The reason that planning software development is bullshit is that you simply cannot know all the little details because in software development you're always do
by Aaargh20318 8y ago
The reason that planning software development is bullshit is that you simply cannot know all the little details because in software development you're always doing something you've never done before (because if you did you could just copy-paste your previous work).
To use the 'going to the supermarket for milk' example. I could make a fairly accurate estimate for that because I've gone to the supermarket hundreds of times. I know all the different things that can go wrong and account for them, because I've encountered them before. The elderly person who wants to pay cash and has a bag full of coins. The guy who finds a 10 cent discrepancy on his €92,30 receipt and has to argue for 5 minutes with the cashier (while the row behind him keeps growing). etc. etc.
Now imagine that today is your first time going to a supermarket. In fact, before today you had never heard of the concept of supermarkets, or milk for that matter. How good will your estimate be ?
The only time you can make a decent estimate is after you've finished. Or to put it differently: making an accurate estimate is possible, if you're going to accept that making the estimate is going to take a long time, but I can't tell you how long.
Development time estimation, and every methodology that attempts it (I'm looking at you, Scrum), are little more than desperate attempts by managers to feel in control and relevant.
- commandlinefan 8y agoAnd TFA's suggestion (use our magical time tracking software) isn't going to solve that problem, either.
- brightball 8y agoRecent discussion: https://news.ycombinator.com/item?id=17154355 https://news.ycombinator.com/item?id=17154355
- jungturk 8y ago> Development time estimation, and every methodology that attempts it (I'm looking at you, Scrum), are little more than desperate attempts by managers to feel in control and relevant. More charitably, they're an opportunity to introduce system 2 slow thinking on the team. There are certainly novel engineering problems that simply won't yield to estimation, but there are also lots of well-solved problems that will. Managing the latter isn't desperate, its just sound practice toward reproducible results (ideally deployed only where reproducible results create value).
- avmich 8y ago> but there are also lots of well-solved problems that will. Certainly when you're writing a double-linked list a third time you can estimate how long will it take you. The problem is that in real life you never solve sufficiently the same well-solved problem. Feature details, matters of integration with other pieces of the system intervene - and in practice those errors introduced by new circumstances are significant comparing to predicted time. So the practice may be sound, but it doesn't give the desired results, like predictability of required time.
- majormajor 8y agoSo you integrate with a few systems, you learn where the gotchas tend to be, you call those out as things you'd like to know more about when making your initial estimates, etc. Today's software dev has probably integrated with more systems than they have written linked lists. We just have a habit of forgetting all the little details. If you're looking for a formula that lets you estimate once and then move on to the "real work" now that that tedious BS is out of the way, there isn't one. But you can still do something. There's ground between "I can't estimate that in 30 minutes" and "I can't estimate it at all" and it's up to you and your stakeholders to come to terms on how to balance the risks in your estimates (in broad terms: too inaccurate estimates vs too much time wasted estimating requirements that have since changed). (There's a parallel theme in some other comments: "if it's a well-understood problem why am I not using the existing solution?" Similarly, there's a difference between "well-understood" and "perfectly abstractable and automatable", otherwise almost none of us would be employed these days. :) )
- Aaargh20318 8y ago> there are also lots of well-solved problems that will But if it's a solved problem, why not use the existing solution ?
- nradov 8y agoEven if the solution exists you still have to integrate and test it. Those tasks can require a lot of engineering labor, but fortunately they're fairly amenable to estimation.
- roberttod 8y agoI completely agree. I'm lucky to work in an environment where management aren't too fussy about sticking to deadlines, as long as progress is pretty decent. It's a nice way of working, I use system 1 for estimates which generally works pretty well and saves time needlessly trying to pin down an exact eta. On the whole our team delivers a lot of features on time and generally doesn't go over 2 weeks late for anything, even though it often wouldn't matter if we did go over. I appreciate that sometimes hard deadlines are necessary but if I can I'll always avoid them.
