We need time estimates so we can have an idea of what something will cost. If the estimate is too high, maybe we don't have time to build X, but we can can buil
by HeyLaughingBoy 14y ago
We need time estimates so we can have an idea of what something will cost. If the estimate is too high, maybe we don't have time to build X, but we can can build Y instead because it takes less time.
Planning with no idea of how long something will take is higher risk. If your estimate is that it will take a week, I'll be OK. If you estimate 4 months, I worry because a lot more can go wrong in that 4 months, so now I have to think about contingencies for handling those problems.
My first job out of college did not estimate anything as far as I could see. We started projects, and they were done when they were done. If they took too long, we'd put them on hold and do something else. Of course, it meant that we couldn't do any advance marketing or pre-sales, because no one knew when project X was scheduled to be ready, so we probably lost a lot of sales. But there was no sales estimates, so no one knew that either...