I've picked up so many of these types of projects, it's sort of become my specialty. The first thing to do is to ask oneself if it's worth completing the proje
by ap22213 13y ago
I've picked up so many of these types of projects, it's sort of become my specialty.
The first thing to do is to ask oneself if it's worth completing the project at all. All stakeholders _will_ have to be ready to make some sacrifices; is it worth it? Also, like others have said, communication is key. If the team can't have open conversations up-front, it may be best to walk. But, if the team can communicate openly and most are on-board for an adventure, then there are things that are possible.
This is also where a team 're-org' may have to happen, unfortunately. At this point, there may be a huge amount of internal tension that's probably slowing things down. This is a very difficult task, but identify those who have become burned-out and/or antagonistic. Sometimes it's better to cut the team down from 5 to maybe 2-3 instead of adding more people. Is there a 2-3 person team that works most effectively together? The others who are 'cut' will have bad feelings about this. If possible (it usually is), get them on part-time contract and affirm that they are important to succeed (they probably are). Let them cool-off and slow down and mediate conversations with them to use their existing knowledge most effectively.
Don't think about the sunk costs. This will just depress you. Instead, think about all that you have (e.g. knowledge, code, documents, connections, relationships) as resources to help you get to a destination.
Redefine the destination. Take an honest inventory of your current state and distance to the destination. Where can you realistically get to, with a best effort? Which promises will have to be broken? Which ones must be kept. This is going to irk some people, so it's going to have to be very calculated. Sometimes this means just finding a way to get the ship to a close port, if only just to refuel.
If there isn't one, stand up an automated test harness with as many tests as possible, in the shortest period of time. If you can find a 3rd-party tool that's easy to set up, use it. But, you may have to write some throwaway code just to get something working. Don't worry if it takes a day or two to get going, it will be worth it. Shoot for broad tests, rather than unit tests, at first.
Divide and conquer; Isolate and build out from the solid parts. Which parts of the system can be hidden behind a black box interface and add value? Which parts of the system are so rotten that they have to be re-written? Slice the system up into pieces and remove the bad ones. Unfortunately, this requires a bit of skill, art, and talent. I most often deal with systems in OO languages. So, it's quite easy to apply a refactoring interface/factory pattern to things. The really rotten parts can even be replaced with mocks for the short-term, if an interface can be defined. Another thing: the Pareto principle. Re-write the 20% of the system that is creating the 80% complexity.
Aim for early, easy wins. Shrink the development cycle. Show some forward progress. That will help revitalize the team and add momentum.
The gut feeling for a lot of people in this type of situation is to 'brute force' it. People get addicted to 'putting out the fires' But, that's completely the wrong path to take. Come up with a new plan. A plan that can be done with everyone working 40 hour weeks. Let some of 'the fires' burn, but contain them. Don't lose hope, and instead use brains.
However, in the end, it is also completely ok to walk away, especially if there's no incentive to continue.
- levosmetalo 13y agoThe guy clearly said he is a developer. While your advice is sound, it is something that only the manager has authority and responsibility to do. It is just impossible it almost any organization that a developer can turn project and project methodologies upside down like suggested here. > However, in the end, it is also completely ok to walk away, especially if there's no incentive to continue.
- ap22213 13y agoI don't quite agree. I agree it can be difficult. But, if there's sufficient respect between the management and developers, then it's totally possible. The manager wants to succeed, and most are pretty reasonable to ideas, especially when put into a tight spot.
- levosmetalo 13y agoI agree that it's how it should be, but the author of the original question seemed pretty upset exactly because in this particular case it was not like that.
- nmcfarl 13y agoI disagree, and I've seen it done. In my case it was a very small org, with a very hands off manager. He cared about deadlines and deliverables - he didn't care at all about how things got done. Which mean you could change all of this, by winning over the team - and not missing deadlines worse than you were before....
- MartinCron 13y agoThere's an important distinction between management and leadership. Technical leadership can (and should) come from anyone.
- jdavid 13y agoAs a Developer, I would buy a book or pay for a class on a topic covering how do you improve team dynamics and strive for success. Most of my schooling and knowledge is from the perspective of building a 'thing' and it would be great to learn how to rebuild a team when management is lackluster. Out here in Silicon Valley there are a lot of inexperienced managers working on good or great products, and as an engineer you might recognize the problems, but not know how to help them, or nudge them in the right direction. It would be nice to learn from the experience of others rather than having to learn on your own each time. Maybe this is something to talk about at FAILCON?