- diego_moita 8y agoA lot of people have been praising this "estimates based on data and rigorous planning" for decades. Steve McConnell wrote a whole book about it (Software Estimation: Demystifying the Black Art). It works only very special circumstances: when the task can be very well defined because it has been done a lot of times before and the people doing the task are very experienced on it. But the caveat is that if you are doing such a task you're not really doing any innovation at all. Actually, if it is so well defined and trivial it should probably already have been automated. True innovation must have a lot of unknowns, it isn't innovation without it.
- brightball 8y agoFor what it's worth, the examples in that book are usually contract development shop where you're doing the same thing for multiple clients over and over.
- nradov 8y agoIf you actually read Steve McConnell's book the focus is really on accurate estimates more than data and rigorous planning. He makes it clear that a high level of precision is impossible in some cases. (Many people fail to appreciate the difference between accuracy and precision.)
- raphaelb 8y agoI haven't read the book and was going to ask about accurate vs precise but found this helpful article discussing it as it relates to software here if anyone else is curious about that distinction: http://itsadeliverything.com/accuracy-vs-precision-in-estimation http://itsadeliverything.com/accuracy-vs-precision-in-estima...
- notheguyouthink 8y agoThis is being a little extremist, no? I'm consistently asked to give estimates, and I mostly give estimates that are accurate within sane expectations. I think what's missing here is that I can predict how long something is going to take when I talk with the managers/feature-planners about what the feature is. If I feel I have a solid understanding of the requirements, which pieces of code it'll touch, etc - then I can give a reasonable estimate. Now, the bigger the project the more difficult this becomes. Details I've missed is always a possibility, and that just stacks up the bigger the project is. So I think being specific in this type of discussion is really important. A feature that's going to take 6 months to implement is insanely tough to estimate, and very likely to have a wrong estimate. A feature that takes a week can pretty reliably be accurate within a day or two, in my experience. I'm not defending management in these sorts of things.. I think it's our job to not only give estimates, but include understanding about the expected validity of that estimate. All estimates are worth while though, your post makes it sound like they're not. You tell me you need a feature that's going to take 12+ months? It's so hard to predict that it's laughably wrong.. but that's still insanely useful. Why? Because now the management knows it's highly unlikely to be a 1 week, 1 month, w/e feature. It's big.
- Aaargh20318 8y ago> I think what's missing here is that I can predict how long something is going to take when I talk with the managers/feature-planners about what the feature is. If I feel I have a solid understanding of the requirements, which pieces of code it'll touch, etc - then I can give a reasonable estimate. I'd argue you can't. Right now I'm working on a feature that I estimated as 'a couple of hours'. I've been working on it all day by now. Not because the feature is that difficult, or because I didn't get a set of good requirements. The requirements are crystal clear and should be easy to implement. The reason it's taking so long is that I'm fighting with a UI component that doesn't behave as expected (or documented). What should have been a trivial part of this task, a matter of seconds and not worth estimating at all, turns out to take all day because I didn't know this specific component is misbehaving and I couldn't have known until I started implementing it. You cannot predict things like that without doing it.
- jbigelow76 8y agoThe reason that planning software development is bullshit is that you simply cannot know all the little details because in software development you're always doing something you've never done before (because if you did you could just copy-paste your previous work). If you can plan and execute putting a person on the moon, you can plan and execute software development. I think the problem is the overwhelming majority of software development is so low stakes, easy to replace, assumed that bugs are par for the course, etc... that most orgs have stopped putting real effort into planning AND executing on that planning, instead just cargo culting the planning phase.
- toasterlovin 8y ago> If you can plan and execute putting a person on the moon, you can plan and execute software development. But the budget for planning is limited. To realistically plan out most software projects would entail almost as much work as simply executing on them. That level of resources for planning vs. execution is acceptable for putting people on the moon. Probably not for building a line of business app.
- wvenable 8y agoYou've missed the point. Nobody can (or did) accurately estimate how long the planning and development would take to get someone on the moon. Half the materials weren't even invented yet in 1962. Nobody knew that Velcro was flammable in pure oxygen. Sure once all that expensive and unknowable planning and development is done, you can double-click that executable and put a man on the moon.
