Why software projects take longer than you think: a statistical model (2019)
- Jtsummers 6y agoPast discussion with a lot of comments: https://news.ycombinator.com/item?id=19671673 https://news.ycombinator.com/item?id=19671673
- vbtemp 6y agoI tend to be skeptical of statistical analyses like this. At the end of the day, it's usually someone who is paying or funding a task, and someone who will perform the task. The person performing the task wants to please the person funding it (in order to secure that funding). This commonly involves minimizing difficulty and giving optimistic estimates. People who give straight answers (something like: this is really hard, it will take a lot of time, there are lots of unknowns, and might not be achievable given the budget) won't get the award. Those who overdo the bullshit and give transparently falsely optimistic estimates will not receive it either. So those who fall in the middle do end up getting the award. TLDR being, model this effect Game Theoretically, where the "blowup factor" is derived from a Nash equilibrium between counterparties playing optimal strategies seeking to optimize their payoff. Finally, take three companies: Company A delivers a project in 50% of the time, and 50% under budget. Company B fails to deliver the project, after consuming 100% of the budget. Company C completes 90% of the project with 100% of the funding, and only needs 20% more money to finish it. The customer will most likely top them off, because they are so close, and it's a sunk cost. Who makes the most money? Company C. Who is the biggest loser? Company A (despite being the best). Anyway, for my next trick, I'll explain why this same effect causes agile to make everything take longer, cost more, and make everyone more miserable.
- fart32 6y agoI'd love to hear your standpoint on the agile.
- mikequinlan 6y agoAgile plays this scenario out every two weeks, instead of once per project.
- sorokod 6y agoHow does the ABC example extends to repeated games?
- vbtemp 6y agoCompany (or team, or individual) A "the best" is perceived to not work hard. They are perceived to be underutilized. They miss out on so much potential revenue they don't make it to the next round. Company B is obviously incompetent, and doesn't make it to the next round. Meanwhile, company C, barely competent, is perceived to make best use of resources and remain fully utilized. They are received to work really hard. They get not just the initially agreed upon budget but a top off in addition. They have the most profit to compete in the next round. If company (or individual A) makes it to the next iteration, they know how to manage expectations, stretch the budget, and make a theater of working hard.. thus turning into company C. After enough iterations everyone kind of ends up like company C. Just good enough to complete the task with estimated level of effort some double digit percentage over the original estimate, but not incompetent enough to flop altogether. It is to this I attribute why software is usually behind schedule and over budget to a reliably predictable degree
- z3t4 6y agoWould love to hear your take on agile. You should write a "blog" post about it... Company A would eventually get a good reputation and win in the long run.
- vbtemp 6y agoIn an idealized world consisting of perfectly rational econ agents company A would win out. However we live in a world of people full of cognitive biases and driven by fear, greed, sentiment, and a whole slew of not perfectly rational drives.
- tonyedgecombe 6y agoI've seen individuals and small groups that would fit in category A loose out to C's. People that quietly get on with their work without problem whilst a bunch of drama queens get all the attention for heroically fixing problems they created in the first place.
- vbtemp 6y agoThis is exactly right. A team that crams agile sprints with tons of "tickets", makes features that aren't fully thought out (necessitating more "tickets" to fix them), and has steady influx of general bugs cropping up is perceived to work super hard. People like to see noses to the grindstone and people stressed out. The team that works carefully and deliberately, does things well the first time, and seems to be moving at a relaxed pace is perceived to be lazy and inefficient. People are offended by this. This hit me hard the first time I was a project lead -- the customer was delighted, the product was steady and reliable, but my staff were super uncomfortable and insecure -- because the project was successful and they did their job well and like professionals, they realized that they weren't super busy. And when they aren't super busy it means they may be on the chopping block - it was terribly depressing. No amount of reassurance that, well, this is what life is like when you're good at what you do really settled anyone. So, consciously or not, we fill our time with "work theater". We work really hard to write new code that then requires more work to get right and to fix, and with a backlog of work, it looks like we're working really hard. Being always a little behind, we then make the case for more funding, more staff, more resources, etc etc etc... And the cycle continues.
