I can’t believe California pays 1 billion dollars a mile just to drill out tunnels. I think the going rate in Europe (not even China!) is something like $40M/km
by ComputerGuru 8y ago
I can’t believe California pays 1 billion dollars a mile just to drill out tunnels. I think the going rate in Europe (not even China!) is something like $40M/km or fifteen times less than what California is paying per mile.
- bluedino 8y agoEven in one of the largest cities in the country? Can you dig a tunnel in London, Berlin, or Paris for that price?
- fredley 8y agoYou can for a lot less than $1bn/mile. Crossrail was ~£200m/mile. Even the Channel Tunnel, under the sea, was £300m/mile. Those prices are all inclusive, so that includes building stations, rolling stock etc. Also unlike old cities, there are no archeological issues when digging under LA.
- deleted 8y ago[deleted]
- etiennemarcel 8y agoThis article is interesting: https://www.nytimes.com/2017/12/28/nyregion/new-york-subway-construction-costs.html https://www.nytimes.com/2017/12/28/nyregion/new-york-subway-... "But while the Second Avenue Subway cost $2.5 billion a mile, the Line 14 extension is on track to cost $450 million a mile." (that price includes stations, emergency exits, rails and systems...)
- notatoad 8y ago$250mm per km in paris and berlin. $145mm per km in Sao Paolo. $130mm per km in singapore. $58mm per km in madrid. https://www.citylab.com/transportation/2011/11/1-billion-doesnt-buy-much-transit-infrastructure-anymore/456/ https://www.citylab.com/transportation/2011/11/1-billion-doe... $55mm per mile ($34mm per km) would be pretty cheap, but closer to what the rest of the world pays for subways than what NYC does. accounting for musk-math, expect it to cost more like $70mm per km, which would put it on the low end but not the bottom of international subway construction costs.
- ComputerGuru 8y agoI misremembered. That was the cost in the middle of Barcelona, which is a big city: https://blogs.crikey.com.au/theurbanist/2012/02/15/why-do-subways-cost-so-much-to-build-here-than-elsewhere/ https://blogs.crikey.com.au/theurbanist/2012/02/15/why-do-su...
- rndgermandude 8y agoMadrid built a subway tunnel (Metrosur) for about $60M per km (about 41 km length in total) in 2003. That's about $97M per mile. Tho, the tunnel is actually outside of the actual metropolitan area, Berlin calculated some planned subway extensions (U1, U8 lines) at $120M to $280M per mile (2017), tho, those are short extensions of existing tunnels of about 1 km each and only estimations not actual costs.
- josefresco 8y agoIf the Boring Company’s cost projection of $1 billion is anywhere near accurate, that pencils out to $55.5 million per mile—far and away, the cheapest construction cost for any subterranean transit line in the U.S.
- bbeekley 8y agoI don't think CA pays $1 billion/mi just to drill. The Purple Line Extension project in LA is forecast to cost $8.2 billion total and covers 9 miles (http://media.metro.net/projects_studies/westside/images/factsheet_ple_2018.pdf http://media.metro.net/projects_studies/westside/images/fact...). That's pretty close to $1b/mi but it's also all-inclusive and a subway underneath one of the densest, busiest streets in LA. And the cost of subway in Europe is much more than $40M/km. The Crossrail project in London is 118 km and 15 billion GBP (http://www.crossrail.co.uk/news/crossrail-in-numbers http://www.crossrail.co.uk/news/crossrail-in-numbers). That's about $280 million/mi. Definitely less than the LA project, but it's the same order of magnitude and much of their mileage is in suburban London.
- ant6n 8y agoCrossrail has 21km of (twin) tunnels, which apparently cost 1.5B (just the tunnelling contracts). (https://en.wikipedia.org/wiki/Crossrail https://en.wikipedia.org/wiki/Crossrail)
- jcranmer 8y agoThey don't. The cost of just boring a tunnel is typically somewhere in the region of $50 million/mile. $1 billion/mile is on the mildly pricey side for building a twin-tube subway tunnel, all-inclusive of stations, rolling stock, substations, etc. The Boring Company is guilty of pointing to the latter to complain about tunneling costs while quoting the former for their costs.