I was only involved in government contracting for a bit in the twenty-ought tens, but the whole bit about silly requirements and by picking the lowest bidder yo
by IX-103 2y ago
I was only involved in government contracting for a bit in the twenty-ought tens, but the whole bit about silly requirements and by picking the lowest bidder you were selecting the contributor that "often is the one who understands the technology least" gives me flashbacks to my time in government contracting.
I wasn't around for the whole JTRS fiasco, but from what I heard this effect played out there as well. Ridiculous requirements such as requiring only software updates to support new waveforms and restrictions on SWaP as well as unrealistic network sizes resulted in radios so expensive they couldn't be widely deployed. I know some people like to point to SRW as a success coming out of that, but it never has been successfully deployed to within an order of magnitude of the number of radios in the requirements and resulted in a third, incompatible, radio system used by infantry. Meanwhile, a company that was excluded from the program built the radio that the military actually needed, which could communicate to both of their existing systems.
I was around for it's successor where they swapped software for FPGAs and made the same "software only" update requirement. The primary winner of the contract had no experience in digital logic and decided to implement the thing in MatLab (which provided no real mechanism for multiple clock domains or other features needed for high performance large scale digital design). Other contractors had to fit their design into this mess of a system. When it didn't fit in any FPGA, they opted to put it in an ASIC. And another of the contractors managed to convince the PM that their newest dev board was perfect for integrating this -- allowing them to pay for the internal R&D for that board on the project's expense (after all PCIE and SRIO are practically the same, right?).
I left at that point because failure was the only option and I could make more money writing code to meet silly requirements in the tech sector.
- hinkley 2y agoThe lowest bidder thing has always upset me. Either they are delusional or they are lying. If they understand the domain, they are going to sell you a system they built for someone else. Or they think the system they build for you can be resold to someone with deeper pockets. In which case they will push and push for you not to make it too niche. Sometimes prebuilt is exactly what you need, but only sometimes, and that’s not what you paid for.
- jazzyjackson 2y agoThe term is Lowest Price Technically Acceptable, gov't ought to be pickier (/have more domain knowledge) with what is acceptable.
- hinkley 2y agoOnce upon a time I knew a guy who claimed to know people who took the second lowest bid, figuring the lowest build was full-on crank and the second was only slightly unhinged. I didn't know that guy long enough to find out how that worked out for his friend long-term.
- IX-103 2y agoThe PMs only have a 3-5 year term. They can't be taken from the companies that bid due to conflicts of interest, so they rarely are in charge of an area they have expertise in. How long would it take you to get enough technical domain knowledge in a new field to actually see through a professional PowerPointer that's polished their technological turd for decades? There's supposed to be a set of contractors that the PM refers to for technical advice that also provide continuity over longer terms, but the pay is not really competitive (due to budget cuts) so there's more churn and less talent than there used to be.
- V_Terranova_Jr 2y agoI'm sorry, but this is basically incorrect on every point other than the limited tenure. Source: I work in this sector. PMs often come directly from industry. Once they do, there is a period over which they are not allowed to make direct decisions that affect their previous company, but the previous company is free to bid on that PM's programs and speak with that PM. When these conflict of interest situations arise, the office appoints a delegate PM to make decisions associated with that company. There are absolutely varying qualities of PM, but the majority of them would be considered a domain expert or subject matter expert in some technical area. Standard practice is for a new DARPA PM to inherit existing programs that are already executing as the old PM finishes their tenure. When a PM leaves, the office tries to hand the executing programs to a new PM who knows something about that field (or is an expert). That doesn't always happen, for various reasons, but they do try to do it that way. There is a large contractor staff that does a lot of heavy lifting on both technical and programmatic fronts. The PM is the decision-maker, but the contractor staff are integral. These contractor jobs can pay quite well for senior staff or technical experts. Maybe not FAMANG software developer salaries, but particularly for topics in the physical domain, the salaries can be significantly higher than the equivalent role in industry.