3 ms·
400K would go -fast- if they stuck to a traditional colo setup. Donations like this are rare and it may be all they get for a decade. Personally I would feel b
by lrvick 10mo ago
400K would go -fast- if they stuck to a traditional colo setup. Donations like this are rare and it may be all they get for a decade.
Personally I would feel better about round robin across multiple maintainer-home-hosted machines.
- pilif 10mo ago400k would last me 13 years for a rack, power and 10Gbit/s bandwidth at my colo place (Switzerland, traditionally high prices)
- dotancohen 10mo agoYes, but that's not their only expense.
- Craighead 10mo ago[dead]
- Aurornis 10mo agoYes, but that’s not the last or only donation they’re receiving either.
- LoganDark 10mo agoDon't bet on receiving money in the future.
- Aurornis 10mo agoIt's a community donation-supported project. That's kind of the whole deal. Regardless, the ongoing interest on $400K alone would be enough to pay colo fees.
- fragmede 10mo agoSince you've already done the math, what's the interest on $400k pay for the colo costs?
- serf 10mo agoat a (fairly modest) 3.3 its like 1100/month. I don't know what kind of rates are available to non-profits, but with 400k in hand you can find nicer rates than 3.3 (as of today, at least). that covers quite a few colo possibilities.
- throwaway2037 10mo agoUSD money market funds from Vanguard pay about 3.7% now. Personally, I would recommend a 50/50 split between a Bloomberg Agg bond ETF and a high-yield bond ETF. You can easily boost that yield by 100bps with a modest increase in risk. Another thing overlooked in this debate: Data center costs normally increase at the rate of inflation. This is not included in most estimates. That said, I still agree with the broad sentiment here: 400K USD is plenty of money to run a colo server for 10+ years from the risk-free interest rate.
- throwaway2037 10mo agoStupid question from me: What are their other costs? I'm a total newbie about data center colo setups, but as I understand, it includes: power and internet access with ingress and egress. Are you thinking their egress will be very high, thus thus need to pay additional bandwidth charges?
- Aurornis 10mo ago> 400K would go -fast- if they stuck to a traditional colo setup. I don’t know where you’re pricing coloration, but I could host a single server indefinitely from the interest alone on $400K at the (very nice) data centers I’ve used. Collocation is not that expensive. I’m not understanding how you think $400K would disappear “fast” unless you think it’s thousands of dollars per month?
- deleted 10mo ago[deleted]
- kube-system 10mo agoFor a server? The going rate for a 1/4 cabinet is $300-500/month.
- shrubble 10mo agoA full rack, 10 gigabits bandwidth and 1920W of power is available for as little as $800/month: https://1530swift.com/colocation.php https://1530swift.com/colocation.php Of course you have to buy the switches and servers…
- silisili 10mo agoFor reference, in the US at least, there was/is a company called Joes Data Center in KC who would colo a 1U for $30 or $40 a month. I'd used them for years before not needing it anymore, so not some fly by night company(despite the name). At that rate, that would buy you nearly 1000 years of hosting.
- Aurornis 10mo agoI was trying to avoid naming exact prices because it becomes argument fodder, but locally I can get good quality colo for $50/month and excellent quality coloration with high bandwidth and good interconnects for under $100 for 1U I really don’t know where the commenter above was getting the idea that $400K wouldn’t last very long
- esseph 10mo agoAlaska. Dollars per Mbit + reliable power in colo.
- stackghost 10mo agoJoe's got bought out by Patmos. The jury's still out on whether or not this is a good thing.
- esseph 10mo agoLove finding other metro area folks on hn!
- stackghost 10mo agoI'm actually Canadian, not a metro area person, just a happy customer
- esseph 10mo agoAh, well, it's a great spot. I walked around when Joe was building it from the ground up. Power, HVAC, and racks of wire shelving initially. So glad it grew into what it is now!
- arjie 10mo agoI, personally, have a cabinet in a colo. With $400k, I can host it at that datacentre with the income from risk-free return never exercising the capital with 10 GigE, 3 kW of power. If I can do it, they can do it. Modern computers are super efficient. A 9755 has 128 cores and you can get it for cheap. If you've been doing this for a while you'd have gotten the RAM for cheap too. If I, a normie, can have terabytes of RAM and hundreds of cores in a colo, I'm pretty sure they can unless they have some specific requests. And dude, I'm in the Bay Area. Think about that. I'm in one of the highest cost localities and I can do this. I bet there are Colorado or Washington DCs that are even cheaper.
- lrvick 10mo agoI to am in the bay area, and clearly I have been shopping at the wrong colos. I expected to find nothing with unlimited bandwidth for under $1k/mo given past experience with what may have been higher end DCs. In any event if I was the volunteer sysadmin that had to babysit the box, I would rather have it at my home with business fiber where I am on premises most of the time because getting in and out of a colo is always a whole thing if their security is worth a damn. Even given a frugal and accessible setup like that I can imagine 400k lasting 5 years tops especially if paying for the volunteers business fiber and much more especially given I expect some of it is to provide a sustainable compensation to key team members as well. Every cent will count.
- jeltz 10mo agoIf 100 years is fast, yes. You can get pretty sweet colo for 4k per year. I know cheaper places too.