How I started believing in Cycle Time over Estimation
- jacques_chester 6y agoI feel like I'm fulfilling a stereotyped HN commenter role by asking this, but isn't "prediction based on historical data" actually, you know, an estimate?
- whtrbt 6y agoI think the type of estimation meant here is the agile type, where the team looks at a feature/requirement and estimates the time or relative effort based on the nature of the requirement + whatever other factors they choose. It's usually more intuitive and not based on historical data.
- tekkno89 6y agohe also links to a conference talk about this. "you can make a claim that estimates are based on past behavior, but the fact is that what you're implementing is something that hasn't been implemented before. So any kind of measurement that you've made of something that has happened in the past is not going to impact what you're doing now" https://www.youtube.com/watch?v=QVBlnCTu9Ms https://www.youtube.com/watch?v=QVBlnCTu9Ms
- rualca 6y agoI'm rather skeptical on this idea that just because a specific feature was never implemented, or just because a specific bug was never fixed, that estimates based on past behavior don't work. That assertion doesn't have any basis on reality. I mean, implementing a feature of fixing a bug is not an isolated event performed with improvised approaches starting from scratch. Teams have processes and procedures that are standardized and take time, and need to be performed sequentially, which means that the improvisation part at best represents a small subset of the time invested working on a ticket. For a concrete example, let's imagine a team which has a continuous delivery pipeline which involves a code review step and manual acceptance tests. Let's say that the code review can stay in a queue for a couple of hours, or even sleep into the next day, and that the manual acceptance tests require the feature to be deployed to a preprod stage after passing through all unit and integration tests, and that it might take a day to run. With this process alone, the ticket already takes at least 2 or 3 days between being assigned to someone and being marked as done. Now, let's say that the coding bit of a random ticket might take 5 minutes or 3 days. This means that the overall time between the start and end time of a ticket is about 4 days +- 2day, which means worse case scenario, it takes 6 days to close a ticket. How is this sort of estimate not possible? The problem of providing estimates is not one of predicting the amount of time it takes to close a ticket. The problem of providing estimates is a problem of processes, and how to adequately organize, structure, and classify work. If you don't know what you're doing then you don't know when you're done.
- xchaotic 6y agoYeah, I think the problem the OP overlooked is that most of the cycle time was taken by various internal company processes and these are really not novel every time therefore it takes a similar amount of time to deliver different features. This in my mind is simply called estimation.
- sitkack 6y agoThe external clock is going to be some multiple of the internal clock and tasks were piling up behind contended locks. The ferrari and the skateboard make it through rush hour traffic at the same speed.
- snorberhuis 6y agoGood point you hardly ever start with a clean slate. Using historical data or asking engineers to estimate how long it will take will always be based upon this past performance. But the point I try to make is that it is hard to take into account all the factors you have to deal with in a complex situation. As a human, you tend to ignore irregular influences. With tracking tools, you get this data right out of the box and it is more accurate in my opinion.
- snorberhuis 6y agoThank you for your question! Yes, I try to make the distinction between prediction looking at historical data and estimation asking the engineers how long it will take.
- sitkack 6y agoI couldn't read all the text, but I believe the metapoint is that the need for accurate estimates drop as the cycle time is reduced. It is all about feedback. My analogy is an old analog style joystick that positions a simulated robot arm on a screen. If the update rate is high enough I can track a rapidly moving dot, but if it drops across some threshold, and I needed to accurately position the arm at some time in the future, then I would need to construct a huge model of the system, know the force, stiction, friction, mass, moment and thermal expansion. (edit, I have another analogy, anyone can spray a moving target with a hose, but using a bow and arrow requires skill and practice) Feedback allows us to use unpredictable components to make predictable systems. Those systems are nearly always amplifiers. Systems that use direct feedback don't have to have the same reductionist model as something that needs better prediction (estimates). This is why Lisp was a super power in the 80s, it had a repl. Same as Smalltalk, the IDE and repl and the universe were all the same thing. It makes total sense that agile came out of a system based around repls and instant feedback. Arduino did it for embedded dev. Hypercard for programming, the spreadsheet before that. Highbandwidth feedback allows us to be less skilled. Good estimators need to be highly skilled to make those estimates. Hose vs arrow. That reminds me, have you seen a really skilled FPS player on a predictable but high ping connection? They are almost timeless in how they predict the future, and to everyone else they dance between every 10th frame. Amazing predictors! You can't agile a martian probe (yet). As new ways are discovered to reduce cycle times, the time between cause and effect, each proceeding structure of feedback is replaced with an even higher bandwidth one. Robust DFU is a metarepl as hardware manufactures race to ship products that are literally not finished and require a firmware update on boot to even function.
