The Manhattan Project was authorised because it could be shown that an atomic weapon was possible. Nobody had any idea how to build one or how it would work --
by jacques_chester 13y ago
The Manhattan Project was authorised because it could be shown that an atomic weapon was possible. Nobody had any idea how to build one or how it would work -- they just knew that a calculation based on runaway radioactive breakdown implied a large release of energy.
But how often are we doing a Manhattan Project, where research is a major initial output? Not very often at all. Throwing out estimation for all projects because some of them contain genuine, irreducible novelty is an example of the Nirvana Fallacy.
> But holistically speaking, in real software-centric systems, it happens: particularly when hardware, external system integration, some form of regulation, unique knowledge individuals, or any kind of third party are involved.
These are examples of uncertainty, not novelty. They exist in real non-software-centric systems too. The way you deal with them is to widen the ranges on your early estimates and then look for ways to reduce the uncertainty.
Edit for your edits:
> In the real world, people truck on anyway with relative confidence and frequently reform an informal estimate along the way.
Nothing about having a deliberate estimations process means "we will only do it once" (I suppose that's why you said it's a waterfall thing to do). In fact you should be re-estimating as you go to narrow the cone of uncertainty. One of the nice thing about agile methods is that this tends to be built into the overall loop.
> Perhaps with the 'agile' trend we're finally shifting beyond that.
Agile estimation works by frequently re-estimating. Traditional estimation works from size and then derives other measures. Agile holds other measures constant and then takes the integral of current velocity, which is ... size!
Even the word velocity correctly points out that both of these are two sides of the same bit of conceptual calculus.
> without wasting time hiring a project manager to estimate
Where did I suggest this? In software estimating the consensus is that the developers should be the ones who create estimates. They know the most about software development in this particular environment, after all.
- contingencies 13y agoAll fair enough. Perhaps what we can take from this constructively is that you could consider making the USP for your estimation tool more of a focus on uncertainty/overall project risk modelling more so than straight up timeframes, which we all know are pie-in-the-sky at the best of times and not really as critical as outright SPOFs/third party deps.
- jacques_chester 13y agoI'm taking the PERT 3-point estimation technique as my starting point (decompose the project, for each component, give best/likely/worst, roll up results with a formula). It bakes uncertainty and probabilities directly into the outcomes. I'd encourage users to look at estimating project size first and then deriving effort, schedule and cost. But I won't constrain them to it.
- contingencies 13y agoPERT, eh? 1950s dies hard! It's good to have a model though. I would still ramp up the big-picture risk side. One benefit of that is that you could consider tying in to an operational risk management system with onselling potential to client projects post-launch. I am looking right now but finding it hard to locate anything meaningful in this area, probably as it crosses many units of conventional businesses. Also, you may like https://github.com/mdaines/viz.js/ https://github.com/mdaines/viz.js/ which I recently found generates high quality SVG vectors from graphviz input in pure JS which you can make clickable/interactive and will print at any resolution: I'm using it in a cloud infrastructure management console, myself.
- jacques_chester 13y ago> PERT, eh? 1950s dies hard! Reading the research has been fascinating. There's a bunch of papers which show that it improves estimate accuracy; still other papers where the problems with PERT are neatly highlighted (imagine the idea of a sub-critical path and wondering how many there might be). One of my favourite facts about the classical PERT 3-point is that nobody has a good answer for why those particular formulae were chosen. They've simply passed into the literature as-is. Probably everyone looks, recognises something that approximates the normal distribution and mutters to themselves "yes, yes, I guess that's why". Very silly, of course. Project outcomes don't resemble the normal distribution! So there's literature where this or that alternative formula is substituted for the originals. So I've made sure that part of the design is configurable. > I would still ramp up the big-picture risk side. One benefit of that is that you could consider tieing in to an operational risk management system with onselling potential to client projects post-launch. I'm hoping to keep it relatively narrowly focused, because there's the real risk of bloating by trying to invade multiple neighbouring problem domains too soon. Estimates have surface features in common with work breakdown structures, with quotes, with risk management ... you can get spread too thin too soon. I'm wary of that. I'm hoping to focus on making 3rd party integration as easy as possible instead.