The upfront depends on the project as well; some projects have less, some have more; depends on the size and the number of milestones. If you have, say, a proje
by tluyben2 14y ago
The upfront depends on the project as well; some projects have less, some have more; depends on the size and the number of milestones. If you have, say, a project of $10k with 4 milestones, I would never do a 30/70 payment. Rather 30/10/10/20/30 or something.
Also, you can use the popular agile approach which is popular; in that case you define stories per sprint (which in smaller projects are a week usually) and every monday morning you agree with the client upon the stories to be done that week. When you finished the last story, the client needs to pay the price for that week and go on with the next week. This keeps both sides alert and doesn't allow for slacking on both sides. It can go very wrong if you agree to too much, then you get the dark side of agile which means you'll be working every weekend 24 hours/day to make that monday morning.