- jacques_chester 6y agoI just wanted to reply to say this was a great explanation and that I broadly agree.
- sitkack 6y agoThanks for the feedback. Quip aside, I also learned a lot writing it. Always bet on the Scientific Method and if we know something works, we should have to justify not using it.
- groby_b 6y agoI am still not clear at all how "cycle time" is a meaningful measure without correcting for size of the feature. I'm also confused as to how you can look at "mean of one week, with a standard deviation of two weeks" and not wonder about the asymmetry of the distribution, and if mean/sd are really the metrics of choice here. (I'd think 1st/3rd quartile are a better choice, because it gives some clue as to skewedness)
- lmm 6y agoI'd say SD is a much better measure here, precisely because that big standard deviation jumps out at you. My guess would be that the 3rd quartile is some sensible-sounding number like 1.2 weeks but there are some huge outliers pulling up the SD.
- snorberhuis 6y agoI agree that the Standard Deviation is a good measurement because of the big outliers. We also focus on these during retro. What made us remarkably slow? You want to drive down these issues. This investigation can help you in future work. I worked with another team that was consistently slow if they would need to build new pipelines or get connections up and running to third parties(heavy regulated environment). This insight helped us in planning.
- judofyr 6y agoI'm guessing it's a good metric here because most of their tasks are small tasks that only takes a few hours to complete (in code) and then the average Cycle Time becomes the average overhead for getting a fix into production.
- pointyfence 6y agoWe had a much more primitive version of this for our product roadmap. After working with mostly the same dev team for a few years, we felt that in a given year we seem to consistently be able to complete X “big” projects, Y “mediums” and Z “smalls” despite all the random stuff that invariably pops up. So that list was the spine of our annual planning, the stuff that we really prioritized. The rest of the stuff that people wanted to do would have to fall in between the gaps of that master set. It worked surprisingly well for us, but we had to build this group experience first. After a few years with another dev team at another company, I brought it up as an alternative to over ambitious roadmaps and it worked well there too. How much of this was just due to more team familiarity and experience or this oversimplified process? Don’t know. But it felt like the roadmap trade offs were more thoughtful, devs felt more relaxed and had reserves if we had to red line a bit, and fewer missed commitments.
- ohthehugemanate 6y agothis is the recommended way to plan time in scrum and many other agile implementations. You're just using "T shirt sizes" rather than "story points". It's recommended because it's quite accurate, as you've found!
- judofyr 6y agoThe gist of this article is good. Fixing the code is often the smallest part of rolling out a bug fix. That's extremely important to be aware of. Using historical data can be a great way of seeing how fast you can actually roll out changes. But I don't get how they went from that to "estimations are bad". It seems to me that they're just doing better estimations now by looking at historical data? > I could tell confusion from the look of my team lead. How could I say it would take over five days for a change that we estimate to take 10 minutes! Isn't this like comparing apples and oranges? The estimation of 10 minutes is clearly "the time it takes to flip the flag", but what they actually want to estimate is "the time it takes to make it into production in a safe manner". Maybe the team leader is confused because they thought this was a man-hour estimation? And they're now afraid that one developer will work full-time five days on it? > On Monday, we started with the stand-up and discussed picking up this task. Another engineer proposed fixing a bug on another component first before turning on the flag. Doesn't this imply that their 10 minute estimation was done completely without asking the team? > As humans, it is impossible to consider all the potential complexity. […] We did not consider a legacy system with bugs and scaling problems. […] We did not consider a combined release process with a Release Manager. Really? You couldn't consider the complexity of a release process you designed yourself? You honestly thought this was a 10 minute task even though you knew you were dealing with a legacy system?
- qznc 6y agoThe distinction between effort (man hours) and lead time gets lost often. Clueless managers ask for the first and take it for later.
