My main client is an IT organisation who are trying to entrench Scrum as their method for all projects they handle; regardless of whether the projects are done
by jacques_chester 14y ago
My main client is an IT organisation who are trying to entrench Scrum as their method for all projects they handle; regardless of whether the projects are done with "internal resources" or by hiring freelancers like me.
To help them out, I've started quoting per-sprint. I take an underlying hourly rate, multiply it by the working hours, then give them the big scary amount. I mention the underlying hours I'll work and as of my last contract I've added an overage rate (to discourage fixed-cost shennanigans from creeping into a timeboxed method).
So far, so good.
One other nice thing: since I quote per-sprint, it makes it natural to invoice them per-sprint. That's fortnightly. Huzzah for better cash flow!
- lifeisstillgood 14y agoCould I just clarify (I like the invoice per sprint idea) Do you still contract to work say 40 hours per week (at say 100/hr or 8,000 per sprint). Or do you say I will complete the stories in the sprint ? I take it from the overage rate that you are prepared to say well, this is taking longer than I thought - so I am charging more. But does that not mean you cannot complete the work in 20 hours then go look for some more clients?
- jacques_chester 14y agoTheir billing process requires my invoices to show hours, so I still officially base it on that. 70 hours per sprint.
- lifeisstillgood 14y agoSorry for the late follow up but ... do you "get creative with the truth" on those 70 hours - or are you still just working for one client at a time, full time? if you do get creative - how do you feel about that?
- jacques_chester 14y agoIt says 70 hours, so I work those hours. If and when I can switch to a different unit of billing, I will. Per-hour basis is not without its flaws (the main one being that the last 2 hours are decreasingly productive).