My favorite question: "Is the date slipping, or has it slipped?" What you really need to do is help the person setting the deadlines plan. There are things the
by trjordan 12y ago
My favorite question: "Is the date slipping, or has it slipped?"
What you really need to do is help the person setting the deadlines plan. There are things they're doing that are synchronized with finishing the project, and there are things that simply depend on the project. Marketing may want to publish a blog post. Sales might want to promise a delivery date (or already has). Management might want to claim victory for a Q3 delivery. All of these things are outside your knowledge, and they're frequently based on your initial estimate.
So, over-communicate, but also slip once, and slip hard. If you're a week out, and going to miss by a day, slip the date a week. Fuzzy, frequently communication isn't useful, because nobody can plan around that. Make sure you are clear about the moment in time you want the project manager to go from "I'm worried about date X" to "We've change the date to Y", because while it's fuzzy in your head, it needs to be clear in theirs.
- pseudometa 12y agoI second the "Slip once, and slip hard" tip. Saying "one more day" a second/third time as it is both confusing and annoying to others.
- cpeterso 12y agoFred Brooks wrote, "How does a large software project get to be one year late? Answer: One day at a time!" If a team never admits the project is slipping, then they won't examine whether they need to adjust requirements to meet the date or adjust the date to meet the requirements.