3 ms·
"What if I develop simple statistical models based on the number of squares that are already filled in?" Better to just have the experience to look at a Sudoku
by brudgers 13y ago
"What if I develop simple statistical models based on the number of squares that are already filled in?"
Better to just have the experience to look at a Sudoku and have a good feeling for how difficult it is - it's not just the number of filled in squares but their locations and their values.
After solving 1000's of Sudoku problems, experience will allow one to see the relevant patterns or rather have a feel for them when looking at a particular Sudoku. The process is sped up if one starts off estimating Sudoku solution times from day one and then compares those estimates to actual solution times.
A longer way to developing meaningful estimates (and I prefer meaningful over accurate, since a good estimate can still be very wrong), is to avoid estimating one's time as an end in itself.
- jacques_chester 13y ago> A longer way to developing meaningful estimates (and I prefer meaningful over accurate, since a good estimate can still be very wrong), is to avoid estimating one's time as an end in itself. Could you elaborate? What would one estimate on a book of sudoku problems?
- brudgers 13y agoWho is the audience for the estimate? An estimate of how long it will take me to solve 1000 Sudoku for recreation will not have much meaning to a client who just wants the solution. What are the resources that will be brought to the task? An estimate for solving 1000 Sudoku with a staff of professional programmers will be different from one premised upon bribing a dining hall full of seniors with coffee, juice and donuts down at the retirement village. What is the unit of estimation? Calendar days until delivery is different from man-hours because I spend so much time on HN. The value of an estimate is the integrity and relevance of the process by which it was generated not its accuracy. Accuracy is a fortunate side effect - and then only sometimes. The key is that accuracy correlates to experience at making estimates, and rationalizing the failure to go through the process because past estimates have been inaccurate is the long road I mentioned.