From what I've heard from the official inquiry into it the fire system design was fine for the original plan. But then they pushed massive changes (original des
by detaro 11y ago
From what I've heard from the official inquiry into it the fire system design was fine for the original plan. But then they pushed massive changes (original design had 2 stories of arrivals area below 2 stories of departure areas (or the other way round, not sure), they then changed that to a sandwich of arrival/departure/arrival/departure), and as the article notes didn't give time to let the architects actually do a redesign of all components. From that point on no full plan existed and people drafted up local redesigns as they became necessary, often not talking enough to other groups or missing the entire picture.
IMHO it is a great example for structural failure of the organisation running it, being set up in a way that it couldn't properly communicate or force it's leadership to deal with problems. There even are reports that banks that had been asked to provide guarantees declined to do so after reviewing the management structure, because they thought it would be unable to react to problems properly.