Driving engineers to an arbitrary date is a value destroying mistake
- hvs 7y agoWhat ever this is, the use of colors, arrows, bad clip-art, and everything else just yells, "DON'T LISTEN TO ME."
- throwaway3563 7y agoThe slide at the bottom has “non-technical executive hocus-pocus” written all over it but I thought the rest of the content was sound.
- fsloth 7y agoYou need some estimates if you need to sync the efforts of two or more teams. For single teams with single deliverable there might be a necessity to set a date, or might not. But if there is no external reason to push for a date then setting an arbitrary internal date when it provides no additional value is just silly.
- convolvatron 7y agobeen thinking about this because my current project has suffered from management repeatedly setting unreasonable dates. which causes flailing to get stuff put in, and then we the date finally gets moved out, more stuff to paper over that crappy stuff. but you have to admit that without a date developers will just noodle around forever. I think the only recourse is to constantly be evaluating the current slate and the date and keep sliding it out as necessary or throw stuff off the train. really, you should never miss a date. you should have realized some time ago that it wasn't going to happen and slid it out already.
- Twisol 7y ago> you have to admit that without a date developers will just noodle around forever. This seems more a statement about extrinsic motivation than dates in particular. Dates are the most obvious blunt instrument for applying extrinsic motivation, but there are others. Intrinsic motivation is in some ways even better. You can't force someone to be intrinsically motivated to achieve something... but pushy dates and expectations can decimate any motivation that was already there.
- fsloth 7y ago"but you have to admit that without a date developers will just noodle around forever." Speaking for myself as a software engineer I have only seldom fixed dates and deliver constantly. My main goal is to deliver value to the party I work for and my end users. True artists ship. On the other hand, I do stall occasionally. It's because I don't understand something, and rather than just ship some random junk I try to make my junk do the right thing. To an outside observer this carefull design - engineering if you will - is quite indistinguishable from noodling. If you put an arbitrary date for me then you will just get bad code and that is a bad deal for everyone. There are times when the date is fixed. Then you haul ass and raze mountains to ship, no matter how ugly the result. If the date is constantly set to some random date I have no idea should I dial quality down and increase velocity or vice versa. Therefore a constant fixed date will just get worse quality, even if there was no good reason to hurry. I think you meant to say how to have enough transparency so that everyone is honest and accountable. You don't need imaginary dates for that. Just have people report at fixed cadence what they've done. Good people remember they need to explain what they've done and dont wander off into the wilderness for no good reason. This is sufficient to keep everyone on the right track in almost any environment. Now you say - "Aha! But what about the occasional person who is incapable of doing their job! How do we point him out!" - to which I answer: If you need to design your development process to safeguard against botched hiring since they seem to do it constantly you really need to fix your hiring. Good people will detect a rotten egg eventually and there should be ways to deal with this outside of regular project cadence. If you try to micromanage great engineers and programmers you are just wasting talent and eventually everyone will just move on and all you have left are the rotten eggs.
- deleted 7y ago[deleted]
- commandlinefan 7y agoLazy thinkers like to measure dates because they're easy to measure. I don't think I've ever, in my professional career, seen a date get "hit" - by me or by anybody else - and I've also never seen it matter.
- Etheryte 7y agoI think there is a bigger picture takeaway to be made here, but I'm not sure if I can phrase it too well. The Douglas Adams "I love the whooshing noise [deadlines] make as they go by" quote is perhaps a good introduction. I think the general concept starts out in education, deliver this by date that or there's consequences. And in that moment, the consequences tend to be very real, and if you prefer a smoother ride, not something you want to deal with. What starts out as a way to teach both discipline and whatever it is you're currently learning will then go on to accompany you in your professional life. In reality, in software development all deadlines are pretty much arbitrary. Sure, there is profit to be made if you move quicker, but there's considerably more profit to be made if you move in the right direction instead of just moving quickly. The latter tends to often be overlooked in the management style outlined in the article. I think the healthy choice is to estimate, but not stress over the situation. Your estimate is not a promise, and make that very clear when you do give one. If your estimates are taken to be promises, it isn't probably an environment you want to work in for long.
- recursive 7y ago> I've also never seen it matter. It matters plenty of times. If Turbo Tax doesn't ship their 20xx edition by Jan 1 20xx, they're losing sales. I also work on (non-tax-related) software that is tied to specific dates by regulations coming into effect on certain dates. I don't think this is rare.
