They can’t build the gas plants (backlog to build them is ~5 years with GE and Siemens, and the costs are accelerating beyond reasonable commercial costs). At t
by toomuchtodo 2y ago
They can’t build the gas plants (backlog to build them is ~5 years with GE and Siemens, and the costs are accelerating beyond reasonable commercial costs). At the same time, ERCOT is projecting supply shortages both this year, and more so in future years due to demand growth.
Record May Peak Demand Coming Wednesday: Grid Roundup #57 - https://www.douglewin.com/p/record-may-peak-demand-coming-wednesday https://www.douglewin.com/p/record-may-peak-demand-coming-we... - May 12th, 2025 ("ERCOT is forecasting a peak of over 84 gigawatts which would shatter the previous May record of 77 gigawatts and even threaten the all-time demand record. ERCOT expects plenty of extra capacity despite large thermal power plant outages; solar power is expected to deliver well over 20 gigawatts. Should various anti-energy bills (SB 715/HB 3356, SB 388, SB 819) become law, these kinds of events would almost certainly create energy emergencies")
Energy groups scrap Texas-backed projects as costs rise - https://www.ft.com/content/19a52438-b529-43a8-9a83-b2d680f3d7e3 https://www.ft.com/content/19a52438-b529-43a8-9a83-b2d680f3d... | https://archive.today/lsKf9 https://archive.today/lsKf9 - May 12th, 2025
Texas Attempt to Kickstart New Gas-Fired Power Is Stumbling - https://www.bloomberg.com/news/articles/2025-04-05/texas-attempt-to-kickstart-new-gas-fired-power-is-stumbling https://www.bloomberg.com/news/articles/2025-04-05/texas-att... | https://archive.today/9jRPq https://archive.today/9jRPq - April 5th, 2025
Report on the Capacity, Demand and Reserves
(CDR) in the ERCOT Region, 2025-2029 - https://www.ercot.com/files/docs/2025/02/12/CapacityDemandandReservesReport_December2024.pdf https://www.ercot.com/files/docs/2025/02/12/CapacityDemandan... [pdf] - February 13th, 2025
- chneu 2y agoIsn't basically every major electricity infrastructure plan quite far behind schedule because of supply shortages? I remember reading that transformers, especially the larger kinds, are on a 3+ year backorder. Solar and wind farms are having to order all their parts like 5 years in advance cuz of it.
- toomuchtodo 2y agoNo, solar and batteries can be installed in 18-24 months, from groundbreaking to first kW to the grid. Transformers for transmission? Gas plants? Yes, supply chain issues, the former with ~1 year lead times, the latter with half decade lead times. https://www.eia.gov/todayinenergy/detail.php?id=64586 https://www.eia.gov/todayinenergy/detail.php?id=64586
- chneu 2y agohttps://www.utilitydive.com/news/electric-transformer-shortage-nrel-niac/738947/ https://www.utilitydive.com/news/electric-transformer-shorta... https://pv-magazine-usa.com/2024/03/07/a-look-at-the-great-transformer-shortage-affecting-u-s-utilities/ https://pv-magazine-usa.com/2024/03/07/a-look-at-the-great-t...
- toomuchtodo 2y agoI don’t disagree there are transformer shortages. I disagree these shortages make combustion fossil generation more favorable than renewables for new generation capacity. The generation technology is irrelevant as it relates to these transformer shortages you demonstrate. The gas generator backlogs (~5 years) I mention in my top comment are gas generator specific, due to their specific supply chain and labor needs.