3 ms·
I'm trying to find recent Time Lapse videos - here is one from Australia, 2020 - at the time the largest in Western Australia - so at scale. All the panels we
by ghshephard 2y ago
I'm trying to find recent Time Lapse videos - here is one from Australia, 2020 - at the time the largest in Western Australia - so at scale. All the panels were hand lifted by one person. https://www.youtube.com/watch?v=uCtFG-hIHdM https://www.youtube.com/watch?v=uCtFG-hIHdM
Ahh - better - here is one at scale from a year ago.
https://www.youtube.com/watch?v=72UlzbsON4M https://www.youtube.com/watch?v=72UlzbsON4M
West Texas:
- 200 MW
- 1200 Acres
- Piles -- 68,350
- Support Piles (Crew does 80-100 piles/day)
- Tracker System
- 490,150 Solar Modules
- 540 watts/module
- Crew can install 500 panels a day
- These are multi person 2-4 people lifting.
- 500 workers on site - doing 6200 panels/day.
- (That suggests ~40 person crews if all worker installing
panels. Wow - now I see why this is a big deal)
- Cables panels -> Inverters
- Big Inverter install to to convert to AC
- Lots of concrete pouring for substation/Inverter Pad.