I feel that the title is misleading. Caltrans faulted by practicing terrible project management. If someone underbids the next contractor by $250 million on a
by jacques_chester 12y ago
I feel that the title is misleading.
Caltrans faulted by practicing terrible project management.
If someone underbids the next contractor by $250 million on a job they've never done before, you're supposed to politely laugh them out of the room.
Edit: for the benefit of those now arriving, the title and link have been changed.
- opendais 12y agoNot just the next contractor but the lowest bid by a contractor who has ever built a bridge before. Just in case someone doesn't read the article. ;)
- elnate 12y agoI've worked for a company (electronics design/installation) that desperately underbid competitors to get as many jobs as possible, then the boss piles pressure on the workers to get the job done at an inhuman speed. Inevitably, up fucks occur and the boss has a shit fit, you get in trouble and have a black mark against your name. Not fun all around. The lessons, not every job is worth doing and always allow margins for mistakes.
- pijsong 12y agocaltrans and california gov ... just way too corrupted
- saraid216 12y agoAccepting a lower bid isn't an example of corruption. This is the equivalent of buying a startup's product on the chance they figured out how to provide value more cheaply. That's not corruption; that's basic market forces.
- rwallace 12y agoIf you look carefully at the full text, it's clear the fiasco made no economic sense, and there was bribery and corruption involved.
- cmelbye 12y agoNever attribute to malice that which is adequately explained by stupidity.
- dnautics 12y agoin this case the administrators are probably not malicious, they are thinking, "I'm doing society a solid... I should be entitled to a due". It's only malicious if they actually have a modicum of introspection.
- techsupporter 12y ago> If someone underbids the next contractor by $250 million on a job they've never done before, you're supposed to politely laugh them out of the room. Most of the time, you can't, at least not for government projects. Because of procurement laws and rules (designed, among other things, to allegedly be transparent and to provide accountability), a government body is required to accept the lowest bid from the contractor that met all of the requirements. Seeking an "experienced contractor" is usually seen as code for "we want to use our friends" by a skeptical legislative body, so things like tenure and past projects can't be considered.
- div 12y agoOdd. I've been involved in a few government bidding processes in Europe, and detailing past projects was always a major part of what we'd get graded on.
- Someone 12y agoIndeed. Typically, being able to build the thing is a requirement, and that is typically made objectively measurable by stating that you must have successfully built similar projects. That has its downsides, too. A common complaint in the EU is that there is no way for small building companies to become large companies. Reason is that, to become a large company, you have to do large projects, and to get large projects, you have to have done large projects. In the EU, when comparing offers, one doesn't have to pick the absolutely cheapest that meets the requirements, either. A slightly more expensive offer that more than meets the requirements (for example by having much less environmental impact, by requiring less closure time of a road, or by producing something that has lower maintenance costs) can windhover one that just meets the requirements.
- dagw 12y agoIt's part of your grade, but it is rarely an overriding factor in my experience. Lots of experience plus slightly higher price will beat little experience and slightly lower price, but it won't beat little experience and very low price. I was recently involved in a bid for a government contract where we got perfect scores on all factors, but still lost the bid to a small company with little to no relevant experience, but who claimed they could to the job for a third of the price.
- carlisle_ 12y agoAnd the real kick in the balls: >As the project wound down, ZPMC reaped tangible rewards, sharing with ABF more than $250 million in cost overruns and incentive payments.
- acomjean 12y agousually the wording is "lowest bid from a qualified contractor" If the the contractor is not qualified they should be removed from the bid. In NY there was a list of contractors no longer able to bid state jobs that had to be checked as well.