The idea of running extra load - it sounds good in theory but I can't help thinking that it's a bit like setting your watch forwards to try and stop being late
by brc 14y ago
The idea of running extra load - it sounds good in theory but I can't help thinking that it's a bit like setting your watch forwards to try and stop being late for things. Eventually you know your watch is 5 minutes fast so start compensating for it. I wonder if this strategy starts to have the same effect - putting fixes off because you know you can pull the extra load before it becomes critical. In the same way you leave for the train a couple of minutes later because you know your watch is actually running fast.
- dools 14y agoit sounds good in theory Don't you mean "it sounds good in practice"? This entire post is about practical experience. I don't think this is like setting your watch forward 5 mins. I think it's more like RAID. When you get a warning that one of your drives has died, you know you have to get in and replace it. Depending on how critical the machine is, the cost of getting to the data centre etc. you might leave now, in the middle of the night and drive like a bat out of hell, or you might leave it til next week when you'll be in there anyway. Either way you know your risk just went up a hell of a lot. Depending on how risk averse you are, you will act accordingly.
- joshma 14y agoIt's not exactly the same, though. If you're late 5 minutes by your watch you're on time naturally, without any action. If you're "overloaded" on your servers, you at least have to consciously decrease the extra load or risk having real consequences.
- apu 14y agoI actually purposely used to set all the various clocks at home ahead by anywhere from 0 - 15 minutes. At first, I could remember which ones were ahead by how much, but then soon I started to forgot and had to just assume they were running at the right time. It worked great. After a few years of this, I set them all back to right time and found that I had trained myself to just leave at the right time, with no more trickery needed.
- inerte 14y agoI only have one alarm. If it fails I am late. I found out that depending on complex systems work against you. Once I had three wake up alarms, at different points at the bedroom. Didn't work. Being late is lame. Suffering its consequences is the best teacher one can have.
- chipsy 14y agoWere you the college roommate I had who suspended the alarm on a string over the bed so that standing was required to turn it off?
- pestaa 14y agoI saw an alarm that had a propeller on top of it. The clock made it fly and you had to hunt it down (even if it falls behind the furniture) to shut the alarm.
- andrewflnr 14y agoI've heard of alarms on wheels that run away from you but that takes the cake.
- Game_Ender 14y agoThis is just an adaption of the "margin" system commonly used in systems engineering. Basically you never spec everything out to perfectly match the load it's expected to bare, always leave some headroom. For example if you are designing an aircraft your first design is never perfect. So you when you do the initial design, you do it as if the aircraft has to weight 70% of what it really will. As errors are corrected in your original design (or features creep in) you will slowly eat away at that 30% margin. Hopefully by the time you finish the have some left, or the aircraft will never get off the ground.
- peterwwillis 14y agoCan you imagine if they loaded 1000lbs of lead onto an airplane before they took off, just to see if the plane takes off with the headroom filled? "Oh crap, the plane is falling, let's dump the lead." OP's "extra reads" is dumb because he could have had normal metrics for memcached load and planned to only support like 70% capacity or somesuch, and when load hit that number, he would immediately increase capacity. Instead he's running with a handicap. It's just useless.
- eranki 14y agoIt's actually more like dumping fuel for an emergency landing instead of dumping passengers, if we really insist on using completely irrelevant analogies.
- peterwwillis 14y agoAre planes in the habit of carrying much more fuel than they need, just in case they will weigh too much when landing, in which case they dump the fuel? No. In the inverse example, we don't put extra load on servers in anticipation that load goes up, just so we can dump the extra load and put it back to where it would have been had we not had extra load. The idea is moronic. It is literally the same as putting lead in your servers until you have to dump it, just because you can. Real admins have alerts on their servers to tell them when they will need additional capacity. Incidentally, fuel dump systems were initially added due to a rule by the FAA that a plane's structural landing weight not be exceeded by its takeoff weight. Many commercial planes never had this problem, so dumping systems were not installed. As a result, most planes just circle until they've burned up enough fuel, or land anyway overweight. You could dump fuel to lessen the chance of explosion, but only if your plane is equipped with a fuel dump system, and such incidents are so rare it's not even a safety consideration.
- deleted 14y ago[deleted]
- jaylevitt 14y agoI think (I assume) his point was that when you have a complex system that's growing rapidly, it's difficult to predict what the next breaking point will be. Building in extra load gives you a window of opportunity: You discover the breaking point, turn off the extra load, re-engineer, and turn back on the canary so you can find the next breaking point. In theory, you'd think you can do load-testing and simulations and capacity planning, and find these breaking points ahead of time. In practice, it's not always feasible, and this seems like a simple-enough hack that gets you much of the way there.