- 082349872349872 6y agoManfred Schroeder's "Fractals, chaos, power laws" (1991) had a similar statistical distribution (Levy? or something else?) which reminded me very much of software. Basically, the longer something has been observed to remain uncompleted, the further away the expected date of completion becomes. If you have to slip, slip big.
- hertzrat 6y agoThe hardest part of this is communicating it to a client. “What do you mean it will probably take 5 weeks, but could take between 2 and 10 weeks? That’s a pretty big span. The other programmer I asked promised it would be done in 5, period. Are you sure you know what you’re doing?”
- myth2018 6y agoI've made a comment some minutes ago about the difference between estimates and plans. Making the client aware of the difference may be useful. However, it's also a fact that most clients ask for being deceived. I've seen that scene over and over: Company A presents a fairly detailed 3-months plan while Company B salesperson says that the project is easy and they will deliver it in 1 month. Company B wins the project most of the time, only to (possibly) deliver it in 6 months or so. Some clients even train their employees to avoid such traps, making them informed of estimation techniques and encouraging them to use plain good sense, but those are exceptions. Software projects would be way less painful if clients, and not only software development companies, worried more about achieving higher levels of maturity.
- ncallaway 6y agoWe used to try and present estimates as a range ("between 5 and 10 weeks"), but we've settled for trying to provide a single number rather than a full span. For our time and materials estimates, we try to provide an ~85% confidence estimate, while for fixed bid projects we try to aim for a ~95% confidence estimate (and there's usually a pretty big gap between those two numbers, for the reasons pointed out in the article). So, in this scenario, we'd probably say to the client that it'll be done in about 8 weeks (making clear that's an estimate, and not a promise). One number, rather than a range, seems a lot easier to explain to a client and if you end up low (say it takes 3 weeks), then you have a pleasantly surprised client.
- FpUser 6y agoOver the course of my life I've designed and built many products/projects. Not a single one that had deadlines imposed by the customer was late. It might deviate on non critical feature set but the main course has been always served properly.
- FpUser 6y agoI know, I'm supposed to be modest but it is the truth. And I did not mean just me personally. Some things I did on my own and for some I had to involve team. I think one of the reasons is that while I am reasonably good at architecture and programming in general I do not really get hung up on processes / languages / tools / technologies etc. What makes me tick is when I see the product working and serving people. That's the only thing I really interested in.
- romanows 6y agoWhat kind of things do you make, how well do you know the technology/domain, what are the customers/users like, and how long out are the deadlines set? Why do you think you're so successful when so many other people have problems with estimating schedules?
- FpUser 6y agoI made various things. Two examples to show the range - Enterprise grade business process middleware for Telcos. Software and microcontroller firmware for law enforcement. And then everything in between. I have never really thoroughly analyzed why I am successful with the estimate and delivery. I think I'd be way more interested in it if I was late. Since I am not I do not really care. I just am and this is enough for me. I am eternally grateful to my University (nothing to do with comp science btw) and teachers though who taught me not to blindly remember the rules but how create those. I guess this helped me to become who I am.
- balfirevic 6y ago> I know, I'm supposed to be modest but it is the truth. I don't think you were downvoted because you were immodest (although I'm sure it didn't help) but because your comment doesn't contribute much to the discussion. Do you have any comments on the content of the article? Do you have any estimation techniques to share? What were the deadlines based on?
- myth2018 6y agoI'm not at all experienced on the subject, but, so far, the mindset I liked most is the one presented on "Software Estimation: Demystifying the Black Art": one must be aware about the difference between an estimate and a plan. Estimates are statistical by nature; they are made of "educated guesses" and historical and empirical data available. Estimates must be unbiased. They are unnegotiatable and they are not commitments. Plans are not statistical. They are oriented by estimates, but they must present concrete dates and, when they are not met, the plan must be revised and renegotiated. Plans are commitments. I think this separation brings useful implications and tools to argue sensitively with stakeholders. I've always hated having to commit to hard dead lines based on estimates. While I was aware of the importance of providing concrete deadlines, it felt like I was taking the entire risk of the estimate for myself, which is unfair, to say the least. By making the separation between estimates and plans, I'm more equipped to discuss the matter. I can show the estimate and, when pressed to commit with a tighter deadline, I have some leverage to trade the desired deadline for a decrease on the project requirements set, for instance.
