org where we're doing SAFe/PI planning 6+ months ahead of where the devs will actually do the work, and designs that likely won't represent the true solution in practice among dozens of teams in a very large company. It's kind of insane.