This is actually a solved problem in some industries using a technique called "3 point analysis". I've no idea why it hasn't really caught on among developers;
by onion2k 13y ago
This is actually a solved problem in some industries using a technique called "3 point analysis". I've no idea why it hasn't really caught on among developers; it's very useful. Essentially it goes like this:
1. Estimate the very best possible outcome. How long would something take if everything went to plan?
2. Estimate the very worst possible outcome. If everything that can go wrong does, how long will the task take?
3. Estimate the most likely outcome. Knowing what you do about the client, the task, the tech, etc, how long is it likely to take.
(Point 3 is the normal way of estimating.)
The advantage of 3 point analysis is that you can use the difference between the times to estimate risk. If the best and worst outcomes are similar, then there's little risk of things going horribly wrong. If the best and the likely times are similar but the worst is much longer then there's something that can completely screw up - identify what that is and defend against it. If the likely and worst times are similar but the best time is much shorter, identify why that's the case and try to make sure it happens. And so on.
Better yet, by taking the aggregate best times for a set of requirements and comparing it against the worst, you can get a good view of the overall risk of a project.
Very useful indeed.
- MetaCosm 13y agoThis is basically your solution: http://imgur.com/YNmKId9 http://imgur.com/YNmKId9 PHB: Use the CRS database to size that market. Dilbert: That data is wrong. PHB: Then use the SIBS database. Dilbert: That data is also wrong. PHB: Can you average them? Dilbert: Sure. I can multiply them too. ----- I kid (sorta). It misses the core issue, why are developers estimates so terrible, 3 terrible estimates don't make a "good" one. The post hits on some of the points, but IMHO misses a major one. Estimations are based on experience, yet developers are constantly building brand new types of products. If all you built was "blog engines" over and over again, you would get damned good at estimating them. The trick in software is as soon as something needs to be reused over and over again, it is abstracted, put in a library, built into a framework, so you can make your product different (read: build something entirely new) -- and EVERYONE sucks at estimating the cost of building things entirely new. Think of the (entirely new in 1962) Lunar Module... they thought it would cost at max 350 million. It cost 2.2 billion. Those where very smart people with a major stake in getting the initial number right, but it was just a crazy ass guess because they had NEVER BUILT ONE BEFORE.
- lobotryas 13y agoYou are absolutely right. It's impossible to estimate how long it will take to complete something you have never done before in your life. Unless the new code being written is absolutely trivial, estimates are going to be guesses, at best. The only half-decent solution I found so far is iterative development. Take a feature and break it down i to big rocks. Further break down the big rocks into little chunks - each that you estimate would take you less than a day to complete. Only after completing your first "big rock" in this way can you use your new data to gauge your velocity and give an estimate for completing the rest of the work that's worth the paper it's written on.
- jacques_chester 13y ago> Take a feature and break it down i to big rocks. Further break down the big rocks into little chunks - each that you estimate would take you less than a day to complete. Experimental psychologists have found that decomposing tasks increases estimate accuracy, regardless of how or why the task is decomposed. It's called the "unpacking effect". http://www.sciencedirect.com/science/article/pii/S002210310300177X http://www.sciencedirect.com/science/article/pii/S0022103103...
- webhat 13y agoUnpacking works great when it's clear what the tasks are going to be. In my experience the bulk of the work does not go into the project or tool itself, i.e. completing the tasks, but rather into resolving issues. I usually estimate that writing the code is anywhere from 10-20% of completing the project. Some research shows that 1 kloc of code contains between 15 and 50 defects, and that code reviewing will pick up only 70-90%. This still leaves a lot of bugs. I sometime ago wrote up some meta research on estimating code reviewing: http://specialbrands.net/2011/10/24/code-review-in-scrum-xp-agile-mathematics/ http://specialbrands.net/2011/10/24/code-review-in-scrum-xp-...
- jacques_chester 13y ago> I usually estimate that writing the code is anywhere from 10-20% of completing the project. McConnell's book has a really excellent table of items that are left out of estimates. Nuts-and-bolts things like "API documentation", "deployment scripts", "status emails" and so on. > This still leaves a lot of bugs. Right. The classical software engineering theory is to build multiple quality gates and to study them for defects yielded. I recall that inspection stomps everything else; automatic testing came second. The problem of time-to-fix is subtly different from time-to-release, though. Software with known defects is regularly in use.
