Thermal is an issue that gets worse with distance. Did you look at the article that I posted above? If you are proposing expansion/slip joints at every pier, th
by rmxt 11y ago
Thermal is an issue that gets worse with distance. Did you look at the article that I posted above? If you are proposing expansion/slip joints at every pier, that runs directly counter to the proposal which states that expansion joints will only be needed near the stations. [1, pg. 27] If we go according to the proposal, the slip joint at the stations on the test track will only need to accommodate ~9 feet of movement (5280x5x6.5x10^-6x100)/2 compared to something an order of magnitude higher for a full-scale track.
Successfully designing for earthquakes does not necessarily mean active damping. (That is, it is not "required" as you state.) Yes, many large structures use specially designed mass or viscous dampers for dynamic loading (Citigroup Building, NYC; Taipei 101; Millennium Bridge, London), but others are designed to fail safely such that life and structure are preserved to the greatest extent possible. Specifically for bridge structures, there is the notion of plastic hinging in visible locations. [2] This way, the failures can be identified and repaired before normal use resumes. Here are some relevant state DOT guidelines. [3]
[1] http://www.spacex.com/sites/spacex/files/hyperloop_alpha-20130812.pdf http://www.spacex.com/sites/spacex/files/hyperloop_alpha-201...
[2] https://en.wikipedia.org/wiki/Plastic_hinge https://en.wikipedia.org/wiki/Plastic_hinge
[3] http://www.dot.ca.gov/hq/esc/techpubs/manual/bridgemanuals/bridge-memo-to-designer/page/Section%2020/20-6m.pdf http://www.dot.ca.gov/hq/esc/techpubs/manual/bridgemanuals/b...
- msandford 11y ago> Thermal is an issue that gets worse with distance. I would respectfully disagree. The rail industry has figured out how to do Continuous Welded Rail (CWR) quite well, using the elasticity of steel. http://blogs.agu.org/landslideblog/2011/03/08/distorted-railway-lines-in-the-christchurch-earthquake/ http://blogs.agu.org/landslideblog/2011/03/08/distorted-rail... Similarly the tube for the Hyperloop doesn't HAVE to free-float against its foundations. It might be easier or harder depending on various factors to work on expansion joints or doing the tube equivalent of CWR. You'd probably work on both to figure out which is easier in the long run. Considering that it's a 9-11ft diameter tube with about 1" wall thickness, it's going to be pretty stiff, especially relative to traditional rails. The moment of inertia means that it should be very resistance to bending or buckling under compression and under tension steel is usually very good. Given that there are going to be plenty of turns that the track has to make, I would look at doing a combination of two things: 1. Working towards a CWR style solution 2. Allow some movement so that the corners can take up the slack as the tube expands The turns are very gradual and sweeping. But you could imagine that there's a virtual intersection between two straight portions that you determine by drawing lines from the straight portions until they meet. The actual turn will take place far from here, but it's instructive. So as the tube expands, the actual curve is going to move ever so slightly from the neutral position towards the virtual intersection. So long as there is enough room on the pylons to accommodate this, things will be pretty good. The tube will go from being curved 0.1 degrees per 100 feet to 0.105 degrees per 100 feet (or something like this) but this can be designed for and ensured that it doesn't cause the tube to buckle or collapse. It's engineering, not the utter unknown.
- HCIdivision17 11y agoThat is one of the coolest articles on field engineering I've seen in a while. Thanks a lot for sharing it - it really brings out how something like the hyperloop can be tackled. So far, thermal effects have been my main point of curiosity, but the idea of calibrating the steel to take care of it will likely be the ... easiest? way around the problem. At their desired vacuum pressures, the steel doesn't need to be anything special, so I would love to see the mechanical engineering that goes into designing the 5 mile track's materials.
- msandford 11y agoThe engineering to do a 5 mile section is pretty straightforward. It's only 5 miles long (25000 feet) and around 250 joints. 1. Giant foundations and just handle the thermal stress by not letting anything move 2. Figure out the slip joints really well to soak up the ~125 feet of travel and still hold a good vacuum 3. Figure them out OK and just install extra vacuum pumps since there are only ~250 joints 4. Try out some/all of these options on 500 feet of tube in parallel to see how it all performs and don't make a final decision on the whole 5 miles until you have real cost numbers The other thing I'll mention is that you don't need the steel to be continuous in order to hold a vacuum. You need the inside face of the tube to be smooth in order to not jerk around the vehicles, but all the sealing could be done on the outside with clamp-on seals. If the average continuous tube piece is 100 feet long and the max thermal expansion is 0.5% then you only need a half-inch gap between the tube pieces. If your air bearings are say 3 feet long each and divided into 10 sections internally which are fed through orifices so that no one section can rob all the pressurized air flow then you're never going to lose more than 10% of your bearing force and you should be able to glide right over these 1/2" gaps with no problems. And if there are some problems a few accumulators (plain air tanks or pressurized bladders) inline with the supply lines would probably increase the momentary recharge capabilities enough to negate the problem. 700mph is 1000 feet per second or 12 inches per millisecond. That means a 1/2" gap is crossed in just 40 microseconds or so.
