Software-development estimates are regularly off by a large margin for two reasons. First, the problem is inherently hard. Second, social and business pressures
by tmoertel 13y ago
Software-development estimates are regularly off by a large margin for two reasons. First, the problem is inherently hard. Second, social and business pressures bias the estimates downward.
Why is the problem inherently hard? To see why, let's imagine that the All-Knowing Fairy Godmother of Software Estimation descends from the heavens and lends to us her magic estimating function F that, applied to any software project S, will tell us exactly how much time and money our preferred software team will consume to implement S. Don't worry about how F works, just believe that it does. (Okay, okay. Let's just say that F peers into a parallel universe in which our team has already implemented a software system line-for-line identical to S, and it just observes how much time and money were actually consumed in that universe. Anyway...)
Now that we have the magic F, our problem is easy, right? Nope. The real problem is that we don't know what S is. All we actually know is that our S, whatever it ends up being, must satisfy some set of fuzzy constraints C (commonly called "software requirements").
In truth, there are a countless number of possible values for S. In other words, S is a random variable, a mapping that ascribes a probability to each of the possible software systems that we could build to satisfy C. Therefore, our best estimate, even with the perfect estimating function F, is itself a random variable. In other words, it's not an estimate but a distribution of estimates.
See how fun this is getting?
But, wait, it gets funner. That's because people in the business world don't want a distribution of possibilities. They want a budget, a date on the calendar. So we must squeeze point estimates out of the true distribution. (And, remember, we don't even know what the true distribution is!)
That's where the second reason kicks in. Let's just think about the distribution of possible budgets for our distribution of possible values of S. Because S can range from "the simplest thing that could possibly satisfy C" to "the most insanely complex thing that a frighteningly gifted salesperson for an enterprise consulting firm could get our CIO to throw money at," that distribution is going to be w-i-d-e. From X to 10X wide.
So if we're the folks tasked with coming up with those point estimates, we could plausibly estimate X on the low end, or 10X on the high end, or anything in between. Guess which estimates are going to get us the most push-back from the higher-ups?
Now, we're swell guys and all, and we want to do a good job with our estimates. No question. But, still... We're human. If we think that giving a higher-end estimate is going to make us unpopular with the higher-ups, maybe we'll estimate a little lower. And when we get push-back on that estimate, maybe we'll "take another look at the numbers" to see if we "missed any opportunities."
And that's the old one-two. We start with a hard, fuzzy problem and then add to it the pressure to deliver only feel-good solutions. The result: estimates that are often way low.
- wfunction 13y agoFor what it's worth, I haven't seen hardware engineers complaining about this issue as much as software engineers, which I find baffling. I think if you're going to justify why software development is such a "hard" problem, you should mention what makes it so different from other fields.
- kwantam 13y agoYou've been talking to the wrong hardware engineers, I think. Every engineer on my team has a characteristic "fudge factor" that represents his... optimism (say, from 1.5x to 2.5x). Once I apply those fudge factors, I add another 30% slack to the total schedule. And I usually still underestimate. The team I'm on now has been doing a very good job compared to previous ones about getting good estimates for project duration, but the ability to underestimate is nonlinear in the project size, and most of our projects recently have been pretty small chips. On our most recent tapeout, we did a new baseline based on a new feature request and underestimated the cost of that feature addition by a factor of 2. The total schedule was pushed out about 20% as a result. I still consider this a success in predicting the project's duration: I've been on projects where we taped out six months or more after our "commit" date.
- pratik661 13y agoIts much easier to justify changes in software requirements vs changes in hardware requirements because the perceived cost of adding a few more features on your application is low. Compare that to say.. adding another register to your chip..which might add millions to the whole production process. The changes can be made while the app is live. You can not do that for hardware.
- analog31 13y agoI've seen the opposite, where the effort and bureaucracy to change the software is so prohibitive that changes are made to electronics or even mechanics to avoid a software change.
- 13y ago