> (it's never included in the LCOE). Right, because that would change the definition of LCOE. And you are right that it's important, and there are other terms
by epistasis 1y ago
> (it's never included in the LCOE).
Right, because that would change the definition of LCOE. And you are right that it's important, and there are other terms to look for, as LACE, which EIA has been putting out for a long time. And Lazard's energy reports:
https://www.lazard.com/news-announcements/lazard-releases-2025-levelized-cost-of-energyplus-report-pr/ https://www.lazard.com/news-announcements/lazard-releases-20...
have an entire section on "Cost of firming intermittency" where it estimates costs based on each region of the US.
- buckle8017 1y agoThank you for this link. This is the first time I've seen serious discussion about "firming intermittent" power sources. I'm not sure I agree with the numbers from the various ISOs but it's still an excellent starting point.