> you have a large project, you break it down into smaller parts. If you know what needs to be done, throw it in the backlog, give it a broad estimate, sort it,
by lumost 4y ago
> you have a large project, you break it down into smaller parts. If you know what needs to be done, throw it in the backlog, give it a broad estimate, sort it, and you have an estimate for about how long it will take. If you have unknowns, make resolving them a task. If you need things from the business, give them tasks.
What’s the difference between this and “waterfall” then?
- kube-system 4y agoIt’s a vague todo list instead of a project plan. There are no dates or resources assigned to tasks. And you’re not committed to doing any of it yet. You might change items, add items, or remove items.
- CRConrad 4y ago> What’s the difference between this and “waterfall” then? The difference between this and “traditional waterfall” is that you do this continuously, simultaneously with implementation, and not just once, up-front before building anything. (At least that's the common picture of “waterfall” -- which of course proponents of various “agile” methodologies prefer to contrast their product against -- though IIRC Brooks or someone had proposed / recorded iteration on this in parallel with implementation long before the Agile Manifesto.)