3 ms·
T Boone was too far ahead of the transmission infrastructure with his plan. The SPP lines were not capable of moving much wind (pre ITP build-out) and the ERC
by windchick 10y ago
T Boone was too far ahead of the transmission infrastructure with his plan. The SPP lines were not capable of moving much wind (pre ITP build-out) and the ERCOT CREZ plans were just a twinkle in our eyes at the time. We came up with ERCOT CREZ prelim plans about 2006 but it took until 2013/14 to get em built and energized. So, he launched his boat too early, he did not miss the boat.