- typl 7y agoBob Martin's new book "Clean Agile" covers this topic well. The problem isn't dates or deadlines, it's arbitrary dates or deadlines that are not backed up by data that indicates whether or not they are achievable. Often we create estimates with no prior knowledge of the team composition and particularly their ability to apply their skills to the problem at hand. The only way to make good estimates is to give them work, let them start doing it, and observe their progress. You then can manipulate the scope of your project to determine what you want done (the highest value things) and estimate when you can get those things. The alternative levers (add a bunch of people, sacrifice quality) end up not working in software projects and become the "value destroying mistakes."
- dasil003 7y agoThis post highlights the importance of competent technical management. The problem is not arbitrary dates, it's unreasonable dates with inappropriate feedback loops and lack of trust throughout the management chain. The example given is a strawman of a classic cigar-chomping executive whose philosophy comes largely from unskilled, fungible-labor economies. Taking away the date is definitely not the right move. Now you've given every PM and sales guy carte blanche to throw whatever flavor-of-the-moment idea comes in their head. The team will be churning constantly to keep up with the requirements and then someone will suggest, "I know, let's do scrum!" so now we can all enjoy the stress of unreasonable deadlines on a continuous rather than waterfall basis. To the contrary: a properly-managed date is an incredibly valuable constraint which the entire team can use to make tradeoffs against. To make it work management needs to trust the team, and engineers need to understand the larger business picture because they are the ones with the knowledge to find creative solutions that actually work and decrease time to value without compromising technical quality or long-term maintainability.
- routerl 7y agoI recently found myself in the position you described, to a T. And we did end up switching to scrum... I've left that company after having been unable to fix the situation, which was ultimately a political problem; as you said, we had an "executive whose philosophy comes largely from unskilled, fungible-labor economies". Is this fixable, or is "leave" the only right answer?
- deleted 7y ago[deleted]
- AnimalMuppet 7y agoNo, "leave" is not the only answer. "Fire the executive" also works. But to actually make that happen, there has to be someone with authority do actually do the firing, and that person needs to understand the problem...
- emeerson 7y agoStrongly agree with this. Dates serve a critical goalpost in technical planning, yet they should be viewed as flexible (having a reasonable margin of error) and informed by tight & trust-driven feedback loops. I subscribe to Gantt charts as a planning tool, not a bible. Use it to empower development teams to plan and track execution, but don't use it for 0-margin accounting. One anti-pattern in engineering management is shielding engineers entirely from timeline estimates. A CEO with limited runway, reporting to the Board, doesn't have such a luxury of infinitely elastic time. Edit: Note: dates should never be prioritized over value. If you're hitting dates and not delivering value then it won't do good for anyone. Product value should always be the function to optimize for, but rarely is it entirely independent of time.
- kabdib 7y agoConfession time: In 40+ years of doing software, I've met my schedule once. Actually, that's a lie. I missed by a week on a 150-day long project, my very first project at my very first real company, and that's the closest I ever got with my own estimates. And on that project, marketing wanted it pulled into 30 days (and to hit that 150 days I was doing all-nighters and basically killing myself, so it wasn't a very good schedule to begin with). [For the curious, it was a game cartridge]. The real losers of "schedule chicken" are the customers, who receive buggy and bad products. The company will suffer long product update cycles because of the effort needed to stay ahead of the quality debt. Explaining this to a manager who's never even read even one of his copies of The Mythical Man-Month can be tough. Things aren't necessarily better when you let a project freewheel. "You'll ship someday, just do a good job and get it right" doesn't necessarily translate into the urgency to ship a product, and I've seen efforts on the scale of tens of millions of dollars fail. Other arbitrary dates include things like shows (well, what is the real cost of missing that show versus shipping something buggy to bad reviews?) or holidays (hitting Christmas used to be a good excuse for schedule pressure in the game industry, much less of an excuse now). [Anecdata: Years ago there was a manager at Microsoft who told his team to ship by some arbitrary date, which turned out to be when he was planning to go on a long vacation. I'm happy to say that Microsoft fired him.]
- commandlinefan 7y ago> I was doing all-nighters and basically killing myself I often suspect that the true goal of most time-estimation exercises is to guilt you into working unsustainable amounts of unpaid overtime.
- xupybd 7y agoI honestly don't think so. Companies have finite resources and need to allocate their use efficiently. That's hard to do when you don't know how long it will take / how much it will cost. If you don't think you have the money to meet the estimated project time you need to find ways to reduce the time. Sadly that leads to problems as described in the article. The is an impedance miss match between software development and real world business reality.
- cjohnson318 7y agoLike, sure, if you want me to write Hello World, then I can give you a snappy timeline for that. If you want a POC of something very few people have ever implemented before, then that's going to take about a week. If you want that POC to be ready for production, then that's going to take a lot longer than you're comfortable with to test and develop.
