You can't just spin up such a facility in a few days or weeks though, surely? Even if the core of a process is relatively simple physically, you still need all
by danparsonson 7mo ago
You can't just spin up such a facility in a few days or weeks though, surely? Even if the core of a process is relatively simple physically, you still need all the supporting infrastructure to make it happen.
- jiggawatts 7mo agoStarting from an empty lot, no, it would take nearly a year. However, any air (or gas) liquefaction / separation plant that is already making purified industrial gases from air or other sources could be adapted in a matter of weeks or at most a couple of months.