Irelands big pull to these companies is to not tax them as much as other countries.
by stuaxo 3mo ago
Irelands big pull to these companies is to not tax them as much as other countries.
- dboreham 3mo agoThat said, once built and lit up, it's hard to move a data center to another country.
- deleted 3mo ago[deleted]
- dilyevsky 3mo agoLike 90%+ cost of a dc is actual computers which are pretty shippable
- jamesfinlayson 3mo agoYep, seen a data-centre move happen at work (from a distance - I wasn't effected). For a business with cross-data centre redundancy and no allowable down-time for core business, it was at least a year-long project I think. All for a data-centre in the same city.
- dilyevsky 3mo agoA year isnt very long considering sums involved here. At a certain hyperscaler a full dc build out took 2-3 years but we heard that aws did that in a year all in. And also musk proved you can do it literally over holiday break but you don’t have to go that extreme - just dont let cya pmcs do it