- shkkmo 7y agoThe solution in this hypothetical is that the technical manager should have pushed back on efforts to squash estimates, and instead gotten the feature set reduced down to what would fit inside the desired launch window.
- commandlinefan 7y agoI've seen that tried, I've never seen it actually work. What I've always seen happen is, they'll ask if X can be worked into the schedule, the devs will say no, it can't. Then the next day, they'll ask if X can be worked into the schedule (usually phrased just a little bit differently than before), and the devs will say no, it can't. Then a week later, they'll ask if X can be worked into the schedule. Then, when the devs say no, it can't, they accuse the devs of pushing back on everything, so the devs finally roll their eyes and agree to X (knowing that it's impossible to deliver because it's not even defined, but who cares because nothing ever happens when you inevitably miss the dates anyway). Then the next day, they ask if Y can be worked into the schedule...
- cfmcdonald 7y agoIt can work. There does need to be mutual trust between product leadership and engineering. e.g. in the case you described, the engineers need to be able to communicate without fear that X1 and X2 are basically the same engineering work as X, and still can't be accommodated, and the other side needs to trust that they are not just being lazy.
- MaulingMonkey 7y ago"No" can be interpreted as pure obstinence. "We can do X... I suspect we'll need at least N weeks after we have a proper scope/spec/X/Y/Z from you, though, so if you want it done by $(MILESTONE) we need it by $(MILESTONE-N) at the absolute latest, or more preferrably by $(PREVIOUS_PLANNING_MEETING) so we have some wiggle room. No, that's not a spec. Yes, you need to participate in defining the scope of this thing - otherwise it'll take even longer when we're forced to rework completed things to work how you actually wanted them, and longer still when we work on things we thought you'd find important but don't care about. When can you meet so we can get this properly defined and fleshed out? We need a meeting anyways to discuss what other things you want that we're going to have to cut or defer to fit this into the schedule as well." If they work with you to cut/defer other things they've asked for and actually get you a scope/spec/X/Y/Z on-time, then good! You've successfully responded to a change in their priorities. If they suddenly lose interest when they might have to do some work... you've probably deflected some high work low value ask. Also good! If they put in the work but can't get you scope/spec/X/Y/Z in time... well, hey, that's not on you. You need enough time to get these things done. They might still want 3 women to make a baby in 1 month... but they might believe you when you say that's not possible if you at least look like you're trying to work with them on fitting X into the schedule.
- wwarner 7y agoI think the article lacks nuance. Of course, asking devs to guess at how long something will take at the very beginning of a project is not going to be very accurate. That doesn't mean that sticking to a schedule has no value. Basically, the project plan has to allow for some scope cutting along the way. There will always be a few false assumptions that are discovered only after the project is well underway, and the only way to manage that is minimize the surface area of any given dependency. The responsibility of delivering a project on time belongs to the manager (which for the purposes of this comment can belong to an IC if she or he decides to think like a manager). For every milestone on the schedule, the manager should know all the risks for reaching the milestone and should have a plan for handling each eventuality. This type of planning goes hand in hand with protecting the team from distractions, preventing scope creep at all costs, and setting the goals of the project before it has even started. Software created with time constraints is higher quality and is more fun to make.
- wwarner 7y agoContrast with Patrick Collison's essay on the value of speed. https://patrickcollison.com/fast https://patrickcollison.com/fast
- temac 7y agoThis is not an essay, this is a bunch of anecdotes. So projects that worked reasonably well and developed very fast, or even just somehow fast, are presented. Everybody agrees that's good and a success and better than if they were done slower; but so what? Some are great major engineering projects, but in the context of extreme speed there is a world between a few weeks or even months, and more than 5 years, even if you compare the 5 years in question to project that are a parody in the other direction (yeah, a train project that is planned for 37 years looks ridiculous, but again so what? is it really because diva engineers want to spend all their careers doing "perfect" stuff and reject any deadline they are presented? doubtful) Also, some are successful, but controversial (JS...); some I don't even know what to think about (is growing the population of a city by 22% in a year good?); some are just the work of geniuses. And this is a mix of major physical infrastructure/engineering projects, projects for mass produced physical goods, and random software projects. Then suddenly the discussion focuses on physical infrastructure, ignoring all the other kind without even stating why. This is also hard to contrast with the original article, because we don't know how many of them were mainly date driven. Probably not so much, in the sense that it would be retarded to insist on delivering something that cost a shitload of money to build at a completely arbitrary date without enough concern about the quality. Too finish: some insane major infrastructure projects have been successful in the modern age: what comes to mind is for example the LHC, yes it took quite some time but it is probably somewhat more difficult to design than a random consumer electronic gadget? (is the story of the iPod that much spectacular? I found it quite common...)
