I think you've got that a bit reversed, trying to fix climate change with nuclear is a bit impossible at this point. We can't build it! Why is this plant shutt
by epistasis 6y ago
I think you've got that a bit reversed, trying to fix climate change with nuclear is a bit impossible at this point. We can't build it!
Why is this plant shutting down? Not because of some sort of hate of nuclear technology, as many would have us believe.
No, the real reason this plant is shutting down is because, like every other thermal generation plant, extending its lifetime past the original license means complying with environmental impact laws on waste heat. Once-through waste heat systems are no longer legal [1]. So why not just build a waste heat system and keep it running? Because when the utility tried to come up with one, the cost of the cooling system alone ran into the billions of dollars!
Much better to just by a few billion dollars worth of batteries and site them on location. At current costs, today, $1B gets you 5GWh at 1.25GW, roughly. The very cheapest estimate for a cooling system was $7B and they ran to over $10B for a new cooling system [2]. So even without the inevitable cost overruns, one could purchase 35-50GWh and 9-12GW of batteries.
A 40GWh/10GW battery would be a far better grid asset for California, and massive increase reliability far beyond what Diablo Canyon could ever produce.
When the mere cooling system for nuclear is more expensive than a better battery, the technology is dead, dead, dead. We don't need it and we have better alternatives.
[1] https://www.sanluisobispo.com/news/local/environment/article39459930.html https://www.sanluisobispo.com/news/local/environment/article...
[2] https://www.waterboards.ca.gov/water_issues/programs/ocean/cwa316/rcnfpp/docs/subbechcom_111314.pdf https://www.waterboards.ca.gov/water_issues/programs/ocean/c...
- andbberger 6y ago> I think you've got that a bit reversed, trying to fix climate change with nuclear is a bit impossible at this point. We can't build it! Can't or won't?
- epistasis 6y agoIn the US, it's mostly can't. The last attempt caused massive risk to Toshiba as its subsidiary Westinghouse was destroyed by its attempts. In the UK, at Wylfa, it's more "won't", Hitachi just refused to go forward with a new build, since it couldn't find external investors despite very generous guaranteed pricing for its energy. https://www.bbc.com/news/uk-wales-54158091 https://www.bbc.com/news/uk-wales-54158091 At least, it appears to be "won't", because who knows if a construction project that was started would ever be finished. If the new nuclear startups come through, everything has changed. But the new small ones they are designing are not really anything like the nuclear reactors of yore, so we have to wait and see if they pan out on costs. And in the decades they need to come online, storage and solar and wind keep halving in price every few years. But at the moment, pretend you're Jeff Bezos and want to buy $50B of nuclear reactors, however much that ends up in practice. Who do you go to? Toshiba, Hitachi? No. EDF? Hell no. Maybe South Korea? But they had their recent corruption scandal for inspections of nuclear plants. Rosatom? Feel like getting into bed with Putin? What's left of the industry?
- andbberger 6y agoThat was a rhetorical question. But the answer is won't. I submit to you that the economics and historical precedent are utterly irrelevant. It's a simple choice: build more nuclear power plants..... or face extinction
- epistasis 6y agoThat is not the choice at all, and I have yet to see anybody make a serious case for it. There are lots of plans for renewable, carbon free grids out there. Most include nuclear, but not all. Nuclear is not an essential component of any of them, we have many alternatives, the only question is which will provide the cheapest energy. IMHO, it's unlikely to be nuclear, and I think that because those who include nuclear as a part of their future grids vastly underestimate the pace of change for renewables and storage.
- pfdietz 6y agoAs an example, consider this story out of Utah: https://spectra.mhi.com/hydrogen-and-salt-domes-are-winning-the-west-for-renewable-energy https://spectra.mhi.com/hydrogen-and-salt-domes-are-winning-... A single cavity in that salt dome can store 150 GWh of energy, and there's room for 100 cavities.
- epistasis 6y agoI may have underestimate the potential of salt domes... I think we will be making lots of hydrogen for decarbonization of industrial processes, and maybe even for aviation or shipping, so as long as we can dump electrons to Utah and find the water, this sounds great.
- Dylan16807 6y agoSo about 5 hours of power for the entire US, though ~40% efficient?
- 6y ago
- atoav 6y agoThe one thing most people don't realize, is that this is not only about producing energy more cleanly, this will definitly also mean things like driving less (or less individual), eating different, flying way less, making all things more usable etc. And this quite frankly is the harder thing to tackle because it means changing culture. And that culture needed to change not now, but a while ago. If the whole world fully stopped emitting CO2 today, the latency till we could measure the first effect on climate would be roughly 13 years. Most people I know are way too optimistic about what it takes to deal with this. A good way to get a feeling is to play with the sliders of this model here: https://en-roads.climateinteractive.org https://en-roads.climateinteractive.org Edit: this is btw. not something that I am happy with. Like at all. It stresses me out to think about it. People down voting a post that simply states the scientific consensus on that topic doesn't make it any better to be honest.