- triggercut 6y agoDepending on the complexity of the plans and the dependencies between activities, you absolutely can go over a planned date, so long as it's the early start. In critical path method scheduling, you will typically show an "early start" and "late finish" dates for an activity and maintain float to the early or late start of the next (driven by other activities in the DAG and availability of resources assigned to them). I (and others) like to explicitly state contingency factors and/or risks as successor activities that consume this float. They can also be used for Monte Carlo analysis where those activities are randomly increased in duration (usually on some statistical curve as discussed in the article) What we are really doing is simulating many many permutations of the effects of known risk likelihoods and consequences across the graph. Otherwise in a large program of works we will tell Project Managers or Contractors that they can manage their own float which gives them flexibility to execute. Another method that simplifies this is PERT[1] method, where you take, optimistic, pessimistic and normal durations to produce an expected duration. [1]https://en.wikipedia.org/wiki/Program_evaluation_and_review_technique#Time https://en.wikipedia.org/wiki/Program_evaluation_and_review_...
- commandlinefan 6y agoHofstatder’s law: it always takes longer than expected, even after accounting for Hofstatder’s law.
- lambda_obrien 6y agoThe 80-20 rule: the last 20 percent of the work takes 80 percent of the time.
- rossdavidh 6y agoI've hear it as, "the first 90% of the task takes the first 90% of the time, and the last 10% of the task takes the other 90% of the time." :)
- k3liutZu 6y agoAmin
- kqr 6y agoThe critical thing many people miss about this rule is that it applies recursively. So of the 20 % that takes 80 % of the time, in turn 20 % takes 80 % of that time. Go further and you get a 50-1 rule: 1 % of the work takes 50 % of the time. (Or, equivalently, 50 % of the time gets you 99 % of the way there.) This is a strong argument for clever scope reduction. Edit: To be clear, this is the Pareto distribution with α=1.16 -- and I don't think this applies to software implementation. The tail isn't quite that fat, in the data I've had access to. But the general idea still applies, except with less aggressive percentages!
- Tcepsa 6y agoMy corollary: Never attempt to account for Hofstadter's Law!
- csours 6y agoEstimates are for projects where you know what you're doing. You can estimate home construction because you've built a home before. I can estimate the happy path. I can't estimate edge and corner cases until I get closer to the edge or corner. It's not even there until I get close to it. I strongly agree with these statements from the article: >"Tasks with the most uncertainty (rather the biggest size) can often dominate the mean time it takes to complete all tasks. The mean time to complete a task we know nothing about is actually infinite."
- danaliv 6y agoTotally. Software estimates are like looking at a dungeon map where you can see the beginning and the end, but the rest of the page is blank until you've actually entered that part of the map.
- lambda_obrien 6y agoSometimes you even fall through the floor and find a whole 'nother world down there.
- mtm7 6y agoSometimes you find out that it's a Spirit Temple project and you won't be able to complete it for another seven years.
- BigJono 6y agoWhat I never get about estimates is why people don't just reduce the granularity until they have some amount of accuracy they can work with. 95% of my teams have estimated using the 'story point' crap, or rarely in days (one in hours for a hot minute, that was a fucking joke I'll tell you what). In every single one of those teams eventually some stakeholder chucks a hissy fit because some feature they're emotionally invested in was 3 days worth of points and it ended up taking a month. If they'd measured in weeks, that blowout would have been lost in the noise of other things that took 2 weeks instead of 1, or 3 instead of 2. If they'd measured in months, it wouldn't have been a blowout at all. Which sounds like putting a band-aid over a gaping wound, but the thing is, what does your business really need to respond to on the time scale of days? The point isn't to improve the estimates (everyone should know by now that that's a fools errand), it's to improve the business response to what the development team is doing. If you're trying to decide whether to launch in 8 months or 12, or you need to time a project to some external event that's 6 months away, and your plan is to have a big "how are we tracking" meeting once a month, or once a fortnight. Then why do you need to measure in anything more granular than a month, or a fortnight? Set goals to the cadence of those meetings, try to make them as objective as possible, then hands off and go find something else to do. IME 95% of what teams (especially in enterprise) call estimates is just something for a PO or PM to jack themselves off to for 30 hours a week on projects where their input is only really needed for around 10.