- snorberhuis 6y agoThank you for your comment! > But I don't get how they went from that to "estimations are bad". It seems to me that they're just doing better estimations now by looking at historical data? For me personally, I went from estimations are just really poor even for the most simple things and not worth the effort. It is correct that is can still be seen as migrating to a better form of estimation. If you look at the conference talk by Allen Holub[1]. He tries to make the distinction between estimation and prediction is that the latter is only data driven. > Maybe the team leader is confused because they thought this was a man-hour estimation? And they're now afraid that one developer will work full-time five days on it? That could be the case. I never looked at it that way. > Doesn't this imply that their 10 minute estimation was done completely without asking the team? Yes, it was done with just the team lead and me. We migrated away from Scrum at that point and we did not do full team refinement with estimations sessions pre-sprint. We would collaborate on the technical solution for any story when we would pick it. This could be full team to two engineers. The engineer that brought up the bug would probably bring up the bug. > Really? You couldn't consider the complexity of a release process you designed yourself? You honestly thought this was a 10 minute task even though you knew you were dealing with a legacy system? Yes, I honestly did! It was just a simple code change in our terraform code to set the config from false to true and cycle the machines. I should clarify this more in the story. [1] https://www.youtube.com/watch?v=QVBlnCTu9Ms&t=1s https://www.youtube.com/watch?v=QVBlnCTu9Ms&t=1s
- cheschire 6y agoSounds more like a case for using cycle time as a checksum to make sure the team’s estimates are fully considered. They’re clearly missing 4 days of standard requirements in their estimates.
- deleted 6y ago[deleted]
- snorberhuis 6y agoI am the author of the story. I appreciate any feedback so that I learn from you! I will be participating in the discussion.
- choeger 6y agoIn my experience, you need both numbers. A customer naturally wants to know when a change arrives in production. I call this "latency", you call it cycle time, but maybe there is a small difference because I also try to include the time it takes to even start development. But a customer also wants to know about effort, often. Because usually effort is what gets billed. So a 10min (realistically, the bill we be about an hour, won't it ;) ) change has a five day latency, which is actually a relatively fast pace for a legacy system with many different stakeholders.
- snorberhuis 6y agoGood point, I agree that you need both numbers. This story is only about the latency.
- fn1 6y agoWhat works well for me: 1. Split the project into tasks. (a task taking at least 3-5 PTs) 2. Have a POC / prerelease phase 3. For complex tasks introduce a second polishing task, like "Basic User management 1/2" and later "Basic User management 2/2". If the second one isn't needed: Great! 4. For all tasks/areas estimate a lower and an upper estimation in hours or PT. 5. Revisit your estimation afterwards using this process: 5.1. Imagined that someones gives you the following choice: You get 1000$ if your the true value lies within your estimation 90% of the time. Or you can roll a dice and in 9/10 you get the 1000$. 5.2 If confidently pick your estimation ("I'm 100% sure the true value is within my bounds") then it's too wide. 5.3 If you rather pick the dice-roll, then you don't trust your estimation, it's too narrow. 5.4 Adjust your estimation until both options seem equally probable to you: dice-roll or your estimate being true 90% of the time.
- ohthehugemanate 6y agoThe benefits described here are achieved by ANY abstracted estimation system. Ask people to estimate in units of difficulty, complexity, cups of coffee, whatever. Keep those units consistent relative to each other (a 4 cup task looks roughly twice as big as a 2 cup task, in advance). Track the relationship between units and hour/days over several sprints, and your average automatically factors in all the external things like team collisions, illness, developer downtime, refactoring, bugfixes, release process, etc. The research shows that the law of large numbers makes this MUCH more accurate than pure time estimation. (time estimation is extremely difficult to get correct more than about 35% of the time; averages of consistent units are correct enough to run a casino budget). The scrum people will tell you to call this unit "story points", but it doesn't matter what you call it, as long as it's based on something connected to task duration. Difficulty, complexity, risk, whatever. Note that if you're tracking the conversion rate between developer estimated hours and real hours, you're already doing this. But you'll get an increased accuracy by using units that are explicitly not time-related, just because of quirks in how human brains think about time.
- eyelidlessness 6y agoThe detachment of individual deliverables from estimates is definitely an improvement but I honestly think the notion of even hand waving estimation is a bad idea with harmful consequences. Measure velocity for sure. Keep track of what kinds of things harm or improve it. But the absolute worst thing you can do is find an abstraction like tshirt size or rolling average and superimpose it on discreet work. You’re going to be wrong. And probably disappointed or disappoint someone else. My strategy for estimation is: - It’s tiny and I’m doing it now, I can give you an estimate within an hour margin. - It’s small, it’ll be done in a reasonable amount of time that no further estimation is required. - It’s not small and more research/design/planning is required. Any estimate you extrapolate from this is dishonest. That’s it. Edit: that wasn’t quite all. “It’s tiny” is reserved for urgent situations that require rapid response and not something I offer outside that situation. For daily work, it’s small or it’s too big to say. Tiny things are too easy to abuse (by managers or engineers) if they’re part of the normal flow.