About 20 years ago I was working in IT, and I was responsible for the physical build out (from a shell) of 599 North Mathilda, Sunnyvale - The foundations and o
by ghshephard 1y ago
About 20 years ago I was working in IT, and I was responsible for the physical build out (from a shell) of 599 North Mathilda, Sunnyvale - The foundations and outer walls/roof were up - but nothing inside.
I had responsibility (working with consultants who did this for a living) to work with the project manager, and architect/GC. All of the datacenters (back when companies put data-centers in their buildings), IDFs, MDFs. The MDF in particular was complex as it combined the floors IDF + the buildings MDF/telco connections, punchdowns, and a massive Nortel Option51c set of cabinets. We carefully laid out the room - measuring the minimal possible distance for cable techs to get in between the racks. Everything was designed down to the 1/4" in the room.
I showed up (mostly randomly) with a tape measure during construction - internal walls were up - and they were off by almost 14" - which would have made the internals almost unusable for their original purpose. They had to tear down their framing, pull everything out - thankfully before any electrics/racks/hvac had been put in place.
Having something like this would have greatly reduced that possibility. Bet they end up on every site (if they aren't already).
- jedberg 1y agoHah, I briefly worked in that building! Never dealt with the MDF/IDF though, was just doing software at that point.
- seemaze 1y agoUnfortunately not much has changed in 20 years
- Propelloni 1y agoCan confirm.
- b112 1y agoWas there ever a 'why' given? Did someone not take into account the width of the framing or something weird?