- dspeyer 13y agoIIRC, 1 & 3 are usually the same, and 2 is usually still way too optimistic. And that's from research, not anecdote. It still might be useful. Use 1 to anchor 3 to anchor 2 and then triple it. See also: http://lesswrong.com/lw/jg/planning_fallacy/ http://lesswrong.com/lw/jg/planning_fallacy/
- jacques_chester 13y agoYou've gotten to the first step, which is to provide 3 estimates. The next step is to break estimates into smaller parts, estimate them individually, then roll it back up to build a pseudo-statistical profile of probable outcomes. This is the PERT 3-point estimation technique. It's taught in every project management course in the world. It so happens that almost nobody uses it in practice, because it is a pain in the rear end to do in Excel. It also so happens that I'm working on a tool to make it easy[1]. All I have right now is a landing page, proof-of-concept code and some articles. Oh, and a pile of research papers and books. It's turned out to be a deeper rabbit hole than I expected. [1] http://confidest.com/ http://confidest.com/ edit: how come "professional" is the only word that was spelled wrong on the landing page? Because Murphy is hilarious, that's why.
- nradov 13y agoBuild your tool as a plug-in for existing popular project management tools like Rally. No one will use yours if they have to enter user stories and tasks in two places. I would love a tool that could analyze best / middle / worst case estimates for tasks plus account for predecessor relationships between user stories and generate a probability distribution chart of possible release dates.
- jacques_chester 13y agoI'm aiming to make it interoperable with other tools as a later step (first I need to launch the basic product). But it won't necessarily be a software project tool that's first off the rank.
- ams6110 13y agoIt's turned out to be a deeper rabbit hole than I expected. That's quite ironic, given the subject of this thread....
- jacques_chester 13y agoI keep a list of subjects for articles I want to write for the website. One of them is "Why Research Is Almost Impossible To Estimate".
- ape4 13y agoWhat if the API you are planing on using can't do quite what is needed. But you only find out 2 weeks into the project. That's a worst case but its hard to foresee these things.
- x0x0 13y agothat "solution" is, basically, ridiculous and not adopted for good reason. A quote from Michael O'Church I quite like: Let's say that you have 20 tasks. Each involves rolling a 10-sided die. If it's a 1 through 8, wait that number of minutes. If it's a 9, wait 15 minutes. If it's a 10, wait an hour. How long is this string of tasks going to take? Summing the median time expectancy, we get a sum 110 minutes, because the median time for a task is 5.5 minutes. The actual expected time to completion is 222 minutes, with 5+ hours not being unreasonable if one rolls a lot of 9's and 10's. This is an obvious example where summing the median expected time for the tasks is ridiculous, but it's exactly what people do when they compute time estimates, even though the reality on the field is that the time-cost distribution has a lot more weight on the right. (That is, it's more common for a 6-month project to take 8 months than 4. In statistics-wonk terms, the distribution is log-normal.) Software estimates are generally computed (implicitly) by summing the good-case (25th to 50th percentile) times-to-completion, assuming perfect parallelism with no communication overhead, and with a tendency for unexpected tasks, undocumented responsibilities, and bugs to be overlooked outright. [1] The point is, you are unable to know the worst possible outcome. Since it will have huge input into your average, your average is therefore useless. Perhaps the project isn't specced fully enough and, during implementation, a dev discovers an ugly or impossible feature interaction. You now have to either cut features or rearchitect another feature, ie the dice come up 10 in Michael's analogy. An example from my background: I work on ml code. A learning algorithm was written in parallel with a particular loss function (essentially, this tells you if your estimates are good or bad). The person writing the spec assumed that a different loss function could be dropped in later. Indeed, this is how the math works on paper. But loss function number 2 required a different data layout between the machines. The vision was writing a new loss function should be one or two lines of code dropped into the middle of a hot loop; the reality was it took almost a month of work. [1] https://news.ycombinator.com/item?id=3522910 https://news.ycombinator.com/item?id=3522910
- jacques_chester 13y ago> The point is, you are unable to know the worst possible outcome. Since it will have huge input into your average, your average is therefore useless. Unbounded worst cases don't happen on every project.