How many times did you take a task you have no idea of the timeframe, do some short research without completing it and was able to make a correct estimate? If
by marcosdumay 4y ago
How many times did you take a task you have no idea of the timeframe, do some short research without completing it and was able to make a correct estimate?
If that happened even once, I would be interested to hear about it.
- Ensorceled 4y agoLiterally all the time. Just had exactly this scenario with a technology switch. I spent an hour reviewing their api. We had a meeting with their sales engineer, I asked them a bunch of questions. Estimated 10-12 days to finish phase one integration, was working in single sprint. Larger projects get more upfront investigation and larger error ranges.