You have to convince them that machinery is the critical path - and in a large organization it probably isn't. The bottle neck is probably elsewhere. Suppose t
by brudgers 14y ago
You have to convince them that machinery is the critical path - and in a large organization it probably isn't. The bottle neck is probably elsewhere.
Suppose team leaders meet once a day to review progress and assign workloads - that cancels out at least part of any two minute time gain (and perhaps all of it).
And the larger the organization, the less effect speeding up development may have - adding version 2.5 features to version 2.4 is only beneficial if marketing and product packaging can coordinate their collateral with the new scope AND there are additional new features in the pipeline which can support the release of version 2.5 - and doing that requires approval at increasingly higher levels of management.
Or to put it another way, faster machines may simply mean that the programmers have more time to surf the internet while requiring additional capital outlay. Not that that's the entire story - faster hardware is often an easy way to confer status more cheaply than a raise.
- greggman 14y agoHow does wasting 60 minutes in a meeting cancel out 2 minutes saved elsewhere? I'm not sure I follow that logic. You still got 2 more minutes of labor from that programmer than you would have otherwise.
- brudgers 14y agoWhere did sixty minutes come from? What happens in organizations is that progress is made in quantum steps, not continuously. As you go higher up in the organization, the quantum is a larger period of time and two minutes of programmer efficiency per day never moves the shipping date forward or changes the feature set. The only real tipping point from a management perspective is if the improved efficiency eliminates a full time employee.
- greggman 14y agoSorry, 60 minutes was my personal thinking of "programmers attend a meeting". I'm still not sure I see your point. You can pay programmers $1-$2 a minute to do nothing or you can pay them to do something you need done. If you get them a slow machine such that 10-30 minutes a day they are sitting around waiting for a compile, link, or other long build step you're paying them to sit around. Seems like a waste of money. If you can reduce that 10-30 minutes day just a few minutes (say 8 to 24 mintes a day) at least some of those minutes you're already paying for are actually going toward what you want them to go toward (work)