A key component of the due diligence you're expecting involves asking developers how long things will take. Savitha is building a new feature with about 2 more
by SpicyLemonZest 4y ago
A key component of the due diligence you're expecting involves asking developers how long things will take. Savitha is building a new feature with about 2 more weeks to go, but it can't be deployed until a guy Jim on some other team deploys suchandsuch dependency upgrade. Should I commit us to a mid-April release date, or will Jim need more time? I don't know, I'd better go ask him.
- lr4444lr 4y agoOf course. What I'm saying is, I see failures IME as Jim putting something into the code base that makes Savitha's work consequently incompatible, which was not surfaced to her as even a possibility when she was asked to give her initial estimate.