A GAO report talks about the problems: http://www.gao.gov/products/GAO-13-580T http://www.gao.gov/products/GAO-13-580T "Risk management: OPM did not have a pr
by curiouscats 13y ago
A GAO report talks about the problems:
http://www.gao.gov/products/GAO-13-580T http://www.gao.gov/products/GAO-13-580T
"Risk management: OPM did not have a process for identifying and tracking project risks and mitigation strategies on a regular basis. Thus, it lacked a mechanism to address potential problems that could adversely impact the cost, schedule, and quality of the modernization effort.
Organizational change management: OPM had not adequately prepared its staff for changes to job responsibilities resulting from the modernization by developing a detailed transition plan. This could lead to confusion about roles and responsibilities and hinder effective system implementation.
Testing: The results of tests 1 month prior to the deployment of a major system component revealed that it had not performed as intended. These defects, along with a compressed testing schedule, increased the risk that the system would not work as intended upon deployment."
and on and on.