First, capacity factor is a silly metric to use for this. The industry uses LCOE or system LCOE, because this is about dollars per actual TWh produced, not capa
by atwrk 2y ago
First, capacity factor is a silly metric to use for this. The industry uses LCOE or system LCOE, because this is about dollars per actual TWh produced, not capacity. In other words: A capacity factor of 10% doesn't matter if building 10x the amount is still cheaper.
With that said, the wind capacity factor in Germany is 20% for onshore and 40% for offshore, so even that was wrong by a factor of 2-4.