- k__ 6y agoBecause we take on stuff we don't know enough about. That doesn't mean it's new or hard, it's often just stuff we didn't do before. Or we didn't document what we did and months later start from zero.
- jbay808 6y ago> A reasonable model for the “blowup factor” (actual time divided by estimated time) would be something like a log-normal distribution. Interestingly, we did extensive time tracking on a multi-year in-house software project and collected data comparing the estimated completion time of tickets with their actual time. The software department was under a lot of pressure to improve their forecasting, and were somewhat despairing that their estimates were off by a factor of about 1.6 on average, and sometimes a factor of 10 or more. This persisted in the face of all attempts to improve calibration. Managers were worrying that developers had no idea how long a task would take and estimation was futile. When we plotted the data, in all cases, the actual time was very accurately fit by a lognormal whose scale parameter was precisely the predicted completion time. That is, whether the tickets were predicted to take 1 hour, 3 hours, 13 hours, or whatever, the histogram of their actual completion times followed the exact same shape but with a corresponding scale change on the x axis. This told me that the developers actually have a really good understanding of the class of problem they're dealing with when they start a task. But sometimes tasks have multiplicative factors that make them take longer than you expect. Sometimes the bug turns out to be two bugs, and so on. Based on this analysis, I urged them not to consider it a prediction failure when a ticket takes 10 times longer than expected; that's just a property of the lognormal distribution, and that estimate likely did a good job of reflecting all available information at the time they made it. Instead of changing the estimates, I suggested that we pick a safety factor for external facing commitments that reflects this distribution. Padding the estimate by 1.6 factor gives the mean, but if you want to make a commitment you can take to a customer, you can just extend the lognormal up to 95% confidence or 99% confidence or however trustworthy your promised commitment needs to be. Of course, a 99% confidence interval on a lognormal is a pretty big factor. But if that's better than running late, it is what it is. Another interesting thing is that you'd expect, by the central limit theorem, that sufficiently large tasks would eventually become normally distributed rather than lognormal, because they're composed of a large number of subtasks. But it turns out that lognormals are a pretty pathological case; sums of n lognormals can continue to look nearly lognormal until n becomes really, really large.
- jcims 6y agoThis is pretty interesting, do you doing you are able to defend those estimates using the same methodology?
- godot 6y agoIn my experience from the past decade, it is often the case that, the difficult thing isn't estimating how much time the proposed project takes to build (this is the difficult part for some devs though), but it's how much other stuff comes up. Stuff includes everything not related to your project. E.g. your last project that is now on prod, where bugs were reported and need to be fixed. Another team needs your expertise on something and next thing you know you're in a 2 hour meeting with them, and also reviewing their 1000-lines PR. Maybe a real production fire is happening and you have to help and it takes you the next 2 full days on it. Because of this, my general approach when estimating a project in my head is how much time I know it would take me if I get to work full time on it with nothing else on my plate. Then I can better estimate how much time realistically it would take after factoring in X number of hours per day on distractions. In many cases I also communicate with the stakeholders (PMs, biz ops, leads) directly "This is how long it would take me if I dedicate full work days on it" and let them take it at face value too. (It's a sentence that usually ends with "So realistically probably [2x of what I just said]")
- kybernetikos 6y agoYes, we've recently started to track how much time developers are working on things that were estimated vs how much time they're spending on other things (standups, retros, refinement, one to ones, company meetings, training, customer meetings, builds, support and maintenance....) A surprisingly large portion of the 'estimates being wrong' is actually down to the fact that people generally estimate that they're going to be working 100% without interruptions or other tasks. Sure, there are times when tasks are harder than expected, but this is a smaller factor than I had originally anticipated.
