>> "Under 2.4, can we have more jobs in the jobstore and is the console more optimized?" I agree with this. You create a plan so you have an idea when the proj
by gadders 13y ago
>> "Under 2.4, can we have more jobs in the jobstore and is the console more optimized?"
I agree with this. You create a plan so you have an idea when the project will finish, when resources will become free, when you deliver to other dependent teams etc. That doesn't mean the plan is cast in stone and once the Gantt Chart is finished, it never changes.
Obviously, you do what you can with scope, resource moving, etc to keep to original dates but if you can't, then the plan should be updated to reflect reality.