- handbanana 8y ago> If you can plan and execute putting a person on the moon, you can plan and execute software development Okay, but I think you've missed the point. Planning is hard, and you can't possibly account for all the variables. Everything after that statement I can agree with
- harryf 8y ago> If you can plan and execute putting a person on the moon I think you vastly overestimate the quality of the software and systems that took men to the moon. Try reading https://www.google.com/amp/s/amp.space.com/26593-apollo-11-moon-landing-scariest-moments.html https://www.google.com/amp/s/amp.space.com/26593-apollo-11-m... for example - you might conclude "they got lucky"
- avip 8y agoYet if I ask you how long it takes to buy icecream in Japan, based on your experience grabbing milk in the US, your guess will be "less than half a day". Which is good enough for me.
- vineet 8y agoAnd if I ask you how long it takes to build a Wordpress blog for a music band, based on your experience building blogs for realtors. You guess will likely be good enough for me. :-)
- jfoutz 8y agoBut then you say go for it and get upset about all the time I spend getting a passport, booking flights, and figuring out how to transport the ice cream back. I’m kidding, of course. It really depends on how well business and development understand each other.
- notheguyouthink 8y ago> I’m kidding, of course. It really depends on how well business and development understand each other. Yup. This is the crux of the whole issue, and it's being completely blown out of proportion. There's always going to be details the estimator (dev) won't know, but the more clear a picture you have in your head, the more confidence you can have in an estimation. This is directly related to the size of the project too, of course. If it's a 12 month project, a single developer is massively unlikely to have a reasonable understanding of all the potential roadblocks that the project will take. However a 1 day task, with tools you know/etc, you can have a pretty good idea how long it'll take. There's always some unknowns, but that's literally what an estimate is for - attempting to plan for the unknowns. I can write an add function and I'd bet a lot of money that it won't take more than a day. Unreasonable management seems to be giving developers PTSD here. As I'm having trouble understanding why the idea of an estimate, by definition exactly what we're doing, somehow doesn't apply to software development. If you're being pedantic you could say the same about a lot of things. How long to dig a 1foot hole in open ground? Well who knows, there might be a massive rock - but that doesn't mean you can't give an estimate. It's literally what an estimate is for, an approximation based on assumptions and expectations.
- himynameisdom 8y agoTo be fair, Scrum doesn't try to capture development time estimates, only the effort needed to provide value. Work items inherently vary in size, or estimated effort. However, enough work should be planned during planning for the dev team to forecast what it believes it can do in the upcoming Sprint. It's all about transparency, not adherence. That said, requirements emerge daily. Transparency is essential for honest dialogue. I agree and disagree with the notion that an estimate can only be provided after the work is done. If the work is broken down properly, you can use empiricism to get a good understanding of what is needed based on previous, similar work completed. But to think an estimate can only be provided after the work itself is done is kind of ridiculous. If you section off variables with manageably-sized work you should have a good understanding of what's needed to pull it off.
- superjan 8y agoVery well put. It reminds me of the “Halting Problem”. Although for a subset of programs, it can be proven that they will finish in a predictable amount of time. Maybe this also holds for projects.
- makmanalp 8y ago> you simply cannot know all the little details This is the reason big design up front hasn't been the gold standard in planning. Most modern methodologies acknowledge that there'll be a lot of changing requirements and learning-while-building. The point is, given this information, you could a) run around like crazy doing all manner of reckless and crazy cowboy programming and putting out fires b) carefully plan a relatively short period of time on a small, achievable, well defined goal (not "build the project"), then making a note of what worked and what didn't, and readjust before you plan the next short period of time
- Retric 8y agoThis is often taken to an unhealthy extreme. You need to have some fairly specific goal in mind to start doing anything. AKA are we building a PS4 game or a self driving car? Methodologies like Scrum are all about transitioning a long term objective into short term progress. But, you really do need some fairly well thought out goal. Further course corrections quickly get very expensive. Sort of like sailing from Virginia to Europe then deciding 1/4 of the way in on France then changing your mind to Spain at the midway point is probably fine. However, changing your mind to Australia is a much bigger deal.
