3 ms·
It’s not just the software, it’s the hardware too. Too many companies got good at speeding up VM deployments but ignored theory of constraints and still had a
by coredog64 2y ago
It’s not just the software, it’s the hardware too. Too many companies got good at speeding up VM deployments but ignored theory of constraints and still had a 4-6 month hardware procurement process that gave everyone and their dog veto power.
And then you come to companies that managed to streamline both and ran out of floor space in their data center because they had to hold onto assets for 3-5 years. At one previous employer, the smallest orderable unit of compute was a 44U rack. They eventually filled the primary data center and then it took them 2 years to Tetris their way out of it.