- kvee 6y agoAt my software agency, we were actually inspired by this post when it was on hn a couple years ago to, in a hackathon, build a simple machine learning model around it. Then, recently, we actually built our own internal tool to add "uncertainty points" to estimates for each client project we do. And the ML model predicts better and better how uncertainty uniquely affects each project we're using it in. We've been using it on 1 project for and it's actually working surprisingly well. We're also in the process of rolling it out to most of our other projects, or at least the ones using Pivotal Tracker, which is the only tool we're supporting right now. If happen to be using Pivotal Tracker are interested in testing it out yourself and giving us any feedback you might have, plz shoot me a message at the email in my profile.
- dchuk 6y agoIf you ever port this to jira, I’d give it a shot
- temporallobe 6y agoAnd management would like to add something like “optimism points” so they can cancel that out and have better metrics to report to stakeholders.
- kqr 6y agoThis is interesting. Have you benchmarked it against e.g. a linear regression model built on your own subjective estimations?
- ChrisMarshallNY 6y agoI think there are a number of things that contribute to problematical estimation, and a number of development tactics that make the damage exponentially worse. In my experience, I've found that managers will pretty much always end up using Waterfall, the higher you go. It may be agile in the trenches, but it's Victoria Falls, in the boardroom. At least, projects that have multiple, converging workflows tend to end up looking a bit "waterfallish." I have not had the luxury of working on a standalone, single-line project (until now, as I'm working on my own). Working on my own, I have developed a number of techniques that start from the assumption that any estimate made, that looks forward more than just a few iterations, is a dumpster fire. I've learned to work around evolving specifications, project progress variances, and the need to reduce tech debt. This reminds me of some of the work Watts Humphrey did, way in the day, and also a lot of McConnell's work. I like McConnell. He has a very realistic approach. Humphrey's work was too "eggheadish" for me, but people that used his process raved about it.
- ineedasername 6y agoI'm not sure this unique to software projects. It seems like any major project is subject to similar issues. Although for software projects I think the perception is that things are more malleable, so adding a requirement/feature etc is seen as less problematic than, say, deciding a new construction project should have a few extra rooms added to it.
- temporallobe 6y agoSometimes it comes down to poorly understood user requirements, necessitating design work in the middle of a sprint, causing a cascade of other issues like new data models, different table relationships, updates to UI screens, and on and on. Agile might pride itself on being able to handle such things, but...it’s not. Nothing is. Poor planning, no matter the methodology, results in slow, cumbersome, error-prone execution and tons of rework, 100% of the time. This was not a meant to be a rant against Agile, but in BA (Before Agile) we spent a great deal of time in requirements gathering and architecture research, so that by the time we were ready to code, we could focus on the how and not the what. And damnit, in BA we had requirements documents that actually described what needed to be done. For sone reason that is probably a misunderstood principle of Agile, requirements are considered completely unnecessary or at best a waste of time. The prevailing attitude seems to be just build the darn software, we’ll figure out the requirements later. This is like trying to build a plane while on the runway with passengers trying to board and the control tower screaming at you to take off.
- zaptheimpaler 6y agoAll things considered, agile probably still produces results faster overall. Its like running the requirements gathering & software dev concurrently rather than serially. Faster = cheaper. So the logic of economics dictates that is exactly what will happen, even if it is more stressful :/
- jdlshore 6y ago> And damnit, in BA we had requirements documents that actually described what needed to be done. That’s some damn fine nostalgia juice you’re drinking there. Can I have some of that? Me, I had the time and expense of requirements documents combined with the pleasure of them not actually describing what needed to be done.
- Forgotmypass101 6y agoI don't know where you worked, but have I worked in a place that did a design document, dropped it off on my desk, and left me to work. Them: "Why didn't you include the functionality to twiddle the foo?" Me: "What? I don't know what you are talking about." Them: "I swear it was in the design document, it's one of the most important features!" But it was not. Every design document has flaws, and even if they are as accurate as possible, many projects had to be updated after the fact as even the designers themselves did not predict some of the functionality needed. I've found that when developing new things you need to have steady communication with the people who need to use it, to understand what they need and why. For recreating old the things (CRUD apps and whatnot) I'm sure this is not nearly as important, but I have always wondered why recreating old software with modern tools has usually resulted in everyone just using the old software. I do know in one case I've done this, I was told not to include certain features because no one uses them... only to find our users not updating, because everyone needed those features. Some times even the vendors don't know what the customers want.