- makmanalp 8y agoAgreed! Nothing I disagree with here. But last minute itinerary changes from France to Australia back to France again point to a larger, more systematic problems IMHO. Perhaps it's a lack of understanding of the market and customers, or just bad management and lack of company vision - but no software process is going to fix that.
- AstralStorm 8y agoAnd then a poor maintenance programmer is faced will lack of architecture because the thing was built without any in mind... Just as a perpetual prototype.
- debt 8y agoMassive software companies deliver high-quality software, on-time all the time for one reason: resources. They got the money and the time and the developers and all the enterprise accounts up the wazoo. Typically no one wants to pay more for less, but that's the best strategy to deliver high-quality software on time. You reduce the scope drastically but do not adjust the timelines. You pay for more development resources(tooling, developers, servers, time, etc.). If you can't deliver at that point, then there's a serious fundamental issue with either the leadership or the team or both. Startups don't have this luxury. So they must execute on the least complex scope on a very tight timeline. High-complexity scope increases the fatality risk to the company. So as the scope increases in complexity the risk increases and the likely the company itself will fail increases. Again, because startups do not have the cash to pay for the proper amount of resources.
- chrisbennet 8y ago”Massive software companies deliver high-quality software, on-time all the time for one reason: resources. They got the money and the time and the developers and all the enterprise accounts up the wazoo.” I think that is a myth right up there with “If I was rich, I’d be happy.” Massively funded software projects fail all the time.
- mannykannot 8y agoThis claim of inescapable novelty has a kernel of truth, but it is being exaggerated beyond any sense of proportion. If everything you have done in your day-to-day work has been beyond-estimating original, then either you could out-Knuth Knuth (in which case, kudos to you, and I hope you will have time to write the books someday, but your experience is not generally applicable), or you have been goofing off some of the time. That which is passed off as novelty is often ignorance (not necessarily on the part of the developer.) To continue the retail analogy, software projects are often like the guy who is building a deck on his house, but keeps going back to the hardware store because he made no attempt to think things through, or measure before cutting (note that, in this analogy, the would-be builder is not necessarily playing the role of the developer. In some cases, that might be the hardware store owner's role.)
- thom 8y agoBut it's exactly this 'ignorance' that is the major part of every software project. There are unknown unknowns, and there is no way from a standing start to grasp either their number or their nature. I'm happy if people are saying that this exploratory work should be done (in part or in total) before estimating, but in my experience that's just not palatable to most organisations. I envy _hugely_ anyone who builds software that is even 50% the same as what they were working on six months ago.
- mannykannot 8y agoWell, then let's call it what it is, because there are things that can be done to mitigate ignorance to some extent, if there is the will to do so from all parties.
- Aaargh20318 8y ago> there are things that can be done to mitigate ignorance to some extent Sure, but all you're doing is moving the uncertainty from the development to the planning phase, so instead of a development phase of unknown length and cost, you end up with a planning phase of unknown length and cost.
- tonto 8y agoAlso consider that the management or project is looking for just some vague white liquid and at the store you only see cans (powdered milk? Is that white?)
- btbuildem 8y agohttps://news.ycombinator.com/item?id=17235832 https://news.ycombinator.com/item?id=17235832 If you're really working on new problems all the time, consider yourself extremely lucky.
- cmroanirgo 8y agoTo keep with the 'going to the shops to buy milk' theme you can break it down into bits you can estimate. Assuming you've never bought milk before: - how long will research take? Where do you buy milk? Where is the nearest shop? 3 mins. - how long to get to nearest shop and back (eg 10mins x 2) = 20 mins. - find milk in shop (30 secs to 5 minutes), so say 4 mins. - Buy milk. (1 to 5) say 3 mins. Don't forget that these are estimates and always add a bit of headroom. The above comes to 31 mins, so say 35 and you know you're covered. If the manager isn't happy with it, give him the low down figures.
- shanghaiaway 8y agoProgrammers aren't special snowflakes and there's nothing special about programming. The exact same can be said about anything be it marketing, sales or design.