Pathfinder was not all that expensive by space mission standards. The total budget was only about $200M or so, which was an order of magnitude less than typica
by lisper 13y ago
Pathfinder was not all that expensive by space mission standards. The total budget was only about $200M or so, which was an order of magnitude less than typical prior missions.
Also, while I was not personally involved in Pathfinder, I was in the research program that led up to it. We were doing things that had never been done before, including the first use of an off-the-shelf commercial operating system on a space vehicle. We were under tremendous time and budget pressure, and so was Pathfinder. The idea that an intermittent system reset could be written off as a hardware problem is entirely plausible.
- ErsatzVerkehr 13y agoA hardware problem is still a problem, though... Why would it be "written off"?
- lisper 13y agoBecause it would have appeared to be a problem with the test rig, not the flight hardware.