There's a damning inspector general report on this, dating back to 2011: http://www.publications.parliament.uk/pa/cm201011/cmselect/cmpubacc/808/808.pdf http:/
by danso 14y ago
There's a damning inspector general report on this, dating back to 2011:
http://www.publications.parliament.uk/pa/cm201011/cmselect/cmpubacc/808/808.pdf http://www.publications.parliament.uk/pa/cm201011/cmselect/c...
Here's a key conclusion, along the themes of "this is what happens when the people with the money don't really understand what the developers are doing":
The BBC transferred too much financial risk to the contractor, Siemens, given
the level of technological innovation involved. This approach meant that that
BBC did not have a good enough understanding of the contractor’s design and
development work, and was unable to intervene effectively even when it knew
delivery was at risk. This resulted in a two year delay in securing the technology
for the Programme. We welcome the BBC’s commitment to consider more carefully
the appropriate degree of risk transfer for future contracts. It should have a close
understanding of the design and development approach being taken by a contractor
and should retain the ability to intervene without waiting for non-delivery or
contract termination.