I've been estimating my time as a designer in the AEC industry since my first job more than 20 years ago. The only reason I did was because Greg, the VP of Eng
by brudgers 14y ago
I've been estimating my time as a designer in the AEC industry since my first job more than 20 years ago.
The only reason I did was because Greg, the VP of Engineering, said doing so was the only way I would get better at it. And the only reason I got better at it was because I've tracked my actual time against my estimates on many occasions over the years and been burned by bad assumptions from time to time.
At this point I have a process which produces a fairly accurate range of "billable time" based upon an important recognition: a list of tasks with assigned times doesn't account for flow nor does it account for the efficiency experience brings when dealing with "known unknowns." My first estimates tend to be wildly pessimistic (the opposite of what the author observes in the estimates of others).
On the other hand, one of the ways I evaluate my initial task list with assigned time estimates is by chunking the work into half days, because I've found half-days to be highly accurate across a variety of project sizes...at one point all my proposals were written as $xxx.xx/half day.
One of the useful features of the half day is that it is vague. Maybe it's three hours and I can go for a walk, maybe it's five and I'm at the computer a little longer. Either way, it doesn't have much impact on my day or productivity.
Another useful feature is that it allows chunking multiple small tasks together intuitively.
> (equal half-day (add-hours .25 1.0 .25 .5 .75))
T
> (equal half-day (add-hours 1.25 1.0 .25 1.5 .75))
T
But the half day doesn't try to force the unrealistic optimism of large time spans downward - what does it mean to estimate something will take a week? Billable time does not translate directly into calendar time because of flow and the productive use of procrastination.
In other words, a forty hour project doesn't mean I will be done in a week (unless the work is entirely rote, and in that case I am probably going to be too expensive anyway). From start to end, a forty hour project probably takes at least two months - which is about the same amount of calendar time an 80 or 120 hour project might take - because a 40 hour project tends to have a higher proportion of creative time (in my case design) than a relatively larger project.