3 ms·
Can you give an example of a plant that has been built under this streamlined process and what kind of timeline it had? The only recent nuclear buildouts that
by devmor 4mo ago
Can you give an example of a plant that has been built under this streamlined process and what kind of timeline it had?
The only recent nuclear buildouts that I personally have knowledge of are expansions to existing plants and thus have a lower barrier to get going.
- lazide 4mo agoSince it was just released, that’s pretty hard to do eh? I’m familiar with the reactors built on other previous ‘expedited’ processes that ended up being anything but fast. We’ll see how it goes eh?
- devmor 4mo agoIf it was just released, then your claims about it are entirely hypothetical and best-case-scenario. Of course we have to "see how it goes" - there's no merit but hopefulness to your stance...
- mpweiher 4mo agoWe were talking specifically about the problem of a finished nuclear power plant, built successfully to the specifications in the build permit, not getting an operating license (or taking very long to get it). With the combined license, that case simply cannot happen, no matter what else happens.