- AniseAbyss 6y agoAmusingly only the Chinese seem capable to build nuclear powerplants these days. I was doing some research and practically all the sites in use today were built in the 1970s...
- jackjeff 6y agoI really think the economics behind nuclear traditional power plants are a bit screwed. It takes years to build and costs order of magnitudes more than a gas turbines. In addition gas turbines are particularly well suited to be turned on in a mater of minutes whenever there is peak demand. And you still need power when there is no wind or no sun. Unless there is strong support from government, Nuclear Plants can’t happen. I’m really putting a lot of hope in the next generation of mini self contained nuclear plants. I think Bill Gate is also looking into that. These have the potential to be successful both for the planet (get rid of gas turbines for peak demand when renewables fail) but also economically (easier cheaper to build).
- google234123 6y agoFrance is able to produce 70% of their electricity through nuclear. Anyway, you do release the 40GWh electricity purchased would probably come from non-renewables.
- epistasis 6y agoFrance's efforts to come up with a new fleet to replace their current aging fleet have not been successful, they have had as much trouble as the US. They may be able to modify the EPR... but ever year that they fail to have a new more buildable design is another year that renewables and storage get cheaper while nuclear stays the same price or increases in price. I think if you want to bring up a nuclear success story, Canada would be far better. Their CANDU has been really successful, and they haven't yet tried to build a new generation of reactors so they haven't yet failed.
- ClumsyPilot 6y agoUnpack this for me please, they were able to build a fleet of reactors in the past, but no longer can? Is the new design worse, or unbuildable? Old reactors could not be beluilt today? People with all the skills have kicked the bucket?
- dragonwriter 6y agoThe new reactors that are permitted to be built, and that nuclear advocates stake safety claims on, are not economical, at least in the views of potential operators. The old reactors are the things nuclear advocates dismiss and say modern designs are better than on issues like safety and other concerns.
- epistasis 6y agoI would also add that the word is very different Han 50 years ago. Some things have gotten very cheap, some things have stayed the same price. So the technology that looked good, theoretically, in 1970 may not have the same outlook in 2020. In particular, France's failing attempt is the EPR. There have been construction starts at three sites, and all have been massive off schedule. For the three not in China, they have been massively over budget. The build in China was the third to be started, but is the only one completed; planned construction time was 48 months, but it ended up taking twice as long. I don't know how to judge the pricing of construction in China, but if the Western world could do it in 8 years and at the stated cost of $7.5B, it would be a fantastic deal. What has changed since the last time? I don't know. Maybe different sorts of people go into the same jobs. Maybe executive culture is to blame. Maybe engineering culture is to blame. Maybe procurement and construction is to blame. Nobody has provided a solid explanation of X, Y, and Z with concrete examples. Some will say regulations are different and the cause, but at the same time nobody says that these are unnecessary regulations, or that there's a smarter path that would make them cheap, it's always just vague accusations without any specific call to action.
- yourapostasy 6y agoEvery time I hear of heat from power plants and industrial processes treated like waste, I wonder if it can be repurposed to low-grade heat desalination [1], or other co-generation processes [2]. We can always use more potable water, for example. I'm sure they ran the numbers and worked out the opex isn't worth the effort, and/or the capex hurdle is too high. But man, I'd love a tap into that industrial quantity supply of "waste" heat piped just to my backyard. I'd heat my pool in the cold months, run my spa and sauna all the time, and use it to run an absorption chiller the rest of the time. And of course skim some for my hot water heater. [1] https://www.sciencedirect.com/science/article/abs/pii/S0011916409003130 https://www.sciencedirect.com/science/article/abs/pii/S00119... [2] https://www.buildinggreen.com/news-article/capturing-and-distributing-waste-heat-power-generation https://www.buildinggreen.com/news-article/capturing-and-dis...
- epistasis 6y agoI wonder the same thing! District heating would be an excellent use, if you could transport the heat to a site with dense population. But transport is the challenge, and why we convert energy to electricity in the first place. As far as district heating goes though, it could be an absolutely fantastic way to solve the fuel oil problem in the north east; if we could store heat generated in the summer underground in large stores for clusters of houses, it could provide a great way to heat all through winter with simple heat pumps.
- Daishiman 6y agoWell heat transport it, like any other industry, its own niche of expertise. I doubt plant operators suddenly want to turn into distribution experts, and the outsourcing is likely to be way more expensive.
- deleted 6y ago[deleted]
- khuey 6y agoEither climate change is an existential threat to life on this planet or it's not, and if it is we should be willing to discard the OTC regulations for it.