- Tomte 7y agoI used to work for a company where important deadlines and release dates were often cast in concrete. At the birth date of the former CEO (husband of the current CEO) who had tragically died many years before. So if your "natural" release date was a few weeks after that birthday, it was definitely on that birthday. You only had a chance to escape that if your "natural" release date was months apart from the birthday. But then again, this company never ever hired anyone without a positive graphological expert's report.
- seph-reed 7y agoTotal aesthetic digression: Having the topbar offset inversely based off ~1.5x the scroll position is one of the coolest effects I've seen for hiding top bars. I like this a lot more than the sticky style that most things use.
- brightball 7y agoThis hits on exactly why I was drawn to SAFe. After all the feedback I got from this... https://news.ycombinator.com/item?id=17154355 https://news.ycombinator.com/item?id=17154355 Someone pointed me to Reinertsen's Principles of Product Development Flow book, which put into numbers and models everything I'd been trying to say (and then some). It worked great with my team, but I was failing hard at communicating and involving everyone on the business side so I started researching for something that provided the business side, wrapped around his methods. Which drew me to Scaled Agile Framework. There's a lot in it, but the core of it is simply on a pace of 8-12 week increments, you spend 2 days letting your developers provide you with a plan, estimated based on 2/3 of their actual available time. They make the plan...not management. The plan is presented to management, management discusses tradeoffs and options, then ultimately management will accept a final plan and the developers provide a confidence level in their ability to deliver the plan that they have set out. When new requests come in, they are discussed for the next 8-12 week increment so the developers can focus on executing the plan that everyone agreed on. There's still room left for small things that come up, there are progress check-ins and communications that happen along the way. Risks to the plan are identified and discussed so everyone is aware of them up front. Variability is assumed (up and down) throughout the plan. The only assumed commitment is to the 8-12 week deliverable. Nothing in between is expected to have a guaranteed delivery date. It leaves little room for surprises and plenty of room for people to work in a reasonable manner. I can't speak highly enough of how effective it is to addressing this problem.
- andi999 7y agoYou should multiply the plan of the developers by 3-4 before presenting to management. So management can cut to factor of 2-3 and you will barely reach it. I never met a developer who doesnt underestimate the effort needed by a vast amount. (including myself)
- brightball 7y agoManagement doesn’t get to cut the plan. They get to ask “what if we don’t do this, would it be possible to get this instead?” There’s no “we said it will take X” and management saying “do it in X/3”. That’s no longer a plan made by developers that developers are comfortable standing behind. Over 10 weeks, you would plan based on 2/3 of time for 8 weeks, with nothing planned in the final 2. If things are running behind, this becomes buffer to finish it out. If things are finished on schedule by the 8 week mark then the final 2 weeks becomes time for developers to pursue other things. Training, prototyping things they’ve wanted to build, whatever. It’s the old Google 20% time concept built into each increment.
- xupybd 7y agoI had this happen. First time I'd used a framework for more than a few screens. Totally new way of doing things. Learning RXJS, made a mistake in understanding one of the more strange requirements. Time blew out. But the delivery date was 3 months. Worked crazy hours, product didn't ship the entire thing was seen as a failure. I was burnt out for a good 6 months after that. Even simple tasks took all of my will power to do. It was horrible. 3 months of the hardest work I've done and considered a failure for it.
- 7532yahoogmail 7y agoSoftware dev 20+ years: management is right to ask for estimates. It's ok for engineers to write a throwaway design paper to "get into" the problem before turning to jira epics and stories. It's also right for engineers to reject arbitrary dates, pressure to cut corners and so on. But this or the ops story absolutely don't get anybody anywhere. You wanna move beyond anecdotes and nice sounding business arguments? Read FIRO by Dr. Schutz prob out of print or "Human element" by same. His son Ethan has updated these books. Look, in normal high functioning groups conflict is normal. What confers distinction there is two things: - no individual on team is ridgid and unchanging - conflict is resolved with 100pct buy-in ie not cause the boss yelled, or you were out gamed, politics, favourites. IOW there is trust in the team (together with self awareness, competence etc which the book hits on) When human factors burn down projects down the issues are quite a bit more about trust, individual self awareness, defensive behaviors, and not resolving the problem in a group way. Trying to eliminate conflict with rules of thumbs is a fool's errand. Conflict itself is not a sign of badness. References to organizational modalities (the strong boss, the clear vision, and similar sounding approaches) help at the margins only and then only randomly.
