"Easy estimate does the rocket-sciencey math of your project's ETA based on the current work trends (project velocity) for the project." How does that work exa
by _joel 2y ago
"Easy estimate does the rocket-sciencey math of your project's ETA based on the current work trends (project velocity) for the project."
How does that work exactly, some more detail than handwavey "it's magic" would probably gain more traction with this audience.
- vijaysutrave 2y agoThat is just some fancy wording I went with, it looks at the past velocity (work completed / time taken) on the project to compute the total time required to complete the remaining work. Basic math tbh, but can get "rocket-sciencey" when story points, epics, dates are involved (at least for me lol).