1. North-south links in the UK are already fully utilised. There are more in works and plans but not sure it’s enough to meet even existing demand. 2. Transmis
by citrin_ru 11mo ago
1. North-south links in the UK are already fully utilised. There are more in works and plans but not sure it’s enough to meet even existing demand. 2. Transmission losses are substantial.
- amoshebb 11mo ago"About 1.7% of the electricity transferred over the transmission network is lost" https://publications.parliament.uk/pa/cm201415/cmselect/cmenergy/386/38607.html https://publications.parliament.uk/pa/cm201415/cmselect/cmen...
- chickenbig 11mo agoTransmission in this sense does not include distribution losses (by the DNOs, at lower voltages). 8% in your link. The UK government is now touting datacentre sites with better access to the national grid (transmission network) to avoid the issues inherent in the distribution networks. E.g. Culham which had a grid connection to power the JET fusion experiments.