Most dev estimates are inevitably expressed in ideal hours. Even assuming no potholes, you need to multiply that by a load factor to get an approximation of rea
by dreamfactory 13y ago
Most dev estimates are inevitably expressed in ideal hours. Even assuming no potholes, you need to multiply that by a load factor to get an approximation of real hours. Industry standard load factor is between 2-5x, typically around 3x when a team is up to speed. Therefore management need to multiply all estimates by 5 at the start of a project, ramping down to 3, and pray whilst adding some contractual contingency for the potholes.
The corollary of this is that a management KPI can be to reduce load factor down to around 2 - which becomes a concrete measure of their effectiveness at removing impediments. (And yes this means that increasing productivity is a management task and not a developer issue.)