3 ms·
> Specifically, it was not designed in the sense that megaprojects requiring planning and estimation are designed. Right. Some systems can't be designed that w
by jacques_chester 13y ago
> Specifically, it was not designed in the sense that megaprojects requiring planning and estimation are designed.
Right. Some systems can't be designed that way. But that doesn't mean that no system can be designed. And it doesn't mean that all systems are better off being designed or not-designed.
The reason megaprojects tend to be planned, controlled etc is because they haven't spontaneously emerged on their own. Somebody somewhere wishes to make a positive effort over and above the current baseline.
> I agree that some projects can be estimated. I'm saying a lot of them shouldn't be, because there are more effective ways to get results.
Agreed. A lot of the time a formal estimate isn't necessary. But a "lot of the time" is not the same as "always".
> An instructional contrast is the OSI protocol suite, a top-down alternative to the Internet. Now dead, of course.
There was a good history article on OSI in a recent IEEE or ACM magazine. The two major problems were an irreconcilable fight between circuit-oriented and packet-oriented designers (so they did both) and then lashings and lashings of vendor politics. The author of the piece argued that TCP/IP worked because it was driven by a small group of designers who just went ahead and cut code.
Generally the IETF model has worked because it's done by small groups focusing on a narrow problem in an environment of independent, interacting agents. Some systems work really well that way. Some don't.
> You can read more about that, and about the 3M example, in Mary Poppendieck's books. I think the specific one I have in mind Leading Lean Software Development.
I'll pick it up, thanks for the reference.