> PERT, eh? 1950s dies hard! Reading the research has been fascinating. There's a bunch of papers which show that it improves estimate accuracy; still other pa
by jacques_chester 13y ago
> PERT, eh? 1950s dies hard!
Reading the research has been fascinating. There's a bunch of papers which show that it improves estimate accuracy; still other papers where the problems with PERT are neatly highlighted (imagine the idea of a sub-critical path and wondering how many there might be).
One of my favourite facts about the classical PERT 3-point is that nobody has a good answer for why those particular formulae were chosen. They've simply passed into the literature as-is. Probably everyone looks, recognises something that approximates the normal distribution and mutters to themselves "yes, yes, I guess that's why".
Very silly, of course. Project outcomes don't resemble the normal distribution! So there's literature where this or that alternative formula is substituted for the originals. So I've made sure that part of the design is configurable.
> I would still ramp up the big-picture risk side. One benefit of that is that you could consider tieing in to an operational risk management system with onselling potential to client projects post-launch.
I'm hoping to keep it relatively narrowly focused, because there's the real risk of bloating by trying to invade multiple neighbouring problem domains too soon. Estimates have surface features in common with work breakdown structures, with quotes, with risk management ... you can get spread too thin too soon. I'm wary of that. I'm hoping to focus on making 3rd party integration as easy as possible instead.