- colechristensen 7y agoI don't know about 100% buy-in. Maybe it is just lacking nuance but being ok with going forward in a direction you don't agree with is important in a team. Disagreement is good, it gets you better results in a healthy environment, and it doesn't have to end to make a decision. The signs of a good compromise is everybody leaves unhappy about something. Not that products should be built entirely on compromise... that also leads to garbage. It is difficult to pick the pieces apart, but frequent strong-armed conflict resolution is definitely a sign of a bad environment.
- btilly 7y ago100% buy in is right. See https://en.wikipedia.org/wiki/Disagree_and_commit https://en.wikipedia.org/wiki/Disagree_and_commit for a list of successful organizations that have adopted a principle meaning that and why they did it.
- petedoyle 7y ago> "We believe that communicating dates produces the wrong incentives. What really matters on a long timescale is 1) priorities and 2) velocity." [1] I saw this written during the 2017 cryptocurrency craze. Has stuck with me as one of the most insightful things I've ever read. Also a fan of 37 Signals' budgets. [2] [1] https://medium.com/graphprotocol/introducing-the-graph-4a281b28203e https://medium.com/graphprotocol/introducing-the-graph-4a281... [2] https://signalvnoise.com/posts/3746-drive-development-with-budgets-not-estimates https://signalvnoise.com/posts/3746-drive-development-with-b...
- john_moscow 7y agoAs a person who runs a small software business, coding most of the functionality myself, I actually disagree with the article. There is a huge value in setting deadlines because they force you to prioritize things. Once you realize that you don't have the time to ship features X, Y and Z, you start comparing their impact/complexity/risks, pick the most beneficial one, and ship it before it's too late. Without prioritization it's very easy to get stuck in a loop of endlessly adding small improvements/testing new ideas, but never releasing the final sellable product. There are a few notorious examples from the game industry where no time pressure lead to either no product, or a hopelessly late-to-market product (e.g. Half-Life 3, Duke Nukem Forever). There are more smaller examples where entire teams endlessly juggle the code between web frameworks, as they come in and out of fashion, and neglect more user-impacting features. That said, most of time pressure should only be applied at the decision-making level. Once you have decided to ship feature X with framework Y, it's useless to nag on your devs to do it in half the time by dropping unit tests, or doing 60-hour work weeks. Instead, you should have picked feature Z with 50% the complexity and 80% user impact.
- NullPrefix 7y ago>Half-Life 3 I'm not sure they even worked on it, have they?
- ShamelessC 7y agoThey worked on Half Life 2: Episode 3 for awhile before giving up. There was also a leak of unfinished Half Life 3 source code in 2014 (I think). After the release of Half Life Alyx a few months ago, they have heavily implied a recommitment to Half Life 3 in interviews.
- silentific 7y ago"Arbitrary date". Deadlines are still important.
- tikhonj 7y agoPrioritization is the key thing. I have a simple rule of thumb: a deadline is a "real deadline" if I would reduce scope to hit the deadline. A deadline is just a goal if I would not be able (or willing) to reduce scope to hit it. Treating a date as an absolute deadline without being able to adjust scope is where productive work gets totally derailed.
- uberdru 7y agoThe lost art of 'scoping'.
- at_a_remove 7y agoEstimates are never good enough, when asked you're supposed to tell them two weeks before their guess. I recollect one project with a hard deadline. This landed in my lap during a worthless business trip while I had a fairly serious cold. I had about five weeks, all on my lonesome. It was critical. I had no time and no energy but tackle it I did. I had precisely one meeting with the person who issued the project, during which he made various Agile noises. This taught me something I would later come to expect about those sounds: I met with the stakeholders precisely zero times before delivery, despite my repeated asks. I worked evenings and I worked weekends to deliver something on time that was perhaps a little better than expected. And crickets. For five long months, nothing. I asked tentatively and was told I got paid whether or not it was in use. So this strangled two values for me: Deadlines, certainly. If I hear a deadline, I evaluate from where it came. If it is a nonsense deadline, I lose respect. False urgency is just a way of life with some people. Additionally, the "getting paid whether or not something was used" is an excellent way to develop apathy in an employee, it destroys the value of engagement. Sometimes real dates exist, and I'm all for that. Floods can be expected. But too often dates are picked out of a hat.
