> Each floor would have to be inspected and certified as safe and I don't believe that could be done in under a year. "Nobody" spends that long on modern high
by vidarh 11y ago
> Each floor would have to be inspected and certified as safe and I don't believe that could be done in under a year.
"Nobody" spends that long on modern highrises - the processes are generally well understood and most of the structures are "cookie cutter" designs with solid margins. The ones going up in London now typically takes 1-3 days per floor for the structure.
- SCAQTony 11y agoIf it takes 1-3 days per floor (let's presume this building was built in London and it only took one day per floor) would it not take 57-days then? or do they wait till the building is built and do it all at once? In Los Angeles you build a floor, it has to be inspected one floor at a time. Then again, London does not have earthquakes but both Shanghai and California do.