- epistasis 6y agoOf course climate change is an existential threat. But that doesn't mean drop all environmental considerations, especially when we have cost effective tech that passes environmental regulations.
- cbmuser 6y agoRenewables don’t help with climate change. France: 50 Grams CO2 per kWh Germany: 400 Grams CO2 per kWh Germany invested 500 billion Euros for its renewable program the past 20 years.
- tjansen 6y agoThe renewables would have helped, but only if we wouldn't shut down nuclear plants... Effectively we're replacing nuclear power plants with renewables, which was one of the Green party's original goals (they were born out of the anti-nuclear movement).
- adrianN 6y ago1990 a kWh in Germany produced 800g CO2. That 400g figure would look better if instead of replacing nuclear with renewables we would've replaced more coal with renewables, but the political landscape didn't allow that.
- legulere 6y agoFrance has the same problem of aging nuclear reactors that at some point have to be taken down, with problems building new ones in a timely and cost-efficient manner. Flamanville 3 will probably cost 19 billion alone and won’t start regularly generating electricity by at least 2023 with construction having started in 2007.
- EGreg 6y agoWhat about nuclear fusion or thorium reactors? I see the current solar panels generating tons of waste. Along with plastic this is terrible. Why are we so bad at building biodegradeable things?
- cbmuser 6y agoRenewables don’t help with climate change. Germany has 50% renewables in its electricity mix and they’re one of the dirtiest producers of electricity. France emits only 1/7 of the emissions of Germany in its electricity sector. Reducing emissions with nuclear works extremely well and saves lives: > https://www.giss.nasa.gov/research/briefs/kharecha_02/ https://www.giss.nasa.gov/research/briefs/kharecha_02/ Oh, and plants can run well beyond 40 years: > https://www.energy.gov/ne/articles/whats-lifespan-nuclear-reactor-much-longer-you-might-think https://www.energy.gov/ne/articles/whats-lifespan-nuclear-re...
- stinos 6y agoRenewables don’t help with climate change. Germany has 50% renewables in its electricity mix and they’re one of the dirtiest producers of electricity. You're ignoring the other 50% to make broad general claims about the first 50% not helping? That's not correct, on many levels. Moreover 'has in the mix' doesn't equal 'produces locally' so for all we know Germany is just importing all of it, and producing locally only using gas and coal. Which it isn't. tldr; you might have a point, but its way more nuanced than what you're presenting here (without evidence)
- winrid 6y agoIt doesn't cost $12B. That's just what they want to charge. Also, you have to charge those batteries from somewhere...
- njarboe 6y ago"We can't build it!" You should check out the recently approved in the US nuclear reactor by NuScale[1]. It is what everyone has been waiting for. A small (60MW electrical output) reactor built in a factory and shipped to the power plant site. This could be a real game changer. They had to spend $500 million on just paperwork to get it approved, but they did it. [1]https://www.nuscalepower.com/ https://www.nuscalepower.com/
- epistasis 6y agoI have been following this closely, as well as the other nuclear startups. If nuclear becomes buildable again, it will almost certainly because of the efforts of NuScale, Terrapower, or other small scrappy startup. As you say. It would be a game changer, and the game must be changed before we start deploying nuclear. But they haven't built anything yet. It's fairly easy to design something and show that it's safe. The AP1000 got approval, but the designs turned out to be too difficult to build, with the builders saying that some parts of the design were "unconstructable", resulting them in building their own design instead, which then had to get reapproved. NuScale's bet is that factory-based construction will drive down the construction cost to the level that it compensates for the lack of scale that the larger reactors' teams used as justification for going really big.
- njarboe 6y ago"It's fairly easy to design something and show that it's safe." To spend 2 million man hours and 1/2 a billion dollars on creating documentation for certification? I would agree that one never knows if something will be successful until it is, but if it was "fairly easy" to get approval to build working reactors then a lot more people would be building them. I think a way to get a lot more innovation in this space would be to designate an area in the US, maybe the former nuclear testing area, as a place where the radiation protection rules could be relaxed and work on reactors could be done at a much quicker pace.
- pas 6y agoThe problem is not with radiation. It's cost. There's no efficient way of "trying out" a design. Even if we would allow anyone to build almost anything with constant NRC monitoring, the cost would kill the project. (And we wouldn't really gain much insight, because of complexity. This is basically the same problem that we have with the FDA. Yes phase I-II-III clinical trials are expensive, but biology is complicated.) Now, that said, the whole problem is that of scale. There's no real money in building nuclear power plants. It's basically a few fanatics doing it at new and old companies. If the US would announce a 2T USD new plant budget, there would be competition. And even then, probably we would need to build a few very similar plants to have some sort of efficient design.