- mmcnl 7y agoIt annoys me so much that many people think software development is misunderstood. You think people in other types of business don't have to give estimates based on almost nothing? This happens everywhere, anywhere. But somehow software engineers think they are special and are being treated super unfairly. Giving estimates for software dev is 10x easier than giving estimates on the usual vague business problems management is facing (the same management that's always responsible for everything that is wrong, according to most software developers). Yet I don't hear "management" complaining about that. Software devs are not royalty.
- redis_mlc 7y agoYou made 2 major mistakes: 1) > Giving estimates for software dev is 10x easier No, it's not. If I'm writing software similar to another project, then I can estimate based on the previous project. But that's rare. Instead it's something entirely different, otherwise I'd be able to juse reuse the previous project. In addition, estimating eng. projects like bridges is easy, because bridges obey physical laws, like gravity. That doesn't apply to software. 2) > the same management that's always responsible for everything that is wrong Ultimately, mgmt. is responsible. However, mgmt. being at the apex can and do bury their mistakes, no matter how large. As we found out in 2008, there is no criminal penalty for mgmt. stupidity, regardless of how extreme. A case in point is Boeing. They kill 350 passengers and damage America's trade balance, yet their new CEO is from the same board that was responsible. Mgmt. has no accountability, in the US anyway.
- freepor 7y agoIf you are paying people on a schedule you need to have at least a rough understanding of what they can produce on a schedule. The best illustration of this is client work that is paid "by the job" -- you need to understand what you can produce to have any idea how to bid.
- madeofpalk 7y ago> While it is true that a narrow set of low value software projects are tamable with a Gantt chart, high value software projects that fill previously unmet needs do not lend themselves to being tamable by predictive scheduling techniques. I think the author vastly overestimates the value and importance of project that most developers work on. I don’t think I’ve ever worked on anything that I could consider “high value”. I’ve worked in big (and small) companies, working on Big Important Projects, but if I’m being realistic I think the overall value and actual importance is actually quite low. Other than that, I think the essay has a fatal misunderstanding - it’s not about setting deadlines, but it’s about estimating what it costs to do build software. This is useful because it helps us guess when it would be done, how much can be delivered, etc.
- ineedasername 7y agoI dislike articles like this. They take a situation that isn't representative of the workplace everywhere, generalize it, and come up with a universal "never do X!" headline that grabs attention. There's nothing wrong with deadlines, even arbitrary deadlines. Without them it's easy to get lost down a side path of "oh, it would be nice if we could do X". They serve to focus attention. The thing is not deadlines, but how you work within them. If it's arbitrary, Work backwards from the deadline to what can reasonably done, and present a detailed account of those estimates. If you have a hard-charging "just get it done" boss, part of your responsibilities is to manage upwards, educating your leadership on what your job entails so they can have reasonable expectations. Most managers are not actually pointy-haired bosses, but you have to work towards that relationship: if you treat them like a PHB, you'll give them no way to evaluate your work except their own faulty metrics. Will this work in every situation? No. But that isn't representative of some universal problem with deadlines, it's representative of poor management. here's nothing wrong with setting dates. There's nothing wrong with setting arbitrary dates
- MaulingMonkey 7y agoEven impossible deadlines aren't the end of the world. "We need X Y and Z done in N weeks!" "...I'm not sure if we can get even one of those completed in N weeks - and that's even before accounting for the fact that I'm an optimist among optimists. Since it's so obviously impossible, I'm not going to kill myself trying - instead, let's talk prioritization, so we can deliver as much value as reasonably possible within the deadline, if it's really an important one." What you want to avoid: 1) Pressuring devs into crunch/burnout/quitting/morale loss/checking out. Turnover will eventually cause brain drain when your best talent leaves for greener pastures, and makes hiring more expensive when your reputation sours. 2) Pressuring devs into sacrificing long term productivity for meaningless short term milestones. It's one thing to prioritize a feature or two for an important presentation to investors who will be making decisions about your financial future at the temporary expense of, say, test coverage. It's another to do so routinely that codebase stability suffers, developer velocity gets wasted on disturbingly routine debugging sessions, and build engineers disable code coverage metrics for being "just too gosh darn depressing to even look at."
- sys_64738 7y agoIt's a developer's job to meet their deadlines. If they can't make them then they should be negotiating with management. It's all about risk management. Every developer needs to own their deliverables. No dates means no deadlines, lack of focus, lack of closure, lack of product, lack of revenue, lack of money, lack of job.
- rossjudson 7y agoHigh functioning teams with sustained value creation don't need deadlines. They're not working on one thing; they're working on many things. There's nothing to "adjust" by imposing a deadline. You can reprioritize, but the date is just noise.