- 1123581321 6y agoAn entire management layer could be removed from the average software company or consultancy if only it were possible to maintain multiple estimates for one project. Expecting one number to inform resource scheduling, account management and new business is expensive.
- salty_biscuits 6y agoSo lognormal implies the total time is the product (not sum) of lots of little random tasks. Why would this be?
- tome 6y agoThanks for asking the question. I also wondered. I can't think of any obvious reason such a model would apply to software development.
- hotz 6y agoI always treat it as a thumbsuck because who really knows. I could tell you two to three hours to solve it and then it takes me five minutes. I could say a week and only end up using a day.
- xupybd 6y agoI've always found business expectations are to complete in less time than my estimates. My estimates are often a little under as well.
- KingOfCoders 6y agoSoftware project estimation is fractal.
- tempodox 6y agoAnd quite possibly NP-complete.
- GuB-42 6y agoMore like NP-hard. I don't think that something like a SAT solver will help you much with your estimations. But you can probably turn a NP-complete problem in terms of software project estimation. The traveling salesman problem looks like a good candidate here. Edit: come to think of it, it is like the halting problem, your project may never finish
- kansface 6y ago> Edit: come to think of it, it is like the halting problem, your project may never finish Uncertainty in the solution can only be reduced to the extent you have actually solved the problem. Of course, the problem may may not be solvable or alternatively, the cost can be too high.
- juskrey 6y agoThe reason is way simpler: since no project can be completed in negative time, probability distribution of completion time will be skewed to the right (with edge cases of positive infinity)
- nicky0 6y agoThere's a simple method for software estimates that has worded well for me in practice. Imagine how long it should take if all goes smoothly, then multiply by pi.
- kqr 6y agoWhat does "worked well" mean? What percentile do you practically end up at when you go back and verify after completion?
- nicky0 6y agoBy "worked well" I mean that x3 is the "about right" factor. As software engineers we tend to be optimisitic and so when I think "it'll take about a week", that's assuming no unforseen complications. I'm afraid I haven't conducted a detailed a statisical analysis, however. The pi method is in truth just a joke between myself and a former project manager. There's nothing magic about pi exactly. I imagine each person ought really to come up with their own mental multiplier based on their own tendency to underestimate. But 3 isn't a bad starting point for iteration.
- kqr 6y agoI guess I'm asking what "about right" means. Does it mean you finish faster than that number 50 % of the time? 90 % of the time? No statistics necessary, just your gut feel.
- nicky0 6y agoAh, good question. First instinct says 'success' should be statistically 50% each way. Right in the middle of the bell curve. But on second thought, being behind estimate half the time would be pretty sucky. So I'd like to bring the peak of the curve onto the early side of the line. I guess ultimately it depends on the question being asked of the estimator & the implied confidence interval. What do you think?
- niemandhier 6y agoWeber–Fechner law states that: "that the subjective sensation is proportional to the logarithm of the stimulus intensity". So maybe the "time estimates" actually are estimates for expected stimulus intensity. Think about it as 'guessing the level of dread you feel when looking at the project /after/ you finish it'. According to Fechner this should be related to the actual difficulty by a logarithmic law ( at least for humans). These estimates of sensation are than just normal distributed, as one would expect.
- nednar 6y agoThere are still people who develop software in traditional projects? As software can easily changed according to changing business needs, software is never really done. So, it's unnecessary to put it in a project. While you do a factory building project and decide a point at which you are done, you wouldn't do a car manufacturing project. Software development is more similar to building cars than to building factories. So instead of projects it is better to think of assembly lines (sprints, kanban boards, etc) and throughput (e.g. burndown). The question is how many business changes come in every week and how many can you solve every week. Measuring and viewing things the right way then also shows how successful you actually are as a development team. PS: If your company isn't working like this yet, you might consider getting some external help quickly. This is the standard for quite some time now, but admittedly it's hard to find out what the standard is if you rarely get new people added to your team.
