I don't really understand why it went down like that either. It was the lead/PMs first job with the company and mine too. He may have been concerned with losin
by gnarbarian 13y ago
I don't really understand why it went down like that either. It was the lead/PMs first job with the company and mine too. He may have been concerned with losing face or he wanted to finish the whole project super early and possibly get a bonus because it was fixed bid.
The requirements doc was extremely clear and robust. We felt confident that we were on the right track. Regardless I pestered him to schedule a meeting right away. After two weeks he relented but it took us another two weeks just to get in there due to people leaving at the state, general confusion over there and I assume them spending time rewriting the second deliverable.
There are a number of things we could have done to avoid the grief on our end.
1) We definitely should have made a greater effort to get in there as soon as we were done with the first deliverable.
2) we could have not burned ourselves out working 12s in the first place on salary and finished about at the right time when they were ready for us.
3) After finishing early we could have taken the equivalent time off instead of trying to power through the second deliverable. (not getting ahead of ourselves or burning us out)
We ultimately delivered the project within the time constraints of the estimate (a miracle considering we lost almost a month). although not including the OT we spent initially. So the client was happy but our team's morale never quite recovered.