- agotterer 7y agoThis. I couldn't agree more. My current team is high functioning and regularly delivering value to the business. Delivering value is our measure of progress and success. Sure, we set goals which have dates attached. We usually plan out a whole quarter of what we want to accomplish. Our timeline is based on best guess estimates. We aim to deliver 80% of what we committed to. Sometimes we do it, sometimes we don't. The business rarely complains because they see regular value being delivered. When things aren't going well we communicate openly and regularly so that no one is caught by surprise.
- scruffups 7y agoThe title is a great test for conversational AI. I thought this was about driving (in a car) engineers to an arbitrary (blind) date.
- flattone 7y agoI wish somehow engineers could stop being told what to do. They should be saying what should happen.. right?
- ipnon 7y agoThis is the case when "Jeff" and the "Big Boss" can do the job they are managing. Examples include Zuckerberg at Facebook, Collison at Stripe, Musk at SpaceX. Every new hire at Toyota has to work on the assembly line for 2 weeks before they can begin their role. This applies from secretaries to vice presidents. How many software companies can say the same thing? No one who manages my job is capable of basic web development tasks, e.g. centering a paragraph. The result is they are continuously confused and frustrated and our group is unproductive.
- nimbius 7y agodisclaimer: I am not in STEM, im an automotive tech who is learning python. Why do software developers have arbitrary dates at all? We certainly dont. If a customer says they want their work done by the end of the day, we'll take that into account, but the best we can do is estimate how many hours it will take to work on, update you on our progress and inform you of obstacles we encounter. Work proceeds at a safe and productive rate.
- karatestomp 7y agoMostly managers who hold very low opinions of developers and think they’re useless if you don’t yell “boo!” at them with some frequency.
- johnvanommen 7y agoA big chunk of it is probably writer's block. For instance, if my wife asked me to make a pizza, I know very specifically what steps are necessary. When a client asks my employer to create a piece of software, it's a lot like being told to write a book. Sometimes you don't know where to begin and a lot of the time you get the thing 40% finished and you feel like throwing it in the trash and starting over from step one.
- Joof 7y agoI usually set aggressive dates to keep myself accountable. If it's loose, I'll over-engineer or pick up a side project doing something else. Management doesn't really set dates for us right now.
- jimbob45 7y agoMy current thinking is that sometimes deadlines are needed and Scrum can make that happen. However, the deadline you get from the engineers is going to be vastly slower than if you'd let them just do the work and tell you when it was finished. I know marketing lines to pretend that they can't do their jobs without hard engineering deadlines but marketing is overrated anyway. Ask yourself if you really need a deadline or if you're just slowing down engineering with your incompetent management.
- JulianMorrison 7y agoIt's also about 98% of "agile" - I don't mean the big deadlines, but the endless meaningless little ones. Why are N days okay to finish a thing, N+1 days not okay, and you have to endlessly salami slice it contrary to common sense until you fit in N?
- gfxgirl 7y agoIn games, at least in the past and I'm pretty positive still, you have to make commitments months in advance. Want the cover of some magazine? It's decided 6 months in advance. Want TV commercials to run? Book them 6 months in advance. Want your ads on billboards or large displays? Again, several months in advance. Want shelf space at Walmart, more of the same. So, your company, generally, has to book all of that stuff long before the game is complete. So they go to the team and ask. When will this be done? The team says (in 24 months) and so marketing and sales get to work making all the deals for the things above and now the team has to met their deadline or all that stuff above is not only wasted, those people will never work with you again because you messed up their scheduling. This is especially true for retail space because it's not like they can fill the shelves with random stuff on a moments notice. THey've basically got a hole in their inventory and shelf space they would have filled with another product so you've made them lose money. Much of this is also true for consumer electronics. Deals are made to feature the next smartphone at all outlets, and run commercials etc, months before the phone is ready to ship. All the teams making software for that device have to be ready to ship by that promised date.
- dhbradshaw 7y agoFYI, the billboard lag time was true until a few years ago, even for digital boards. But now you can turn on a national campaign in a few days. (Disclosure: I work with Blip Billboards who are one of the major drivers of this change.)
- gfxgirl 7y agoHow do you do that if they are all booked? Do you just price to the highest bidder so if I wanted my new Star Wars movie on the billboard on May 4th and you want your new Star Trek movie on the same day who ever pays more gets it even if one booked it months in advance?