- rmxt 11y agoThank you for the additional info. I am skeptical merely because they were quite hand-wavy about temperature accommodations, and it certainly is/was simplistic to think that ALL thermal movements can be accommodated for only at stations. (Especially if it's a direct and exclusive SF-LA route) Yes, the cross-sectional properties of the tube are going to be phenomenal, but I've always operated under the assumption that you don't try to resist thermal movements, regardless of the strength of the cross-section. You let them dissipate and design for the deflection (e.g., at the bearings and abutments), rather than the stress (buckling/tensile) in the beam. If we start allowing stress to develop in the superstructure tube, I can't imagine what the cyclic fatigue impacts of that temperature stress will be. (Maybe it's not significant...) I am no rail expert (though I am a civil/structural guy), but even continuous welded rail isn't always continuous for hundreds of miles. [1] I think that there are two factors at play: continuity in the maglev/rail structures, and continuity in the superstructure/tube. I do not know what maglev devices look like, but if they do look like traditional rail, then agreed that a CWR solution seems to be the way to go. That being said, no matter how stiff the tube is, it too will have to accommodate thermal movement. My gut reaction is to call everything tube related simply supported, allow for (6.5x10^-6x100ft.x100deg = 0.065 feet) ~= 0.75" of expansion or contraction at each pier, and surround this expansion zone with a metal sleeve of 2"+ greater diameter than the main tube. Simply supported, multi-span structures are a well-studied problem. Adding in the continuity of the rail/maglev structures are what make it hairy, IMO, and the interplay between seismic considerations and thermal considerations becomes important. As far as I can see, it's very important for the maglev structures to be continuous to ensure for smoothness and speed of the ride. For example, given that you make the superstructure spans simply supported, you have these nearly perfect "mass-on-a-stick" seismic models with well defined, and relatively short periods. Then, you have much longer continuous sections of rail/maglev equipment that contain releases on a far fewer number of span segments. These will have much longer periods of vibration. Maybe I'm stretching here, but the connections between the maglev/rail and superstructure seem like a place that is rife with potential for failure and stress during a seismic event. (I would not want a life-safety issue being my most prominent failure point.) [1] http://boards.straightdope.com/sdmb/showthread.php?t=471152 http://boards.straightdope.com/sdmb/showthread.php?t=471152
- Retric 11y agoIf their test has a station every X feet, then the track needs to follow that same rule. Granted, if they suggest you can build a test track station every X feet and the full scale model over 10x feet then that's an issue with their model. But, again it does not get worse due to the total number of stations just the ratio of stations to track. Anyway, you don't need active dampening to keep the structure intact, but a 750mph vehicle suddenly needing to lift 10 feet in the air you’re going to need a lot of head room not to hit the top of the tube. Not to mention rapid left right displacement. Granted, cost/benifit let em die yada yada.
- seanflyon 11y agoThe design only calls for one station at each end. Many people have said that the best way to deal with thermal expansion is to let the ends (at the 2 stations) move ~500 feet at each end. The alternative is expansion joint every so often along the tube.
- msandford 11y agoIf you do that, though, then all of your support structures the whole way through need to allow the tube to move inside of them. The tube is supposed to be supported every 100 feet or so (if I remember correctly) so that means that the last pylon has to be at least 500 feet from the station and that the tube has to be able to slide inside the support. I suspect that you'd see a lot of wear on the tube that's sliding over the pylon supports as it might go through at least one if not several heating and cooling cycles daily. I could see two cycles if you've got side heating after dawn, midday shade under the solar panels, and then late afternoon heating after the solar panels stop casting a shadow over the tube. You might get another cycle if you have two parallel tubes with two parallel lines of solar panels above them.
- seanflyon 11y agoI think that there are a lot of options for reducing friction wear. My first thought would be to put wheels between the tube an its supports (attached to the supports, not the tube).