Perhaps you could try scaling estimation down, instead of up. For example, in the SEI's Personal Software Process you estimate very frequently. Like agile, it
by jacques_chester 13y ago
Perhaps you could try scaling estimation down, instead of up.
For example, in the SEI's Personal Software Process you estimate very frequently. Like agile, it works by attacking big problems in lots of small pieces. So instead of just doing the 4-6 whole-of-project estimates, you can also do estimates for stories, estimates for modules and so on.
The other thing to consider is re-estimating as you go. The Cone of Uncertainty demonstrates that as a project progresses, uncertainty about the problem and solution domains diminishes and so estimates can be made with tighter ranges.