- dhbradshaw 7y agoRight -- there isn't any booking its just about who brings the money for that sign on that day. You can pre-declare how much money you want to assign to an hour and sign but can't know that you'll win for that sign and hour. If you don't win there, you keep your money to use elsewhere. But we have ~1500 signs and each of them is playing a new ad every ~8 seconds. In other words, there's plenty of space. Those 8 seconds can range from a penny to a buck depending on the time and place and on the current competition. If you want to show up, you can.
- bane 7y ago"Real artists ship" - Steve Jobs After about 20 years working in tech, at multiple companies of all sizes, and in dozens of teams, working through all levels of engineering, management, and other jobs, I can say without any hesitation that without due dates (reasonably negotiated of course), engineers will spin indefinitely and nothing will ever ship.
- atoav 7y agoDepends. I am a MA who fittingly studied art. The university I studied on is one of the few without nearly any time pressure. You can take as long as you like. A receipe for disaster? Only produces bullshit results? Far from it. Ofc there is a percentage of people who just cannot deal with the freedom, but in terms of results (I studied in the Film department) this school creates the best films with the lowest budgets in the country. Most people that work from you get nothing for the job. Again fittingly I now work in the IT department of said university, where I often create software that we need. There is never a deadline, only a "Somebody needs this and wants to use it and is doing a horrible manual workaround in the meantime" that is usually a far better motivator than an arbitray deadline. Rhink about it this way: Imagine you are a carpenter and you have to build a cabin in the woods. What motivates you more: a) An abstract deadline set up by your manager (you know the cabin will be sold to some rich guy who doesn't need it anyways) b) Someone you know will live there. They are couch-surfing with their family in the meantime. There is no deadline. Both create pressure, but one is by far a more effective motivator to do things fast yet good than the other. Of course that would mean your company has to solve meaningful problems with a natural deadline. Natural deadlines by their nature are usually fuzzy. The trick is: make your engineers care. If you can't, you either hired the wrong person with the right skillset or what your company does is not important enough to most people. Many programmers and engineers instinctively know that their work acts as a multiplier for good or for evil. However if you multiply anything times zero it remains zero..
- TrackerFF 7y agoOne persistent problem I've encountered, is that this kind of nonsense very often translates into the bidding process of large projects. If you come up with a realistic offer, which should be pretty close to reality in both time and budget, you're out of the race. Other contractors have put in offers with totally unrealistic numbers, making you look both slow AND expensive. And like clockwork, the undercutting (bid) winners will deliver a 60% finished product come project due date, and then spend years on fixing bugs and "upgrades". Their in-house devs, and outside consultants for that mater, are worked to the bone. Bugs happen, and the tickets pile up. And worst of all, these companies get awarded new projects, again and again.
- goto11 7y agoI know it is not the point, but I find it funny that the "Code done with care" is worse than the "Code done under high pressure". Logging and wrapping is not "handling" an error, that is just making the exception go away.
- deleted 7y ago[deleted]
- huffmsa 7y agoIt doesn't destroy value, it means your team over-scoped the deliverable value at the outset. Shipping dates are good when used correctly. 1. We have this high level idea, we want to ship it by XXXX 2. Here are the features we want it to have that we think can get done by XXXX 3. Here are the features prioritized from mandatory to nice-to-have 4. Move the bottom 10% of features to v2.5 5. Move the next 10%-20% of features to v2.0 to make room for bug fixes, acts of god and management led boondoggles 6. Start development.
- thsealienbstrds 7y agoI don't believe that not setting a deadline is the solution. There are definitely software engineers who will happily change their designs an infinite amount of times if you let them. > The testers keep running into situations where things don't seem to be right, luckily your product manager is happy to defer most issues raised unless it is a real "show stopper," as Jeff loves to exclaim. That might have been the critical mistake. Jeff should not have done that. He should have insisted on lots of feedback loops during the project. He should have put more effort into convincing himself that the product is of sufficient quality. As for the developers, they should have made it clear to Jeff: if he's not allocating resources to convince himself that the product is of sufficient quality, he shouldn't be mad at them when in the end the product doesn't work.
- lihaoyi 7y agoe
- geekraver 7y agoI am old enough to have been writing software since 1976, and still do, although I am mostly a manager of managers now. My view is that dates are unfortunate (but sometimes unavoidable in the real world). But estimates are useful. They help flesh out risk, uncertainty, and ambiguity. They provide a set of approximations against which you can plot a glide path. And of course they must be frequently updated in the face of a changing reality. But that constantly evolving glide path is the “current best known” ship date, and that is very useful information (actually you can go deeper and look at its rate of change to give a better approximation). It’s the job of engineering management to convey to upper management that these dates are projections only with certain levels of confidence.