- triggercut 6y agoDon't get confused between Projects and Operations. What you are describing is actually akin to operational projects (albeit at the risk of bespoke designing and building each car). Projects in the traditional sense produce new assets with new value with new benefits meant to be operationalized. You need to segregate associated costs so that you can depreciate the value of the asset once it's operational. Usually the cost is considered an investment and funded by separate finance. Operational Projects support, extend, enhance existing business assets. This is the assembly line mentality and is more aligned with continuous improvement for which there is usually a fixed budget for the year and is completed during the normal course of business. Yes there is some grey area but both are necessary.
- nednar 6y agoI see, so the financial side between projects and operations is also different. When would you choose to do software as a project, coming from that perspective? Maybe the budget for operational things is more limited, and so you choose to do something as a project, although you know later on you also want to still change it?
- neilwilson 6y agoFits with my rule of thumb for estimation. Come up with your most pessimistic estimate that feels right, then double it.
- tempodox 6y agoBased on personal experience, I use the factor π. Maybe the appropriate factor varies with surrounding conditions that are hard to account for. Also, use the coarsest granularity you can get away with.
- a_imho 6y ago99% there is no incentive to make accurate predictions.
- tempodox 6y agoYou never had a customer rip your head off because they took your estimate as a promise and based their own deadlines on it?
- a_imho 6y agoExactly. So when a customer asks for an estimate you negotiate for the biggest buffer you can get away with, there is no incentive to make an accurate prediction.
- tempodox 6y agoNow I get your point, and agree. Plus, coming out below that estimate will make for a pleasant experience.
- a_imho 6y agoIt depends. In most typical cases if it is billed by the hour (inc. regular employment) it does not worth it to deliver early. When failure to meet deadlines is expected the optimal time to deliver is after the original estimate. The exact numbers can vary a lot.
- jokoon 6y agoWhat about video games?
- andi999 6y agoThese comments read like from a different galaxy (for me). Here it is very clear why. Management asks: how long does it take. Engineer replies: will take X man month. Management: thats too long, lets estimate shorter.
- adamors 6y agoI clearly remember estimating something with a manager at a previous job, saying it will take 2 weeks. His response was, that's too long, let's try 2 days and see what happens.
- andi999 6y agoso what happened?
- j1elo 6y agoI estimate they will answer in 2 days.
- privatemonkey 6y agoHave had the same experience :-) It took two weeks of course.
- bregma 6y agoProject Manager: I promised the customer we'd deliver Vagueness v1 by next Wednesday. Can I have a build? Engineering Manager: ok, Engineer, we need Vagueness, how long will it take? Engineer: I can whip up a prototype in about a week but it's only a prototype and will lack any functionality. I'm also busy trying to get the fire put out on the fourth floor and my kids' daycare is closed because of the riots. Engineering Manager: OK, 3 weeks plus another 3 weeks for QA and bug fixing. Also, have those reviews done and fill out your daily TPS reports. Oh, and can you just slip in those other two projects we talked about informally last week? Project Manager: OK, I'll promise the client they'll have it by Tuesday. Where do I tell them to download from?
- deleted 6y ago[deleted]
- TrispusAttucks 6y agoIn automotive mechanics this is paraphrased as such: "Every 20 minute job is one broken bolt away from being a 3 day ordeal."
- snickerer 6y agoA story from a rainy summer in Berlin: One day my manager came to my office and said: 'Look at this task. How long will it take?' I thought 'two days' and I told him 'ten days'. He said 'Ok, do it!' and went away. I was happy that I had the chance to do it very well. To take the time to write really well structured code without pressure. And I did it. At day 5 I my work was finished. I was proud of it. At day 6 I took the time to re-read everything and to do intense testing. I found a minor bug and fixed it. At day 7 I practised for my next martial arts exam during the work time. At day 8 I went to my manager and told him 'It is finished and it is good'. He was very pleased to hear that I finished early! Before the deadline! My colleagues were happy with the well working code. I call this a win-win-win situation. Oh, what great memories. The day when I told my manager that the task will take 10 days.
- fukmbas 6y agoIt's because of all the bullshit admin work MBA execs give us